Start date | Status | Title | Request type | Estimated NRC review hours | Topic | |
---|---|---|---|---|---|---|
EPID:L-2023-LLL-0004 | 18 January 2023 | Approved Closed | Quality Assurance Program Manual Reduction in Commitment | LLL | ||
EPID:L-2022-LLE-0031 | 26 October 2022 | Open | Request for Exemption from 10 CFR 140.11(a)(4) Concerning Primary and Secondary Liability Insurance | Exemption Request | ||
EPID:L-2022-LLA-0136 | 14 September 2022 | Open | Cyber Security Plan | License Amendment | ||
EPID:L-2022-LRO-0073 | 22 August 2022 | Open | Post-Shutdown Decommissioning Activities Report Public Meeting Slides - September 22, 2022 | LRO | ||
EPID:L-2022-LLE-0024 | 12 August 2022 | Open | Exemption Request | |||
EPID:L-2022-LLA-0099 | 12 July 2022 | Open | License Amendment Request: Proposed Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme | License Amendment | ||
EPID:L-2022-LLE-0032 | 13 June 2022 | Open | Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel | Exemption Request | ||
EPID:L-2021-LLL-0015 | 21 July 2021 | Withdrawn Closed | EA-02-026 | LLL | ||
EPID:L-2021-LLA-0099 | 1 June 2021 | Approved Closed | TSTF-448 TSTF-425 TSTF-545 | License Amendment | ||
EPID:L-2021-LRM-0050 | 10 May 2021 | Open | LRM | |||
EPID:L-2021-LRO-0014 | 25 March 2021 | Approved Closed | 2020 Steam Generator Tube Inspection Report | LRO | ||
EPID:L-2020-LLE-0240 | 27 January 2021 | Approved Closed | Indian Point Nuclear Generating, Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) | Exemption Request | ||
EPID:L-2020-LLR-0160 | 30 December 2020 | Open | Arkansas, Units 1 and 2; Grand Gulf, Unit 1; River Bend, Unit 1; and Waterford, Unit 3, Relief Request Number EN-20-RR-003, Proposed Alternative to Use American Society of Mechanical Engineers Code Case N-711-2, Alternative Examination Cove | Relief Request | ||
EPID:L-2020-LLM-0003 | 23 December 2020 | Approved Closed | Post Shutdown Decommissioning Activities Report Including Site-Specific Decommissioning Cost Estimate for Palisades Nuclear Plant | License Transfer | ||
EPID:L-2020-LRM-0111 | 7 December 2020 | Open | LRM | |||
EPID:L-2020-LLE-0190 | 12 November 2020 | Approved Closed | Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic | Exemption Request | ||
EPID:L-2020-LRM-0088 | 2 November 2020 | Open | LRM | |||
EPID:L-2020-LRO-0051 | 13 October 2020 | Open | Summary of September 11, 2020, Conference Call with Entergy Nuclear Operations Inc. Regarding the Fall 2020 Steam Generator Tube Inspections at Palisades Nuclear Plant | LRO | ||
EPID:L-2020-LLE-0155 | 30 September 2020 | Approved Closed | Request for One-Time Exemption from 10 CFR 50, Appendix E, Biennial Emergency Preparedness Exercise Requirements Due to COVID-19 Pandemic | Exemption Request | ||
EPID:L-2020-LRM-0091 | 27 September 2020 | Open | LRM | |||
EPID:L-2020-LLR-0108 | 18 August 2020 | Open | Relief Request | |||
EPID:L-2020-LLR-0128 | 21 July 2020 | Approved Closed | ASME Code Case N-729-4 | Relief Request | ||
EPID:L-2021-LLE-0033 | 26 March 2020 | Approved Closed | Units 1, 2, and 3; and Palisades - Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) | Exemption Request | ||
EPID:L-2020-LLM-0000 | 2 December 2019 | Approved Closed | Firstenergy Nuclear Operating Company - Letter, Order, SE Approving Direct and Indirect Transfer of Licenses and Draft Conforming Amendments for Beaver Valley, Units 1 and 2, Davis-Besse, Unit 1, and Perry, Unit 1 | License Transfer | ||
EPID:L-2019-LRO-0033 | 25 July 2019 | Approved Closed | LRO | |||
EPID:L-2019-LRO-0051 | 24 June 2019 | Open | Proposed Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule | LRO | ||
EPID:L-2019-JLD-0000 | 8 May 2019 | Open | JLD | |||
EPID:L-2019-LLR-0009 | 31 January 2019 | Open | ASME Code Case N-831-1 | Relief Request | 150 hours6.25 days <br />0.893 weeks <br />0.205 months <br /> | |
EPID:L-2018-LRM-0087 | 18 December 2018 | Open | LRM | |||
EPID:L-2018-LLA-0258 | 8 November 2018 | Withdrawn Closed | TSTF-425 | License Amendment | ||
EPID:L-2018-LLA-0296 | 1 November 2018 | Approved Closed | License Amendment Request to Revise Existing Facility Operating License Conditions Regarding NFPA 805 Modifications | License Amendment | ||
EPID:L-2018-LRO-0039 | 16 October 2018 | Open | LRO | |||
EPID:L-2019-LLA-0070 | 27 September 2018 | Approved Closed | TSTF-425 | License Amendment | ||
EPID:L-2018-LRM-0057 | 26 September 2018 | Open | LRM | |||
EPID:L-2018-JLD-0015 | 25 September 2018 | Open | Revised Mitigating Strategies Assessment for Flooding Pursuant to 10 CFR 50.54(f) Request for Information Regarding Recommendation 2.1: Flooding of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident | JLD | ||
EPID:L-2018-LLA-0153 | 3 July 2018 | Approved Closed | License Amendment | 525 hours21.875 days <br />3.125 weeks <br />0.719 months <br /> | ||
EPID:L-2018-LRM-0022 | 10 April 2018 | Open | Tech Spec 3.3.5.2a Change Pre-Submittal Meeting Presentation Slides | LRM | ||
EPID:L-2017-FPR-0007 | 5 April 2018 | Open | Package: RAI Regarding Entergy Operations, Inc.'S Decommissioning Funding Plan Update for ISFSI Docket Nos.: 72-43, 72-51, 72-1044, 72-07, 72-12, and 72-59 | FPR | ||
EPID:L-2017-LRO-0058 | 22 January 2018 | Open | LRO | |||
EPID:L-2017-LRM-0053 | 5 December 2017 | Open | LRM | |||
EPID:L-2017-LLR-0142 | 1 December 2017 | Open | Proposed Alternative - Relief Request Number RR 5-6, Alternative to the Reexamination Frequency for a Relevant Condition - Foreign Material in Reactor Vessel | Relief Request | 160 hours6.667 days <br />0.952 weeks <br />0.219 months <br /> | |
EPID:L-2017-LRM-0054 | 28 November 2017 | Open | LRM | |||
EPID:L-2017-LLR-0141 | 17 November 2017 | Open | ASME Code Case N-513-4 | Relief Request | 160 hours6.667 days <br />0.952 weeks <br />0.219 months <br /> | |
EPID:L-2017-LLA-0369 | 1 November 2017 | Approved Closed | License Amendment Request to Change the Full Compliance Implementation Date for the Fire Protection Program Transition License Condition for Required Modifications | License Amendment | 100 hours4.167 days <br />0.595 weeks <br />0.137 months <br /> | |
EPID:L-2017-LLL-0037 | 24 May 2017 | Open | Inadequate Protection from Tornado Missiles Identified Due to Nonconforming Design Conditions, LER 17-001-00 for Palisades Nuclear Plant Regarding Inadequate Protection from Tornado Missiles Identified Due to Nonconforming Design Conditions | LLL |