 Issue dateTitleTopic
ML20260K8479 September 1989Closed LOOP Cooling Service Water and Screen Wash Trubine Bldg and Screen House P & I Diagram. Sheet 2 of 4
ML20260K8439 September 1989Closed LOOP Cooling Service Water and Screen Wash Turbine Bldg and Screen House P & I Daigram. Sheet 1 of 4
ML20260K8565 August 1989Closed LOOP Cooling & Service Water Reactor & Waste Bldg P & I Diagram. Sheet 4 of 4
ML20260K8402 June 1989Reactor Core Spray P & I Diagram
ML20260K85129 March 1989Closed LOOP Cooling & Service Water Reactor & Waste Bldg'S P & I Diagram. Sheet 3 of 4
ML20259D0408 December 1988Reactor Bldg Core Spray Piping Plan at El 198 Ft & 218 Ft. Rev Date Illegible
ML20259D0688 December 19882 Aluminum Cone Roof Condensate Storage Tanks 30-OD & 42 Hg
ML20259D0638 December 1988Turbine Bldg Condensate Storage & Surge Tank. Rev Date Illegible
ML17055E06228 July 1988Reactor Bldg Closed LOOP Cooling Sys Piping at Reactor Recirc Pumps & Motors Section 1-1. Rev Date Illegible
ML17055E06028 July 1988Reactor Bldg Instrument Room El 237.0 Feet Instrument Piping Upper Plan & Section 4-4. Rev Date Illegible
ML17055E06928 July 1988Reactor Bldg Liquid Poison System Sections 1-1,2-2,3-3,4-4 & 5-5. Rev Date Illegible
ML17055E06328 July 1988Reactor Bldg Drywell & Torus Continuous Leak Rate Monitoring Sys Lowering Instr RM El 237.0 Feet. Rev & Rev Date Illegible
ML17055E06428 July 1988Reactor Bldg East Instr Room El 284 FEET-0 Inches Instrumentation & Misc Piping.
ML17055E06528 July 1988Reactor Building Emergency Condenser Piping Penetration Details X-34 & X-38 10 Feet Steam Supply. Sheet 1 of 3
ML17055E06828 July 1988Reactor Bldg Breathing Air & House Service Air.
ML20259D04411 February 1988Reactor Core Spray Sys 81 & 81.1 Piping Isometric from Torus to Topping Pumps to Ext Isolation Valves. Sheet 2
ML20259D04811 February 1988Reactor Core Spray Sys 81 & 81.1 Piping Isometric from Torus to Topping Pumps & from Topping Pumps to Ext Isolation Valves. Sheet 3
ML17055E0584 December 1987Reactor Bldg Instrument Room El 237.0 Feet Instrument Piping Section 11-11,12-12,13-13. Sheet 6
ML20259D05624 November 1987Condensate Flow P&I Diagram
ML17055E06129 October 1987Reactor Building Sampling Sample Station Details, as-built
ML20259D03728 August 1987Reactor Core Spary Sys 40 Piping Isometric from External Isolation Valve to Reactor
ML20266J8284 August 1987Piping & Instrumentation Diagram Symbols. Issue Date Illegible. Actual Drawing NUMBER:12177-PID-0-2A-1
ML20266J8294 August 1987Piping & Instrumentation Diagram Symbols. Issue Date Illegible. Actual Drawing NUMBER:12177-PID-0-2B-1
ML20266J8304 August 1987Piping & Instrumentation Diagram Symbols. Issue Date Illegible. Actual Drawing NUMBER:12177-PID-0-2C-1
ML20266J8324 August 1987Piping & Instrumentation Diagram Symbols. Issue Date Illegible. Actual Drawing NUMBER:12177-PID-0-2D-1
ML20266J77616 June 1987Piping & Instrumentation Diagram High Pressure Core Spray System. Issue 6
ML20266J77316 June 1987Piping & Instrumentation Diagram High Pressure Core Spray System. Issue 7
ML20266J80916 June 1987Piping & Instrumentation Diagram Primary Containment Purge & Standby Gas Treatment. Issue 7
ML20266J77216 June 1987Piping & Instrumentation Diagram LOW Pressure Core Spray. Issue 6
ML20266J85316 June 1987Piping & Instrumentation Diagram Service Water System. Issue 7
ML20266J86916 June 1987Piping & Instrumentation Diagram Instrument & Service Air. Issue 6
ML20266J80312 June 1987Piping & Instrumentation Diagram Control Building Chilled Water. Issue 5
ML20266J81512 June 1987Piping & Instrumentation Diagram Reactor Building Equipment and Floor Drains. Issue 7
ML20266J84118 May 1987Piping & Instrumentation Diagram Main Steam. Issue 4
ML20266J86418 May 1987Piping & Instrumentation Diagram Instrument & Service Air. Issue 6
ML20266J84018 May 1987Piping & Instrumentation Diagram Main Steam. Issue 6
ML20266J87018 May 1987Piping & Instrumentation Diagram Instrument & Service Air
ML20266J86718 May 1987Piping & Instrumentation Diagram Instrument & Service Air. Issue 6
ML20266J87118 May 1987Piping & Instrumentation Diagram Instrument & Service Air
ML20266J81311 May 1987Piping & Instrumentation Diagram DBA Hydrogen Recombiner. Issue 5
ML20266J81111 May 1987Piping & Instrumentation Diagram DBA Hydrogen Recombiner. Issue 7
ML20266J8231 May 1987Piping & Instrumentation Diagram Standby Diesel Gen System. Issue 4. Actual Drawing NUMBER:12177-PID-104A-4
ML20266J82220 April 1987Piping & Instrumentation Diagram Containment Atmosphere Monitoring System. Issue 4
ML20266J76820 April 1987Piping & Instrumentation Diagram Residual Heat Removal. Issue 5
ML20266J78520 April 1987Piping & Instrumentation Diagram Standby Liquid Control. Issue 6
ML20266J80520 April 1987Piping & Instrumentation Diagram Control Building Ventilation and Air Conditioning. Issue 6
ML20266J84520 April 1987Piping & Instrumentation Diagram Service Water System. Issue 7
ML20266J85114 April 1987Piping & Instrumentation Diagram Service Water System. Issue 5
ML20266J84914 April 1987Piping & Instrumentation Diagram Service Water System. Issue 5
ML20266J86014 April 1987Piping & Instrumentation Diagram Reactor Building Closed LOOP Cooling Water. Issue 5