SECY-12-0020, Enclosure 2 - Future Activities for Watts Bar Unit 2, Reactivation Project Plan

From kanterella
(Redirected from SECY-12-0020)
Jump to navigation Jump to search
SECY-12-0020 - Enclosure 2 - Future Activities for Watts Bar Unit 2, Reactivation Project Plan
ML11349A370
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 12/30/2011
From: Bavol B
Watts Bar Special Projects Branch
To:
Bavol B
Shared Package
ML11349A034 List:
References
SECY-12-0020 SECY-12-0020
Download: ML11349A370 (1)


Text

Nov-11 Issue Draft EIS for Public Comment (NRR)

Oct-12 Conduct On-Site Audit (10 CFR50.54(hh)(2))

Dec-11 ACRS Subcommittee Jul-12 Primary Hydro (TVA)

Aug-12 TVA Certify Tech Specs Jul-12 Complete Pre-Operational Testing (TVA)

Sep-12 Final As-Built Drawing (TVA)

Sep-12 INPO Readiness Assessment (TVA)

Dec-12 Certification of As-Built Plant (R-II)

Nov-12 Cyber Security Inspection (R-II)

Oct-12 ACRS Full Committee (Open Items)

May-12 Issue Final FES-OL (NRR)

Jul-12 ACRS Full-Committee Jun-12 ACRS Subcommittee May-12 Final Draft Tech Specs to TVA Oct-12 TVA Certify Readiness for Fuel Load Sep-12 Integrated Safeguards Test (TVA)

Dec-12 NRC Senior Mgt Meeting at Site Apr-12 Cyber Security Pilot (R-II)

Feb-13 Commission Briefings Aug-12 Complete Hot Functional Testing (TVA)

Jan-13 Commission Paper Nov-12 Operational Readiness Assessment (R-II)

Jan-12 FEMA Issue Emergency Preparedness Exercise Report Oct-12 Load Ice Baskets (TVA)

Mar-13 Decision Full Power License (NRR)

WATTS BAR UNIT 2 REACTIVATION PROJECT PLAN U.S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation PHASE II PHASE III Dec-12 Verify Readiness to Load Fuel (R-II)

Center for Planning and Analysis Branch Control Number:

171273_DP_TMLN_Rev20.vsd Oct 11 Jan 12 Apr 12 Jul 12 Oct 12 Jan 13 Apr 13 2011 2013 Mar-13 Fuel Load (TVA)

PHASE IV As of January 18, 2012 Sep-12 Final ACRS Subcommittee (Open Items)

Oct-12 TVA Certify As-Built Plant (TVA)

Operating License Jan 13 - Apr 13 Apr-12 Complete Fire Protection Program Review (NRR)

Production Review Oct 11 - Jun 12 Hearings and Briefings Jul 12 - Dec 12 Hearings and Briefings Operating License Production Review