Start date | Status | Title | Topic | |
---|---|---|---|---|
EPID:L-2023-LLA-0051 | 16 May 2023 | Approved Closed | ||
EPID:L-2022-LLR-0078 | 14 April 2023 | Approved Closed | ||
EPID:L-2023-LLA-0072 | 5 April 2023 | Approved Closed | License Amendment Request: More Restrictive Action for Technical Specification 3.1.9 (LAR-23-006) | |
EPID:L-2023-LLA-0005 | 12 January 2023 | Approved Closed | ITAAC Closure Notification on Completion of Item 2.3.13.05.i (Index Number 462) | |
EPID:L-2022-LLA-0190 | 21 December 2022 | Approved Closed | ITAAC Closure Notification on Completion of ITAAC 2.1 .02.08d.ii (Index Number 33) | |
EPID:L-2022-LLA-0187 | 16 December 2022 | Approved Closed | TSTF-529 | |
EPID:L-2022-LRO-0120 | 30 September 2022 | Approved Closed | Pre-Submittal Meeting on September 13, 2022 - Vogtle Online Monitoring LAR | |
EPID:L-2022-LLE-0022 | 1 August 2022 | Approved Closed | Dashboard Report 8-12-2022 | |
EPID:L-2022-LLE-0021 | 1 August 2022 | Approved Closed | ||
EPID:L-2022-LLA-0130 | 15 June 2022 | Approved Closed | Tier 1, Revision 10, Updated Through 04/22/2022 | |
EPID:L-2022-LLR-0042 | 8 April 2022 | Approved Closed | Submittal of Updated Final Safety Analysis Report, Tier 1, Technical Requirements Manual and Technical Specifications Bases Annual | |
EPID:L-2022-LRO-0030 | 1 April 2022 | Approved Closed | Icn Review Status for Vogtle Unit 3 as of July 19, 2022 | |
EPID:L-2021-LLA-0235 | 22 December 2021 | Approved Closed | License Amendment Request to Relocate Augmented Piping Inspection Program Details | |
EPID:L-2021-LLA-0234 | 22 December 2021 | Approved Closed | TSTF-269 | |
EPID:L-2022-LLE-0020 | 21 December 2021 | Approved Closed | ITAAC Closure Verification Evaluation Form (Vef) for ITAAC Number 2.2.05.07a.i (Index No. 265) for Vogtle Unit 3 Combined License (VOG3) | |
EPID:L-2021-LLA-0236 | 21 December 2021 | Approved Closed | TSTF-283 | |
EPID:L-2021-LLE-0051 | 3 November 2021 | Approved Closed | Request for Exemption: Applicability of 10 CFR 26.3, Scope, Until Initial Fuel Load | |
EPID:L-2021-LLE-0049 | 1 November 2021 | Approved Closed | Vog 3 Dashboard 11-1-2021 | |
EPID:L-2022-LLA-0097 | 27 October 2021 | Approved Closed | TSTF-286 TSTF-471 TSTF-490 TSTF-051 TSTF-571, TSTF-448 | |
EPID:L-2021-LLA-0178 | 30 September 2021 | Approved Closed | License Amendment Request: Revise Technical Specification 3.7.2 Limiting Condition for Operation to Remove One Main Steam Isolation Valve System | |
EPID:L-2021-LLA-0175 | 29 September 2021 | Approved Closed | TSTF-554 | |
EPID:L-2021-LLA-0163 | 17 September 2021 | Approved Closed | TSTF-577 | |
EPID:L-2021-LLR-0068 | 10 September 2021 | Approved Closed | Proposed Alternative Requirements for the Repair of Reactor Vessel Head Penetrations for the 4th 10-Year Inservice Inspection Internal (VEGP-ISI-ALT-04-05, Version 1.0) | |
EPID:L-2021-LLA-0115 | 22 June 2021 | Approved Closed | License Amendment Request to Remove Table of Contents from Technical Specifications | |
EPID:L-2021-LLA-0153 | 15 June 2021 | Approved Closed | to Tier 1 | |
EPID:L-2021-LLA-0109 | 9 June 2021 | Approved Closed | Units 1 and 2, Vogtle Electric Generating Plant - Units 1 and 2, Voluntary License Amendment Request to Use Beacon Power Distribution Monitoring System | |
EPID:L-2021-LLE-0031 | 9 June 2021 | Approved Closed | Units 1 and 2 and Vogtle Electric Generating Plant - Units 1 and 2, Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule | |
EPID:L-2021-LLR-0041 | 3 June 2021 | Approved Closed | Request for Alternative Requirements for ASME Section III Remediation of Containment Vessel Unistrut Welding (VEGP 3-ALT-16) | |
EPID:L-2021-LLA-0054 | 30 March 2021 | Approved Closed | 3 to Updated Final Safety Analysis Report, Technical Specification Bases Changes, Technical Requirements Manual Changes, 10 CFR 50.59 Summary Report and Revised NRC Commitments Report | |
EPID:L-2021-LLA-0052 | 25 March 2021 | Approved Closed | License Amendment Request to Revise Technical Specification 5.7, High Radiation Area, Administrative Controls | |
EPID:L-2021-LRM-0023 | 18 February 2021 | Approved Closed | ||
EPID:L-2020-LLE-0134 | 17 December 2020 | Approved Closed | ||
EPID:L-2020-LLE-0183 | 4 December 2020 | Approved Closed | ||
EPID:L-2020-LLR-0159 | 13 October 2020 | Approved Closed | Summary of 10-15-20 Public Meeting with Southern Nuclear Operating Company | |
EPID:L-2020-LLE-0216 | 13 October 2020 | Approved Closed | Construction Reactor Oversight Process Resources October 2020 | |
EPID:L-2020-LRO-0059 | 17 September 2020 | Approved Closed | Uncompleted ITAAC Notification Checklist (UINC) 2.3.07.07b.vii for ITAAC (Index No.) for Vogtle Unit 4 Combined License (VOG4) | |
EPID:L-2020-LLA-0182 | 9 September 2020 | Approved Closed | Exemption - Vogtle GSI-191 | |
EPID:L-2020-LLR-0109 | 12 August 2020 | Approved Closed | Request to Use a Portion of a Later Edition of the ASME B&PV Code, Section XI | |
EPID:L-2020-LLR-0101 | 6 August 2020 | Approved Closed | ||
EPID:L-2020-LLA-0151 | 30 June 2020 | Approved Closed | Southern Nuclear Operating Co., Inc. - License Amendment Request to Revise the Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Emergency Response Organization Positions | |
EPID:L-2020-LLA-0150 | 30 June 2020 | Approved Closed | Southern Nuclear Operating Co., Inc. - License Amendment Request to Revise the Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Emergency Response Organization Positions | |
EPID:L-2020-LLA-0135 | 19 June 2020 | Approved Closed | Request for License Amendment for Vacuum Relief Valve Technical Specification Changes (LAR-20-005) | |
EPID:L-2020-LLR-0074 | 22 May 2020 | Approved Closed | Submission of Proposed Alternative to Submitting Hatch and Vogtle Inservice Inspection Summary Reports within 90 Days of Outage Completion | |
EPID:L-2020-LLA-0101 | 7 May 2020 | Approved Closed | ITAAC Closure Verification Evaluation Form (Vef) for ITAAC Number 2.2.03.08c.i.01 (Index No. 177) for Vogtle Unit 3 Combined License (VOG3) | |
EPID:L-2019-LLA-0287 | 30 April 2020 | Approved Closed | Cyber Security Plan | |
EPID:L-2020-LLR-0142 | 9 April 2020 | Approved Closed | Order (Ruling on Nuclear Watch South Extension Request) | |
EPID:L-2020-LLE-0009 | 7 February 2020 | Approved Closed | VEGP Unit 3 Issuance of Amendment Re Auxiliary Building Wall 11 Seismic Gap Requirements (LAR 20-001) | |
EPID:L-2019-LLR-0109 | 31 December 2019 | Approved Closed | EPRI Technical Report 3002014590, Technical Bases for Inspection Requirements for PWR Steam Generator Feedwater and Main Steam Nozzle-to-Shell Welds and Nozzle Inside Radius Sections. | |
EPID:L-2019-LLA-0279 | 13 December 2019 | Approved Closed | Request for License Amendment: Reconciliation of Environmental Conditions Inputs to Civil Structural Design Licensing Basis (LAR-19-019) | |
EPID:L-2019-LLA-0097 | 22 November 2019 | Approved Closed | Request for License Amendment and Exemption: Auxiliary Building Room Heat-up (LAR-19-010) |