ML22020A07118 January 2022Scott Wall
NRC/NRR/DORL/LPL3
NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Proposed Alternative VR-12Acceptance Review
ML22089A24530 March 2022Scott Wall
NRC/NRR/DORL/LPL3
NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Request VR-12RAI
L-22-110, Response to Request for Additional Information Re 10CFR50.55a Request Number VR-12, Revision 0, Request for Relief from Containment Isolation Valve ASME OM Code Requirement28 April 2022Penfield R
Energy Harbor Nuclear Corp
Response to Request for Additional Information Re 10CFR50.55a Request Number VR-12, Revision 0, Request for Relief from Containment Isolation Valve ASME OM Code RequirementResponse to RAI
L-22-104, Annual Radiological Environmental Operating Report28 April 2022Penfield R
Energy Harbor Nuclear Corp
Annual Radiological Environmental Operating ReportRequest
ML22187A25912 July 2022Nancy Salgado
NRC/NRR/DORL/LPL3
Issuance of Relief Proposed Alternative Request Vr 12, Revision 0, Associated with the Fourth 10-Year Inservice Testing IntervalApproval