SECY-23-0103, Summary of Staff Biennial Review and Findings of the 2023 Decommissioning Funding Status Reports from Operating and Decommissioning Power Reactor Licensees

From kanterella
Jump to navigation Jump to search
SECY-23-0103: Summary of Staff Biennial Review and Findings of the 2023 Decommissioning Funding Status Reports from Operating and Decommissioning Power Reactor Licensees
ML23304A230
Person / Time
Issue date: 12/15/2023
From: John Lubinski
Office of Nuclear Material Safety and Safeguards
To: Commissioners
NRC/OCM
Shared Package
ML23304A222 List:
References
SECY-23-0103
Download: ML23304A230 (1)


Text

December 15, 2023 FOR: The Commissioners SECY-23-0103 FROM: John W. Lubinski, Director Office of Nuclear Material Safety and Safeguards

SUBJECT:

SUMMARY

OF STAFF BIENNIAL REVIEW AND FINDINGS OF THE 2023 DECOMMISSIONING FUNDING STATUS REPORTS FROM OPERATING AND DECOMMISSIONING POWER REACTOR LICENSEES PURPOSE:

The purpose of this paper is to inform the Commission of the staffs findings from its biennial review of the 2023 decommissioning funding status (DFS) reports submitted by operating power reactor licensees and power reactor licensees in decommissioning. This periodic paper aligns with the submittal of DFS reports from operating power reactor licensees that is required every 2 years. This paper does not address any new commitments or resource implications.

BACKGROUND:

In 1988, the U.S. Nuclear Regulatory Commission (NRC) established technical and financial requirements to ensure that decommissioning of all licensed facilities would be accomplished in a safe and timely manner and that adequate licensee funds would be available for this purpose (Volume 53 of the Federal Register [FR], page 24018 [53 FR 24018]; June 27, 1988).

Decommission, in accordance with Title 10 of the Code of Federal Regulations (10 CFR) Section 50.2, Definitions, means to remove a facility or site safely from service and reduce residual radioactivity to a level that permits: (1) release of the property for unrestricted CONTACT: Mable A. Henderson, NMSS/REFS 301-415-3760

The Commissioners 2 use and termination of the license; or (2) release of the property under restricted conditions and termination of the license. Therefore, decommissioning, as used in NRC regulations, refers exclusively to radiological decommissioning.

In 1998, in response to the anticipated deregulation of the power-generation industry, the NRC amended the decommissioning financial assurance rules under 10 CFR 50.75, Reporting and recordkeeping for decommissioning planning, resulting in additional methods and flexibility for reactor licensees to provide financial assurance for decommissioning (63 FR 50465; September 22, 1998). Additionally, the amended regulations established the requirements that power reactor licensees report, on a biennial basis, the status of their decommissioning funds and material changes to their external trust agreements and other financial assurance mechanisms.

In 2011, the NRC further amended its regulations to improve decommissioning planning and to reduce the likelihood that any current operating facility would become a legacy site1 (76 FR 35512; June 17, 2011). As a result, 10 CFR 50.82, Termination of license, requires power reactor licensees in decommissioning to provide annual DFS reports to the NRC that include information on decommissioning expenditures made during the previous calendar year, the remaining balance of decommissioning funds, and an estimate of the cost to complete decommissioning.

DISCUSSION:

NRC regulations at 10 CFR 50.75(f)(1) and 10 CFR 50.75(f)(2) (for operating power reactors) and 10 CFR 50.82(a)(8)(v) (for power reactors in decommissioning) require licensees to submit DFS reports to the NRC. DFS reports are required every 2 years from operating power reactor licensees, annually from operating power reactor licensees that are within 5 years of the projected end of their operation or involved in a merger or acquisition, and annually from power reactor licensees in decommissioning. Licensees must submit these reports by March 31 for the preceding reporting calendar year. The reports must provide specified information that will allow the agency to monitor the status of decommissioning funds for all power reactor licensees from the time they begin operating until their license is terminated.

For operating reactors, in accordance with 10 CFR 50.75(f)(1), the DFS reports must include:

(1) the amount of decommissioning funds estimated to be required pursuant to 10 CFR 50.75(b) and 10 CFR 50.75(c); (2) the amount of decommissioning funds accumulated to the end of the calendar year preceding the date of the report; (3) a schedule of the annual amounts remaining to be collected; (4) the assumptions used in regard to rates of escalation in decommissioning costs, rates of earnings on decommissioning funds, and rates of other factors used in funding projections; (5) any contracts on which the licensee is relying; (6) any modifications occurring to a licensees current method of providing financial assurance since the last submitted report; and (7) any material changes to trust agreements.

Under 10 CFR 50.75, the NRC also requires power reactor licensees to demonstrate reasonable assurance of funding for decommissioning. Specifically, 10 CFR 50.75(b)(1) requires applicants and licensees to certify the amount of financial assurance for decommissioning, and 10 CFR 50.75(c) states the minimum amounts of funds for 1 As defined in the Statement of Considerations accompanying the 2011 rule, a legacy site is a facility that is in decommissioning status with complex issues and an owner that cannot complete the decommissioning work for technical or financial reasons.

The Commissioners 3 decommissioning by reactor type. Adjustments to the certification amount are required annually over the operating life of the facility to account for escalation in the labor, energy, and waste burial components of decommissioning costs. The staff notes that while the decommissioning funding amounts certified by licensees under 10 CFR 50.75 do not represent the actual cost of plant decommissioning, they do provide assurance that licensees have available the bulk of the funds to safely decommission the facility. Additionally, 10 CFR 50.75(b)(4) states, in relevant part, that the amount of a licensees certification may be based on a cost estimate for decommissioning the facility if that amount is not less than the amount in 10 CFR 50.75(c)(1).

Decommissioning cost estimates are a more accurate representation of the licensees cost to decommission as compared to the NRC-required minimum specified in 10 CFR 50.75(c).

Shortfalls identified during the operating cycle and between biennial DFS reporting periods are considered to be temporary lapses in funding for decommissioning that may be remedied by use of a parent company guarantee, trust fund growth, or trust fund contributions. In any event, licensees must correct shortfalls identified in a biennial DFS report by the time the next report is due. Pursuant to 10 CFR 50.75(e)(2), the NRC reserves the right to review, as needed, the rate of accumulation of decommissioning funds and to take additional actions as appropriate, on a case-by-case basis, to ensure a licensees adequate accumulation of decommissioning funds.

This includes modification of a licensees schedule for the accumulation of decommissioning funds.

For power reactors in decommissioning, in accordance with 10 CFR 50.82(a)(8)(v), the annual DFS reports must include: (1) the amount spent on decommissioning, both cumulative and over the previous calendar year, the remaining balance of any decommissioning funds, and the amount provided by other financial assurance methods being relied upon; (2) an estimate of the costs to complete decommissioning, reflecting any difference between actual and estimated costs for work performed during the year, and the decommissioning criteria upon which the estimate is based; (3) any modifications occurring to a licensees current method of providing financial assurance since the last submitted report; and (4) any material changes to trust agreements or financial assurance contracts. Pursuant to 10 CFR 50.82(a)(8)(vi), if the sum of the balance of any remaining decommissioning funds, earnings on such funds calculated at not greater than a 2 percent real rate of return, and the amount provided by other financial assurance methods being relied upon does not cover the estimated cost to complete the decommissioning, the DFS report must include additional financial assurance to cover the estimated cost of completion. Additionally, in accordance with 10 CFR 50.82(c), for licensees that shut down their reactors prematurely, the collection period for any shortfall of funds will be determined on a case-by-case basis upon application by the licensee, taking into account the specific financial situation of each licensee.

Using staff guidance in the Office of Nuclear Reactor Regulation Office Instruction LIC-205, Procedures for NRCs Independent Analysis of Decommissioning Funding Assurance for Operating Nuclear Power Reactors and Power Reactors in Decommissioning, Revision 6, dated April 10, 2017,2 the NRC staff reviewed the 20233 DFS reports for completeness and compliance with 10 CFR 50.75(f)(1) and (2) and 10 CFR 50.82(a)(8)(v) and (vi). The staffs review included reports for 93 operating power reactors and 26 power reactors in decommissioning. Two tables summarizing the staffs review are enclosed. Table 1, 2023 Decommissioning Funding Status Report for Operating Power Reactor Licensees (December 31, 2022), summarizes the information from the 93 DFS reports submitted by 2 Agencywide Documents Access and Management System (ADAMS) Accession No. ML17075A095 3 The 2023 DFS reports reflect the financial status as of December 31, 2022.

The Commissioners 4 operating power reactor licensees,4 and Table 2, 2023 Decommissioning Funding Status Report for Power Reactor Licensees in Decommissioning (December 31, 2022), summarizes the information from the 26 DFS reports submitted by power reactor licensees in decommissioning.5 These tables provide the projected decommissioning trust fund (DTF) balance before decommissioning along with the NRC minimum calculated in accordance with 10 CFR 50.75(c) or the site-specific cost estimate (if available). Note that a projected DTF balance less than the NRC minimum does not necessarily indicate a shortfall, as the staff also considers several other factors, including the withdrawal rate from the DTF during decommissioning and the growth of funds over time.

Results of the NRC Staffs ReviewOperating Power Reactor Licensees The NRC staffs review of the 2023 DFS reports for operating power reactor licensees resulted in the following findings:

  • All 93 operating power reactor licensees met the reporting requirements of 10 CFR 50.75(f) and are currently demonstrating decommissioning funding assurance.
  • As of the December 31, 2022, reporting period cutoff date, the NRC did not identify any shortfalls in the 2023 DFS review cycle for the 93 operating reactors.
  • The 2023 DFS report review cycle included 93 operating power reactors. Since the last summary of the staff review and findings for DFS reports,6 Vogtle Unit 3 was added to the DFS review list of power reactor licensees in operation, as that licensee provided certification in early 2023 that financial assurance for decommissioning is being provided as required under 10 CFR 50.75 for combined licenses. In addition, three units have transitioned to a decommissioning status (Palisades Nuclear Plant, Indian Point Nuclear Generating, Unit 2, and Indian Point Nuclear Generating, Unit 3) and are now included in the review of power reactor licensees in decommissioning.
  • Amounts accumulated in the DTFs for operating power reactors totaled approximately

$67 billion as of December 31, 2022.

Results of the NRC Staffs ReviewPower Reactor Licensees in Decommissioning The NRC staffs review of the 2023 DFS reports for power reactor licensees in decommissioning resulted in the following findings:

  • All 26 power reactor licensees in decommissioning met the reporting requirements of 10 CFR 50.82(a)(8)(v) and (vi).
  • All 26 power reactor licensees in decommissioning demonstrated decommissioning funding assurance by either showing a sufficient funding balance or providing additional assurances.

4 ADAMS Accession No. ML23304A233 5 ADAMS Accession No. ML23304A225 6 SECY-21-0108: Summary of Staff Biennial Review and Findings of the 2021 Decommissioning Funding Status Reports from Operating and Decommissioning Power Reactor Licensees, dated December 16, 2021 (ADAMS Package Accession No. ML21285A219)

The Commissioners 5

  • Current balances in the DTFs for power reactor licensees in decommissioning totaled approximately $11.7 billion as of December 31, 2022.

CONCLUSION:

Based on its review of the 2023 DFS reports, the NRC staff finds that all licensees are in compliance with the decommissioning funding assurance reporting requirements of 10 CFR 50.75(f)(1) and (2) for operating power reactor licensees and 10 CFR 50.82(a)(8)(v) and (vi) for power reactor licensees in decommissioning. The staff also finds that all licensees are in compliance with the decommissioning funding assurance requirements of 10 CFR 50.75 and 10 CFR 50.82, as applicable, for the 2023 DFS reporting cycle.

COORDINATION:

The Office of the General Counsel has reviewed this paper and has no legal objection.

Signed by Lubinski, John on 12/15/23 John W. Lubinski, Director Office of Nuclear Material Safety and Safeguards

Enclosures:

1. 2023 DFS Summary Table 1
2. 2023 DFS Summary Table 2

PKG - ML23304A222 SECY Paper - ML23304A230 WITS XXXXXXXXX OFFICE NMSS/FAB/REFS NMSS/FAB/REFS NMSS/FAB/REFS TechEd NAME MHenderson RTurtil FMiller THerrera DATE 11/01/2023 11/03/2023 11/06/2023 11/03/2023 OFFICE OGC - NLO NMSS/REFS/DD NMSS/OD NAME AGendelman JMoses JLubinski DATE 11/15/2023 11/09/2023 12/15/2023