SECY-21-0083, Enclosure - Differing View

From kanterella
Jump to navigation Jump to search
SECY-21-0083: Enclosure - Differing View
ML21266A141
Person / Time
Issue date: 09/23/2021
From:
Office of Nuclear Reactor Regulation
To: Commissioners
NRC/OCM
Nolan C
Shared Package
ML21266A133 List:
References
SECY-21-0083
Download: ML21266A141 (1)


Text

DIFFERING VIEW

Some subject matter experts (SMEs), including the Agency 2.206 Petition Coordinator and the Senior Attorney assigned to the working group, expressed concer ns about implementing the Expert Evaluation Teams recommendations for the petition revie w process under Title 10 of the Code of Federal Regulations (10 CFR) 2.206, Requests for action under this subpart. The SMEs felt that the Expert Evaluation Team recommended unnecessa ry changes considering the 10 CFR 2.206 process was updated in March 2019. Furthermor e, the SMEs pointed out that the Office of the Inspector General (OIG) had audited the 10 CFR 2.206 process in 2017, and the 2019 update to Management Directive (MD) 8.11, Review Process for 10 CFR 2.206 Petitions, was responsive to the two OIG recommendations (i.e., perform periodic formal process assessments and clarify petition acceptance criteria). For the applied 10 CFR 2.206 process, assessments of process effectiveness occur every 3 yea rs, and experience-based changes (such as enhanced communication with petitioners) are i mplemented in real time and are noted to be considered for future MD 8.11 updates. The SME s stated that making experience-based process changes is a more conscientious approa ch than reactive process changes and will better ensure that the 2.206 process is as eff ective as it can be.

In the February 2020 OIG event inquiry, the OIG discussed the 1 0 CFR 2.206 process and concluded that the Indian Point petition review board (PRB) di d not accurately communicate its analytical work performed. The SMEs clarified that the PRB di d not follow the 2000 MD 8.11 process of documenting the analytic work performed during the p etition review process in a Directors Decision. The SMEs question why a single PRB strayi ng from the 2000 MD 8.11 process, when 200+ other PRBs didnt, would prompt a change to the 2019 process. The SMEs further stated that the Expert Evaluation Team was only gi ven 2 months to understand how the 2000 MD 8.11 process was applied, how the revised proce ss addressed issues with the 2000 version of the process, and how the revised process should be enhanced. The SMEs noted that the Expert Evaluation Team did not attend any PRB me etings when responding to the OIG event inquiry in April 2020 and did not discuss the rev ised 2019 process with current SMEs. This led the SMEs to question how the Expert Evaluation Team was able to recommend four process changes less than 2 months after issuance of the O IG event inquiry. Additionally, the staff notes that the 2019 update of MD 8.11 was used for a very short time before the Expert Evaluation Team made its recommendations. Therefore, the recom mended changes are not being driven by experience or data but rather by the Expert Eva luation Teams consideration of a single petition evaluated under a previous version of the MD. Making some of the recommended changes to the language of MD 8.11 will decrease ef ficiency and the staffs flexibility in processing petitions, likely leading to addition al criticism from petitioners.

These SMEs found that the Expert Evaluation Teams Recommendati on 1, provides no different process oversight than what is already in practiceonly a diffe rent structure, which the SMEs do not feel is an improvement. The SMEs also clarified that Re commendations 3 and 4 are already part of the process (if proper process oversight is bei ng practiced). Finally, with respect to Recommendation 2, the SMEs observed that the Desktop Guide a lready included suggestions to ensure PRB diversity of technical perspectives i n 3 places, and they concluded that adding that language to MD 8.11 in a future update may be reasonable.

Overall, the SMEs concluded that the U.S. Nuclear Regulatory Co mmission is pursuing unneeded process changes and choosing to bypass the experience based periodic assessment of the 10 CFR 2.206 process. The result may be an overly presc riptive process with unforeseen problems.

Enclosure