Name | Start date | End date | |
---|---|---|---|
EPID:L-2023-LLA-0078 | TSTF-505 TSTF-425 TSTF-411 TSTF-45 TSTF-266 | 31 May 2023 | 26 June 2023 |
EPID:L-2023-LRM-0027 | 13 April 2023 | 26 June 2023 | |
EPID:L-2023-LLR-0020 | Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) | 17 February 2023 | 30 May 2023 |
EPID:L-2023-LLA-0028 | TSTF-554 | 16 February 2023 | 29 August 2023 |
EPID:L-2023-LLA-0020 | License Amendment Request to Address Administrative Changes to the Operating License and Technical Specifications | 7 February 2023 | 6 March 2023 |
EPID:L-2023-LLR-0018 | Request to Use a Provision of a Later Edition and Addenda of the ASME Boiler and Pressure Vessel Code, Section XI | 2 February 2023 | 1 May 2023 |
EPID:L-2023-LLA-0015 | TSTF-493 TSTF-425 TSTF-545 | 1 February 2023 | 20 June 2023 |
EPID:L-2023-LLR-0003 | Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) | 23 January 2023 | 26 July 2023 |
EPID:L-2022-LRM-0031 | TSTF-425 TSTF-545 | 20 April 2022 | 10 May 2022 |
EPID:L-2022-LLR-0041 | Relief Request for Inservice Testing Program Plan - Fourth Ten-Year Interval | 7 April 2022 | 2 September 2022 |
EPID:L-2022-LLA-0036 | TSTF 569 | 24 March 2022 | 12 September 2022 |
EPID:L-2022-LLA-0011 | TSTF-541 | 18 January 2022 | 14 November 2022 |
EPID:L-2021-LLA-0230 | SECY-22-0090: Duke Energy Request to Relocate the Emergency Operations Facility | 14 December 2021 | 10 March 2023 |
EPID:L-2021-LRM-0112 | 29 November 2021 | 29 December 2021 | |
EPID:L-2021-LLA-0167 | 15 October 2021 | 28 July 2022 | |
EPID:L-2021-LLA-0193 | TSTF-554 | 20 September 2021 | 16 November 2021 |
EPID:L-2021-LLA-0161 | TSTF-577 | 16 September 2021 | 4 March 2022 |
EPID:L-2021-LLA-0149 | License Amendment Request to Revise Technical Specifications Related to Reactor Protection System Instrumentation | 6 August 2021 | 9 August 2022 |
EPID:L-2021-LLA-0108 | License Amendment Request Regarding Administrative Change to Reflect Development of a Technical Requirements Manual | 7 June 2021 | 20 January 2022 |
EPID:L-2021-LLA-0058 | 15 April 2021 | 10 February 2022 | |
EPID:L-2021-LLA-0027 | 22 March 2021 | 10 March 2022 | |
EPID:L-2020-LLA-0198 | 1, 2; Catawba Nuclear Station 1, 2; H. B. Robinson Steam Electric Plant 2; Mcgguire Nuclear Station 1, 2; Oconee Nuclear Station 1, 2, 3; Shearon Harris Nuclear Power Plant 1 - Response to RAI Re Amend for Emergency Plan | 4 February 2021 | 26 August 2021 |
EPID:L-2020-LLA-0262 | TSTF-493 | 3 December 2020 | 18 January 2022 |
EPID:L-2020-LLR-0156 | Duke Energy Carolinas, LLC - Relief Request for Alternative for Reactor Vessel Closure Stud Examinations | 1 December 2020 | 18 November 2022 |
EPID:L-2020-LLR-0143 | Radiation Safety Baseline Inspection Information Request | 4 November 2020 | 18 March 2021 |
EPID:L-2020-LLR-0126 | Duke Energy Carolinas, LLC - Request to Use a Provision of a Later Edition and Addenda of the ASME Boiler and Pressure Vessel Code, Section XI in Accordance with 10 CFR 50.55a(g)(4)(iv) | 21 September 2020 | 16 February 2021 |
EPID:L-2020-LLR-0124 | Duke Energy Corp. - Request to Use Provision of Later Edition and Addenda of ASME Boiler and Pressure Vessel Code, Section XI for Repair/Replacement Activities in Accordance with 10 CFR 50.55a(g)(4)(iv) | 16 September 2020 | 6 May 2021 |
EPID:L-2020-LLR-0125 | Duke Energy - Request to Use a Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI | 16 September 2020 | 9 November 2020 |
EPID:L-2020-LLE-0064 | 9 June 2020 | 9 June 2020 | |
EPID:L-2019-LLA-0256 | 16 April 2020 | 8 December 2020 | |
EPID:L-2020-LLA-0045 | 15 April 2020 | 16 March 2021 | |
EPID:L-2020-LRO-0016 | Har 2019 Mtg Slides | 8 April 2020 | 24 June 2020 |
EPID:L-2019-LLR-0035 | 5 April 2020 | 5 April 2020 | |
EPID:L-2020-LLR-0045 | TSTF-563, TSTF-448 TSTF-529 TSTF-4, TSTF-563 | 12 March 2020 | 10 December 2020 |
EPID:L-2020-LLA-0040 | TSTF-339 TSTF-5 | 6 March 2020 | 8 April 2021 |
EPID:L-2020-LLA-0024 | TSTF-359 | 6 February 2020 | 9 October 2020 |
EPID:L-2019-LRM-0064 | 29 January 2020 | 29 January 2020 | |
EPID:L-2019-LRO-0078 | 27 November 2019 | 27 November 2019 | |
EPID:L-2020-LLA-0111 | License Amendment Request to Correct Non-Conservative Technical Specification 3/4.4.9, Pressure/Temperature Limits - Reactor Coolant System | 23 October 2019 | 22 March 2021 |
EPID:L-2019-LLA-0218 | TSTF-505 | 7 October 2019 | 4 May 2021 |
EPID:L-2019-LRM-0053 | 24 September 2019 | 24 September 2019 | |
EPID:L-2019-LRM-0048 | 7 August 2019 | 26 August 2019 | |
EPID:L-2019-LLA-0160 | TSTF-439 TSTF-108 TSTF-52, TSTF-258 | 25 July 2019 | 24 September 2020 |
EPID:L-2019-LLA-0142 | License Amendment Application to Relocate Technical Specification Unit/Facility Staff Qualification ANSI N18.1-1971, ANSI/ANS-3.1-1978 and ANSI/ANS-3.1-1981 Requirements to the Duke Energy Corporation Quality Assurance Program Description | 8 July 2019 | 21 September 2020 |
EPID:L-2019-LLR-0046 | 11 June 2019 | 17 September 2019 | |
EPID:L-2019-LLA-0076 | TSTF-363 | 10 April 2019 | 13 October 2020 |
EPID:L-2018-LRM-0089 | 7 January 2019 | 7 January 2019 | |
EPID:L-2017-LLA-0347 | 19 November 2018 | 19 November 2018 | |
EPID:L-2018-LRM-0073 | 8 November 2018 | 8 January 2019 | |
EPID:L-2016-LLA-0356 | 28 September 2018 | 28 September 2018 |