ML18058A090 | 28 February 2018 | NRC/NRO/DNRL/LB4 Paul Kallan | LAR-17-023 Audit Plan | Request |
ND-18-0302, Supplement to Request for License Amendment and Exemption Regarding Improvements to Main Control Room (MCR) Post-Accident Radiological Consequences (LAR-17-023S2) | 8 March 2018 | Southern Nuclear Whitley B | Supplement to Request for License Amendment and Exemption Regarding Improvements to Main Control Room (MCR) Post-Accident Radiological Consequences (LAR-17-023S2) | Supplement |
ML18072A318 | 3 April 2018 | NRC/NRO/DNRL/LB4 Paul Kallan | Audit Report for Vogtle Electric Generating Plant, Units 3 and 4 LAR-17-023 | Request |
ML18085A628 | 20 April 2018 | NRC/NRO/DNRL/LB4 Paul Kallan | Safety Evaluation - Vogtle Electric Generating Plant, Unit 3 and 4 LAR 17-023 | Approval |
ML18085A627 | 20 April 2018 | NRC/NRO/DNRL/LB4 Paul Kallan | Attachment - Vogtle Electric Generating Plant Unit 4 (LAR-17-023) | Acceptance Review |
ML18085A626 | 20 April 2018 | NRC/NRO/DNRL/LB4 Paul Kallan | Amendment -Vogtle Electric Generating Plant, Unit 4 LAR 17-023 | Other |
ML18085A625 | 20 April 2018 | NRC/NRO/DNRL/LB4 Paul Kallan | Attachment - Vogtle Electric Generating Plant Unit 3 (LAR-17-023) | Acceptance Review |
ML18085A624 | 20 April 2018 | NRC/NRO/DNRL/LB4 Paul Kallan | Amendment - Vogtle Electric Generating Plant, Unit 3 LAR 17-023 | Other |
ML18085A623 | 20 April 2018 | NRC/NRO/DNRL/LB4 Paul Kallan | Exemption - Vogtle Electric Generating Plant, Unit 4 LAR 17-023 | Other |
ML18085A622 | 20 April 2018 | NRC/NRO/DNRL/LB4 Paul Kallan | Exemption - Vogtle Electric Generating Plant, Unit 3 LAR 17-023 | Other |
ML18085A621 | 20 April 2018 | NRC/NRO/DNRL/LB4 Paul Kallan | Cover Letter - Vogtle Electric Generating Plant, Units 3 and 4 - LAR 17-023 | Other |