Start date | Status | Title | Request type | Estimated NRC review hours | Topic | |
---|---|---|---|---|---|---|
EPID:L-2023-LLA-0027 | 1 March 2023 | Approved Closed | Emergency License Amendment Request for Technical Specification 3.5.2 Regarding One-Time Action for Valve Leak Repair | License Amendment | ||
EPID:L-2022-LLA-0135 | 6 September 2022 | Withdrawn Closed | Request for Fire Protection Program Changes | License Amendment | ||
EPID:L-2022-LLA-0071 | 16 May 2022 | Approved Closed | Request for an Amendment to Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time | License Amendment | ||
EPID:L-2022-LRO-0064 | 5 May 2022 | Approved Closed | 180-Day Steam Generator Tube Inspection Report | LRO | ||
EPID:L-2022-LLA-0048 | 30 March 2022 | Approved Closed | TSTF-501 | License Amendment | ||
EPID:L-2022-LRO-0014 | 10 February 2022 | Approved Closed | Steam Generator Inspection Report- Fall 2021 Refueling Outage | LRO | ||
EPID:L-2020-LLA-0229 | 15 October 2021 | Approved Closed | License Amendment | |||
EPID:L-2021-LLA-0193 | 20 September 2021 | Approved Closed | TSTF-554 | License Amendment | ||
EPID:L-2021-LLA-0160 | 15 September 2021 | Approved Closed | TSTF-547 | License Amendment | ||
EPID:L-2021-LLA-0220 | 15 September 2021 | Approved Closed | TSTF-577 | License Amendment | ||
EPID:L-2021-LLA-0156 | 29 August 2021 | Approved Closed | License Amendment Request to Revise Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start and Bus Separation Instrumentation | License Amendment | ||
EPID:L-2021-LLA-0127 | 14 June 2021 | Approved Closed | Emergency Plan Safety Evaluation | License Amendment | ||
EPID:L-2021-LLA-0075 | 26 April 2021 | Approved Closed | Request for an Amendment to Revise Technical Specification 5.6.3, Core Operating Limits Report (COLR) | License Amendment | ||
EPID:L-2021-LLR-0026 | 1 April 2021 | Approved Closed | ASME Code Case OMN-27 | Relief Request | ||
EPID:L-2021-LLA-0019 | 17 February 2021 | Approved Closed | TSTF 554 | License Amendment | ||
EPID:L-2021-LLL-0002 | 27 January 2021 | Approved Closed | TSTF-577 | LLL | ||
EPID:L-2020-LLE-0211 | 20 November 2020 | Approved Closed | Incoming Request-Beaver Valley-Energy Harbor Nuclear Corp | Exemption Request | ||
EPID:L-2020-LLE-0171 | 28 October 2020 | Approved Closed | Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(1)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic | Exemption Request | ||
EPID:L-2020-LLL-0023 | 28 October 2020 | Approved Closed | WCAP-18558-NP, Analysis of Capsule Y from the Beaver Valley Unit 2 Reactor Vessel Radiation Surveillance Program. Part 4 of 4 | LLL | ||
EPID:L-2020-LRO-0063 | 13 October 2020 | Approved Closed | License Amendment Request to Correct Non-conservative Technical Specification 3.7.4, Atmospheric Dump Valves (Advs) | LRO | ||
EPID:L-2020-LLE-0149 | 22 September 2020 | Approved Closed | Request for One-Time Exemption from 10 CFR 50, Appendix E, Biennial Emergency Preparedness Exercise Requirements Due to COVID-19 Pandemic | Exemption Request | ||
EPID:L-2020-LRO-0042 | 28 July 2020 | Approved Closed | Steam Generator Inspection Reports - Spring 2020 Refueling Outage | LRO | ||
EPID:L-2020-LLA-0154 | 10 July 2020 | Approved Closed | TSTF-567 | License Amendment | ||
EPID:L-2020-LLA-0127 | 29 June 2020 | Approved Closed | TSTF-563 | License Amendment | ||
EPID:L-2020-LLA-0138 | 23 June 2020 | Approved Closed | License Amendment Request to Correct Non-conservative Technical Specifications 3.2 .1, Heat Flux Hot Channel Factor Fa(Z) and 5.6.3, Core Operating Limits Report (COLR) | License Amendment | ||
EPID:L-2020-LLA-0140 | 22 May 2020 | Approved Closed | License Amendment Request to Revise Technical Specification Requirements Related to Inspection Method and Service Life for Alloy 800 Steam Generator Tubesheet Sleeves | License Amendment | ||
EPID:L-2020-LLE-0026 | 6 May 2020 | Approved Closed | Federal Register Notice | Exemption Request | ||
EPID:L-2020-LLE-0025 | 18 April 2020 | Approved Closed | Exemption Request | |||
EPID:L-2020-LLA-0071 | 16 April 2020 | Approved Closed | License Amendment | |||
EPID:L-2020-LLR-0053 | 2 April 2020 | Approved Closed | CFR 50.55a Request Number 2-TYP-4-RV-07 for Bottom Mounted Instrumentation Penetration Examinations | Relief Request | ||
EPID:L-2020-LLR-0052 | 2 April 2020 | Approved Closed | CFR 50.55a Request Number: VRR4, Revision 0, Containment Isolation Valve Test Frequency | Relief Request | ||
EPID:L-2020-LLR-0050 | 2 April 2020 | Approved Closed | 10 CFR 50.55a Request Number 2-TYP-4-RV-06, Hardship for Hot Leg Nozzle Inspections | Relief Request | ||
EPID:L-2020-LLR-0049 | 1 April 2020 | Approved Closed | CFR 50.55a Request Number: VRR5, Revision 0, Relief Valve Test Frequency | Relief Request | ||
EPID:L-2020-LLE-0011 | 25 February 2020 | Approved Closed | Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50. 75(h)(1 )(Iv) | Exemption Request | ||
EPID:L-2020-LLA-0025 | 11 February 2020 | Approved Closed | License Amendment Request - Proposed Change to Technical Specifications Sections 1.1. Definitions, and 5.0 Administrative Controls. for Permanently Defueled Condition | License Amendment | ||
EPID:L-2019-LLA-0155 | 18 December 2019 | Approved Closed | November 2019 NPDES Discharge Monitoring Report (DMR) | License Amendment | ||
EPID:L-2019-LLA-0223 | 20 October 2019 | Approved Closed | License Amendment Request to Modify Technical Specifications 3.4.16, RCS Specific Activity, 3.7.13 Secondary Specific Activity, 5.5.7, Ventilation Filter Testing Program (Vftp), and 5.5.14, Control Room Envelope. | License Amendment | 940 hours39.167 days <br />5.595 weeks <br />1.288 months <br /> | |
EPID:L-2019-LLR-0082 | 27 August 2019 | Approved Closed | Impractical American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI Examination Requirements | Relief Request | ||
EPID:L-2019-LLR-0083 | 23 August 2019 | Approved Closed | Unit 1, Impractical American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI Examination Requirements | Relief Request | ||
EPID:L-2020-LLE-0033 | 26 July 2019 | Approved Closed | Withdrawal of Certification of Permanent Cessation of Power Operations for Davis-Besse Nuclear Station. Unit No. 1. and Perry Nuclear Power Plant, Unit No. 1 | Exemption Request | ||
EPID:L-2018-LLE-0016 | 4 June 2019 | Approved Closed | Exemption Request | |||
EPID:L-2019-LLL-0028 | 30 April 2019 | Approved Closed | Request for Approval of Decommissioning Quality Assurance Program, Revision 0 for the Davis-Besse Nuclear Power Station | LLL | 180 hours7.5 days <br />1.071 weeks <br />0.247 months <br /> | |
EPID:L-2017-LRO-0083 | 1 April 2019 | Approved Closed | LRO | |||
EPID:L-2019-LRO-0000 | 28 March 2019 | Approved Closed | Day Steam Generator Tube Inspection Report | LRO | ||
EPID:L-2019-LLM-0000 | 15 March 2019 | Approved Closed | Stations - Irradiated Fuel Management Plans | License Transfer | 550 hours22.917 days <br />3.274 weeks <br />0.753 months <br /> | |
EPID:L-2019-LLR-0013 | 20 February 2019 | Approved Closed | Request Alternative Examination Frequency for Reactor Vessel Nozzle to Safe-End Welds (Request 2-TYP-4-RV-05, Revision 0) | Relief Request | ||
EPID:L-2018-LLE-0025 | 18 December 2018 | Approved Closed | Request for Exemption from Specific Provisions in 10 CFR 50 Appendix H | Exemption Request | 150 hours6.25 days <br />0.893 weeks <br />0.205 months <br /> | |
EPID:L-2018-LRO-0105 | 13 November 2018 | Approved Closed | Submittal of Beaver Valley Unit 1, Revision 31 to Updated Final Safety Analysis Report | LRO | ||
EPID:L-2018-LLR-0026 | 3 April 2018 | Approved Closed | Relief Request | 120 hours5 days <br />0.714 weeks <br />0.164 months <br /> | ||
EPID:L-2018-LLA-0075 | 28 March 2018 | Approved Closed | License Amendment | 230 hours9.583 days <br />1.369 weeks <br />0.315 months <br /> |