 Start dateStatusTitleRequest typeEstimated NRC review hoursTopic
EPID:L-2023-LLR-00244 May 2023OpenRelief Request (RA-23-0018) to Utilize Code Case N-853 PWR Class 1 Primary Piping Alloy 600 Full Penetration Branch Connection Weld Metal Buildup for Material Susceptible to Primary Water Stress Corrosion Cracking Section XI, Division 1Relief Request
EPID:L-2023-LLA-00494 April 2023Withdrawn
Closed
TSTF-52License Amendment
EPID:L-2023-LLR-002017 February 2023OpenProposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1)Relief Request
EPID:L-2023-LLA-002816 February 2023Approved
Closed
TSTF-554License Amendment
EPID:L-2023-LLR-00182 February 2023OpenRequest to Use a Provision of a Later Edition and Addenda of the ASME Boiler and Pressure Vessel Code, Section XIRelief Request
EPID:L-2023-LLA-00151 February 2023OpenTSTF-493
TSTF-425
TSTF-545
License Amendment
EPID:L-2023-LLR-000323 January 2023OpenProposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1)Relief Request
EPID:L-2022-NFO-001022 November 2022OpenNFO
EPID:L-2022-LRO-015221 November 2022Approved
Closed
Refuel 31 (O3R31) Steam Generator Tube Inspection ReportLRO
EPID:L-2022-LRO-006926 May 2022Approved
Closed
Refuel 30 (O2R30) Steam Generator Tube Inspection ReportLRO
EPID:L-2022-LLR-006019 May 2022OpenProposed Alternative to Use American Society of Mechanical Engineers (ASME) Code Case N-752, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems.Relief Request
EPID:L-2022-LRM-003120 April 2022OpenTSTF-425
TSTF-545
LRM
EPID:L-2022-LLA-005031 March 2022Approved
Closed
TSTF- 359License Amendment
EPID:L-2022-LLA-001118 January 2022Approved
Closed
TSTF-541License Amendment
EPID:L-2021-LLA-023014 December 2021Approved
Closed
SECY-22-0090: Duke Energy Request to Relocate the Emergency Operations FacilityLicense Amendment
EPID:L-2021-LRM-011229 November 2021OpenLRM
EPID:L-2021-LLA-01572 September 2021Approved
Closed
Application to Revise Technical Specification 3.7.7, Low Pressure Service Water (LPSW) System, to Extend the Completion Time for One Required Inoperable LPSW Pump on a Temporary BasisLicense Amendment
EPID:L-2021-LLR-005119 August 2021OpenRelief Request
EPID:L-2021-LLR-005219 August 2021OpenASME Code Case OMN-22Relief Request
EPID:L-2021-LLR-005519 August 2021OpenRelief Request
EPID:L-2021-LLR-005319 August 2021OpenASME Code Case OMN-26Relief Request
EPID:L-2021-LLR-005429 July 2021OpenASME Code Case OMN-28Relief Request
EPID:L-2021-LLA-01119 June 2021Approved
Closed
TSTF-439License Amendment
EPID:L-2021-SLR-00007 June 2021Approved
Closed
Application for Subsequent Renewed Operating LicensesSLR
EPID:L-2021-LLR-00346 May 2021OpenProposed Alternative for Inservice Inspection of Containment Post-Tensioning System ComponentsRelief Request
EPID:L-2021-LLR-00324 May 2021Approved
Closed
ASME Code Case N-853Relief Request
EPID:L-2021-LRM-003316 March 2021OpenASME Code Case N-853LRM
EPID:L-2021-LRO-000211 February 2021Approved
Closed
Refuel 31 (O1R31) Inservice Inspection (ISI) and Steam Generator Inservice Inspection (SG-ISI) Reports, Fifth 10-Year ISI IntervalLRO
EPID:L-2020-LLA-01984 February 2021Open1, 2; Catawba Nuclear Station 1, 2; H. B. Robinson Steam Electric Plant 2; Mcgguire Nuclear Station 1, 2; Oconee Nuclear Station 1, 2, 3; Shearon Harris Nuclear Power Plant 1 - Response to RAI Re Amend for Emergency PlanLicense Amendment
EPID:L-2021-LLR-000419 January 2021Approved
Closed
Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection IntervalsRelief Request
EPID:L-2020-LLR-01561 December 2020OpenDuke Energy Carolinas, LLC - Relief Request for Alternative for Reactor Vessel Closure Stud ExaminationsRelief Request
EPID:L-2020-LLE-018018 November 2020Approved
Closed
Exemption Request
EPID:L-2020-LLR-012621 September 2020OpenDuke Energy Carolinas, LLC - Request to Use a Provision of a Later Edition and Addenda of the ASME Boiler and Pressure Vessel Code, Section XI in Accordance with 10 CFR 50.55a(g)(4)(iv)Relief Request
EPID:L-2020-LLR-012416 September 2020OpenDuke Energy Corp. - Request to Use Provision of Later Edition and Addenda of ASME Boiler and Pressure Vessel Code, Section XI for Repair/Replacement Activities in Accordance with 10 CFR 50.55a(g)(4)(iv)Relief Request
EPID:L-2020-LLR-012516 September 2020OpenDuke Energy - Request to Use a Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XIRelief Request
EPID:L-2020-LLA-00768 May 2020Approved
Closed
TSTF-421License Amendment
EPID:L-2020-LLE-002217 April 2020OpenExemption Request
EPID:L-2020-LLA-007513 April 2020Approved
Closed
TSTF-272License Amendment
EPID:L-2020-LRO-000510 March 2020Approved
Closed
Refuel 29 (O2R29) Inservice Inspection (ISI) and Steam Generator Inservice Inspection (SG-ISI) Reports, Fifth 10-Year ISI IntervalLRO
EPID:L-2020-LLR-00362 March 2020OpenRequest for Alternative to Defect Removal Prior to Performing Repair/Replacement Activities on Low Pressure Service Water (LPSW) System PipingRelief Request
EPID:L-2019-LLA-018428 August 2019Approved
Closed
Proposed License Amendment Request to Revise the Oconee Nuclear Station Current Licensing Basis for High Energy Line Breaks Outside of the Containment BuildingLicense Amendment
EPID:L-2019-LRM-00487 August 2019OpenLRM
EPID:L-2019-LRO-000431 July 2019Approved
Closed
LRO
EPID:L-2020-LLS-000031 July 2019Approved
Closed
License Amendment Request for Measurement Uncertainty Recapture Power UprateLLS
EPID:L-2019-LRM-004230 July 2019OpenLRM
EPID:L-2019-LLA-01428 July 2019Approved
Closed
License Amendment Application to Relocate Technical Specification Unit/Facility Staff Qualification ANSI N18.1-1971, ANSI/ANS-3.1-1978 and ANSI/ANS-3.1-1981 Requirements to the Duke Energy Corporation Quality Assurance Program DescriptionLicense Amendment200 hours8.333 days <br />1.19 weeks <br />0.274 months <br />
EPID:L-2019-LLR-004611 June 2019OpenRelief Request200 hours8.333 days <br />1.19 weeks <br />0.274 months <br />
EPID:L-2019-LLR-002928 March 2019OpenASME Code Case N-770-2Relief Request190 hours7.917 days <br />1.131 weeks <br />0.26 months <br />
EPID:L-2019-LLR-002821 March 2019OpenASME Code Case N-853Relief Request190 hours7.917 days <br />1.131 weeks <br />0.26 months <br />
EPID:L-2018-JLD-017325 February 2019OpenJLD