Issue date | From | Title | Project stage | |
---|---|---|---|---|
ML20085H900 | 25 March 2020 | Exelon David Gudger | R. E. Ginna Nuclear Power Plant, License Amendment Request for Implementation of WCAP-14333 and WCAP-15376, Reactor Trip System Instrumentation and Engineered Safety Feature Actuation System Instrumentation Test Times and Completion Times | Request |
ML20106F248 | 15 April 2020 | V Sreenivas NRC/NRR/DORL/LPL1 | Acceptance Review: R. E. Ginna Nuclear Power Plant to Implement WCAP, TSTF-411, and TSTF-418 | Acceptance Review |
ML20218A642 | 5 August 2020 | V Sreenivas NRC/NRR/DORL/LPL1 | R. E. Ginna Nuclear Power Plant - Request for Additional Information (RAI) for LAR to Implement WCAP, TSTF-411, and TSTF-418 | RAI |
ML20248H388 | 4 September 2020 | Exelon David Gudger | Response to Request for Additional Information - License Amendment Request for Implementation of WCAP-14333 and WCAP-15376, Reactor Trip System Instrumentation and Engineered Safety Feature Actuation System. | Response to RAI |
ML20353A126 | 11 March 2021 | V Sreenivas Plant Licensing Branch I | R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 144 Implementation of WCAP-14333 and WCAP-15376, TSTF-411-A, and TSTF-418-A to Revise Reactor Trip and Engineered Safety Feature Actuation System Instrumentation | Approval |