Semantic search

Jump to navigation Jump to search
 Issue dateTitleTopic
IR 05000249/201700927 February 2017Final Significance Determination of a White Finding and Notice of Violation; NRC Inspection Report 05000249/2017009Mission time
Significance Determination Process
Preliminary White Finding
IR 05000237/201700927 February 2017Dresden Nuclear Power Station, Unit 3 - Final Significance Determination of a White Finding and Notice of Violation; NRC Inspection Report 05000249/2017009Mission time
Significance Determination Process
Preliminary White Finding
IR 05000237/201501016 September 2015EA-15-115; Final Significance Determination of White Finding and Notice of Violation; NRC Inspection Report No. 05000237/2015010; Dresden Nuclear Power StationSignificance Determination Process
Preliminary White Finding
IR 05000249/201500826 March 2015EA-15-001; Final Significance Determination of a White Finding with Assessment Followup and Notice of Violation; NRC Inspection Report No. 05000249/2015008; Dresden Nuclear Power StationSignificance Determination Process
Preliminary White Finding
IR 05000237/201500826 March 2015EA-15-001; Final Significance Determination of a White Finding with Assessment Followup and Notice of Violation; NRC Inspection Report No. 05000249/2015008; Dresden Nuclear Power StationSignificance Determination Process
Preliminary White Finding
ML14105A3381 May 2014Sliv Notice of Violation
IR 05000237/201300231 July 2013EA-13-079; Final Significance Determination of a White Finding with Assessment Followup and Notice of Violation; NRC Inspection Report No. 05000237/2013002, 05000249/2013002; Dresden Nuclear Power Station, Units 2 and 3Reactor Vessel Water Level
Significance Determination Process
Earthquake
Preliminary White Finding
IR 05000237/201300931 July 2013EA-13-079; Final Significance Determination of a White Finding With Assessment Followup And Notice Of Violation; NRC Inspection Report No. 05000237/2013002, 05000249/2013002; Dresden Nuclear Power Station, Units 2 and 3Reactor Vessel Water Level
Significance Determination Process
Earthquake
Preliminary White Finding
IR 05000249/200901026 October 2009IR 05000249-09-010, for Dresden, Unit 3, Final Significance Determination for a White Finding and Notice of ViolationSignificance Determination Process
Preliminary White Finding
IR 05000237/20070045 November 2007IR 05000237-07-004; 05000249-07-004, on 07/01/2007 - 09/30/2007; Exelon Generation Company, Dresden Nuclear Power Station, Units 2 and 3, Flood Protection Measures, Event Followup and Other Activities and Notice of ViolationSafe Shutdown
Loop seal
High Radiation Area
Non-Destructive Examination
Fire Barrier
Internal Flooding
Temporary Modification
Locked High Radiation Area
Condition Adverse to Quality
Significance Determination Process
Flow Accelerated Corrosion
Maintenance Rule Program
Through Wall Leak
IR 05000237/200201529 August 2003EA-03-102, Dresden, Notice of Violation, IR 05000237-02-015, 05000249-02-015, and OI 3-2002-027License Renewal
IR 05000237/20010213 April 2003EA-02-075 Dresden Notice of Violation NRC Office of Investigation Report No. 05000237-01-021 & 05000249-01-021(Redacted Version of Non-Public Version)