 Issue dateTitleTopic
ML17283A10928 September 2017Northwest Medical Isotopes, LLC Response to U.S. Nuclear Regulatory Commission Request for Additional Information Regarding Application for Construction Permit (TAC No. MF6138), Docket No. 50-609, Dated September 18, 2017Earthquake
ML17265A04619 September 2017Northwest Medical Isotopes, LLC Response to U.S. Nuclear Regulatory Commission Request for Additional Information Regarding Application for Construction Permit
ML17265A04719 September 2017Response to the U.S. Nuclear Regulatory Commission, Northwest Medical Isotopes, LLC - Request for Additional Information Regarding Preliminary Safety Analysis Report, Construction Permit ApplicationEarthquake
ML17265A04818 September 2017Responses to Advisory Committee on Reactor Safeguard Questions on Docket No. 50-609, Northwest Medical Isotopes, LLC, NWMI-2013-021, Construction Permit Application/Or Radioisotope Production, at Meetings on June 19, 2017; July 11, 2017; &Safe Shutdown
Fukushima Dai-Ichi
Earthquake
ML17128A06728 April 2017NWMI-2017-RAI-002, Rev. 0, Response to the U.S. Nuclear Regulatory Commission Northwest Medical Isotopes, LLC - Request for Additional Information Regarding Application for Construction Permit (TAC MF6138).Safe Shutdown
ML17128A06628 April 2017Northwest Medical Isotopes, LLC Response to the NRC Regarding the Request for Additional Information Regarding Application for Construction Permit (Letter Dated March 29, 2017)
ML17128A06528 April 2017Northwest Medical Isotopes, LLC Responses to the NRC Environmental Request for Additional Information - Letter Dated January 25, 2017
ML17093A6616 March 2017Northwest Medical Isotopes, LLC Responses to the U.S. Nuclear Regulatory Commission Environmental Request for Additional Information - Letter Dated January 25, 2017
ML16344A05328 November 2016Northwest Medical Isotopes, LLC - Response to the U.S. Nuclear Regulatory Commission Request for Additional Information Regarding the Preliminary Safety Analysis Report and Environmental ReviewSafe Shutdown
Safe Shutdown Earthquake
Operating Basis Earthquake
Tornado Generated Missile
Design basis earthquake
Earthquake
ML16270A3771 September 2016Northwest Medical Isotopes, LLC, Response to Environmental Request for Additional Information - Additional Clarification on POSA3-1A, POSA3-2A, POSA3-3A, NOI3-IB, and PA3-1
ML16210A30518 July 2016Northwest Medical Isotopes, LLC, Response to Request for Additional Information Regarding Chapters 4, 13, and 19 of the Preliminary Safety Analysis Report and Environmental Review
ML16124A51026 May 2016Summary of Telephone Conference Call Held on April 21, 2016, Between the U.S. Nuclear Regulatory Commission and Northwest Medical Isotopes, LLC Concerning Clarifications on Responses to Request for Additional Information for the Environment
ML16123A11925 April 2016Northwest Medical Isotopes, LLC - Responses to the NRC Environmental Request for Additional Information - Letter Dated March 28, 2016
ML16053A20412 February 2016Northwest Medical Isotopes, LLC - Responses to the U.S. Nuclear Regulatory Commission Environmental Request for Additional Information - Letter Dated January 19, 2016
ML15328A07120 November 2015Northwest Medical Isotopes, LLC - Response to the U.S. Nuclear Regulatory Commission Request for Additional Information, Environmental Review of the Construction Permit Application, Including Document No. NWMI-2015-RAI-001. Part 1 of 14
ML15328A07020 November 2015Northwest Medical Isotopes, LLC - Responses to the U.S. Nuclear Regulatory Commission Environmental Request for Additional Information - Letter Dated November 2, 2015