ML21257A41922 February 2021
14 September 2021
Request for Licensing Amendment Regarding Transition to GNF3 FuelRequest
ML21257A42014 September 2021Exelon
Simpson P
Request for Licensing Amendment Regarding Transition to GNF3 FuelRequest
ML21294A00326 October 2021Booma Venkataraman
Plant Licensing Branch III
Supplemental Information Needed for Acceptance of Requested Licensing Action License Amendment Request Regarding Transition to GNF3 FuelAcceptance Review
RS-21-113, Response to Supplemental Request for Information Related to Request for Licensing Amendment Regarding Transition to GNF3 Fuel3 November 2021Exelon
Simpson P
Response to Supplemental Request for Information Related to Request for Licensing Amendment Regarding Transition to GNF3 FuelRequest
ML21312A5618 November 2021Booma Venkataraman
Plant Licensing Branch III
Acceptance Review: Quad Cities, Units 1 and 2 - License Amendment Request Regarding Transition to GNF3 FuelAcceptance Review
ML21301A22010 November 2021Booma Venkataraman
Plant Licensing Branch III
Request for Withholding Information from Public Disclosure for Quad Cities Nuclear Power Station, Units 1 and 2 License Amendment Request Regarding Transition to GNF3 FuelWithholding Request Acceptance
ML21301A22610 November 2021Request for Withholding Information from Public Disclosure for Quad Cities Nuclear Power Station, Units 1 and 2 License Amendment Request Regarding Transition to GNF3 FuelRequest
ML21301A21910 November 2021Booma Venkataraman
Plant Licensing Branch III
Request for Withholding Information from Public Disclosure for Quad Cities Nuclear Power Station, Units 1 and 2 License Amendment Request Regarding Transition to GNF3 FuelWithholding Request Acceptance
ML21342A3848 December 2021Booma Venkataraman
NRC/NRR/DORL/LPL3
NRR E-mail Capture - Request for Additional Information: Quad Cities 1 & 2 License Amendment Request Transition to GNF3 FuelRAI
ML21347A00120 December 2021Booma Venkataraman
Plant Licensing Branch III
Audit Plan to Support the Review of NEDC-33930p, Revision 0, Gexl98 Correlation for Atrium 10xm Fuel Included in the License Amendment Request Regarding Transition to Gnf3 FuelOther
ML22032A1253 February 2022Booma Venkataraman
Plant Licensing Branch III
Audit Plan to Support the Review of Licensees Information Related to Equipment Qualification License Amendment Request for Transition to Gnf3 FuelOther
ML22076A11215 March 2022Robert Kuntz
Plant Licensing Branch III
Request for Additional Information Related to the Amendment Request to Transition to GNF3 Fuels (EPID L-2021-LLA-0159) (Redacted)RAI
ML22098A0834 May 2022Robert Kuntz
Plant Licensing Branch III
Regulatory Audit Report Regarding License Amendment Request to Transition to Gnf3 FuelOther
ML22165A27516 June 2022Booma Venkataraman
Plant Licensing Branch III
Audit Plan to Support the Review of Exelon Calculation for Dispersion Factors Included in the License Amendment Request Regarding Transition to Gnf3 FuelOther
ML22214A0042 August 2022Robert Kuntz
Plant Licensing Branch III
Audit Plan to Support the Review of Amendments to Revise Criticality Safety Analysis Methodologies (Epids L-2022-LLA-0085, L-2021-LLA-0124, and L-2021-LLA-0159)Other
ML22229A0307 September 2022Robert Kuntz
Plant Licensing Branch III
Regulatory Audit Report Regarding License Amendment Request to Transition to GNF3 FuelOther
ML22300A2533 November 2022Robert Kuntz
NRC/NRR/DORL/LPL3
Regulatory Audit Report to Support the Review of Amendments to Revise Criticality Safety Analysis Methodologies (Epids L-2022-LLA-0085, L-2021-LLA-0124, and L-2021-LLA-0159)Approval
ML22298A00215 December 2022Robert Kuntz
Plant Licensing Branch III
Issuance of Amendment Nos. 293 and 289 Transition to GNF3 Fuel (EPID L-2021-LLA-0159) (Public)Approval