EPID:L-2023-LRM-01064 January 2024Open
EPID:L-2023-LLE-001810 August 2023Open
EPID:L-2023-LLA-007525 May 2023OpenITAAC Closure Verification Evaluation Form (Vef) for ITAAC Number 2.3.02.08a.i (Index No. 301) for Vogtle Unit 4 Combined License (VOG4)
EPID:L-2023-LLA-00611 May 2023OpenLicense Amendment Request to Revise Technical Specification Surveillance Requirement 3.4.14.1 and Proposed Inservice Testing Alternative ALT-VR-02
EPID:L-2023-LLR-001612 April 2023OpenGEN-ISI-ALT-2023-01, Request to Use Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI
EPID:L-2023-NFO-00023 April 2023Open
EPID:L-2023-LLA-004324 March 2023OpenRequest for License Amendment: Relocation of TS 3.7.9, Spent Fuel Pool Makeup Water Sources (LAR-23-003)
EPID:L-2023-LLA-00023 March 2023Open
EPID:L-2023-LLA-005028 November 2022OpenSummary of December 8, 2022, Public Meeting with Southern Nuclear Operating Company
EPID:L-2022-LRM-00948 November 2022OpenSouthern Nuclear Pre-Submittal Meeting on December 1, 2022 - Vogtle SR 3.4.14.1 LAR and Alternative Relief Request 1
EPID:L-2022-LLR-00794 November 2022OpenITAAC Closure Verification Evaluation Form (Vef) for ITAAC Number 2.6.01.02.i (Index No. 579) for Vogtle Unit 4 Combined License (VOG4)
EPID:L-2022-LLA-014814 October 2022OpenTSTF-95
TSTF-241
TSTF-290
TSTF-99
EPID:L-2022-LRM-006730 August 2022Open
EPID:L-2022-LLA-00961 August 2022OpenTSTF-490
EPID:L-2022-LLR-005329 June 2022OpenResponse to March 12, 2012, Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(1) Regarding Recommendations 2.1, 2.3, and 9.3, of the Near-Term Task Force Review.
EPID:L-2022-LLL-00108 June 2022OpenRequest for One-Time Exception to LIC-109, LIC-101, and LIC-500 Acceptance Review Criteria for Accident Tolerant Fuel Lead Test Assemblies License Amendment Request and Exemptions
EPID:202316 May 2022Open(TMl-2) - License Amendment Request - Three Mile Island, Unit 2, Decommissioning Technical Specifications, Response to Questions
EPID:L-2022-LRM-00334 May 2022OpenTSTF-490
EPID:L-2022-NFO-000211 April 2022Open
EPID:L-2022-LRO-001223 February 2022Open
EPID:L-2022-LRM-000327 January 2022Open
EPID:L-2021-LRM-010815 October 2021OpenPre-Submittal Meeting Regarding Proposed Revision to Technical Specification (TS) 5.5.16 for Farley Nuclear Plant (Farley), Units 1 and 2; and Vogtle Electric Generating Plant (Vogtle), Units 1 and 2
EPID:L-2021-LRM-008412 August 2021Open
EPID:L-2021-LRM-007323 July 2021OpenSlides - SNC Slides - Pre-Submittal Meeting on August 13, 2021 - Vogtle TS 3.3.1 and 3.3.2 LAR
EPID:L-2021-LLE-00348 July 2021OpenLate Filed Allegations (Lfa) Process
EPID:L-2021-LRM-00599 June 2021OpenTSTF-490
EPID:L-2021-LLQ-00027 May 2021OpenQuality Assurance Topical Report, Reduction in Commitment (Pandemic Related)
EPID:L-2021-LRM-00476 May 2021Open
EPID:L-2021-LRM-002824 March 2021OpenNotice of Meeting with Southern Nuclear Operating Company (SNC) Regarding a Proposed Quality Assurance (QA) Licensing Action for the SNC Fleet
EPID:L-2021-LRM-002619 February 2021Open
EPID:L-2021-LRM-00115 February 2021Open
EPID:L-2021-LRM-00048 January 2021OpenFixed 8-Hour Emergency Light Deviation Pre-Submittal Meeting, February 2021 (Slides)
EPID:L-2020-LLL-002119 September 2020Open
EPID:L-2020-LLR-008028 July 2020OpenRevision to Request for Alternative Requirements for Preservice Inspection Acceptance of Volumetric Examinations (VEGP 3&4-PSI/ISI-ALT-14R1)
EPID:L-2020-LLM-004523 June 2020OpenSlides - Vogtle Pre-Submittal Meeting - 06-23-2020 - Cultural Resources Management Plan for the Vogtle Electric Generating Plant 2020 Update - Final
EPID:L-2020-LLE-004714 May 2020Open
EPID:L-2019-LLR-009711 February 2020OpenASME Code Case N-831-1
EPID:L-2019-LRQ-000220 January 2020OpenAssessment of Communications for Vogtle Electric Generating Plant Units 3 and 4
EPID:L-2019-LLA-010411 December 2019Open
EPID:L-2019-LLA-023518 November 2019Open
EPID:L-2019-LRM-005429 August 2019OpenSNC Slides for Public Pre-Submittal Meeting on August 29, 2019 (Eptd L-2019-LRM-0054)
EPID:L-2019-LLR-001718 February 2019OpenProposed ISI Alternative VEGP-ISI-ALT-19-01 for Tendon Inservice Inspection Extension
EPID:L-2017-LLA-012723 August 2018OpenIssuance of Amendments Technical Specification Updates for Reactivity Controls and Other Miscellaneous Changes (LAR 17-024)
EPID:L-2018-LLA-001812 July 2018OpenIssuance of Amendments Technical Specification Applicability Changes to Support Pressurizer Safety Valve Operability (LAR 18-004)
EPID:L-2018-LLA-003131 May 2018OpenAmendments for COLR and Consistency Changes (LAR 18-006)
EPID:L-2018-LRM-003224 May 2018Open
EPID:L-2018-LLR-008224 May 2018OpenThird 10-Year Interval Inservice Inspection Program ISI Program Update: Notification of Impractical ASME Code Requirements
EPID:L-2018-LLA-01094 May 2018Open
CAC:RP953213 March 2018Open
CAC:MG018825 January 2018Open