MONTHYEARRS-24-088, Relief Requests Associated with the Fifth Inservice Inspection Interval2024-09-13013 September 2024 Relief Requests Associated with the Fifth Inservice Inspection Interval RS-24-064, Nuclear Radiological Emergency Plan Document Revisions2024-06-28028 June 2024 Nuclear Radiological Emergency Plan Document Revisions RS-24-066, Inservice Testing Interval Extension for Essential Service Water Valves Due to Required Use of Containment Chiller2024-06-25025 June 2024 Inservice Testing Interval Extension for Essential Service Water Valves Due to Required Use of Containment Chiller RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations RS-24-044, License Amendment to Transition to Framatome Gaia Fuel and Exemptions to 10 CFR 50.46 and 10 CFR 50 Appendix K. Attachments 1 to 11 Enclosed2024-05-28028 May 2024 License Amendment to Transition to Framatome Gaia Fuel and Exemptions to 10 CFR 50.46 and 10 CFR 50 Appendix K. Attachments 1 to 11 Enclosed RS-24-043, Application to Remove Power Distribution Monitoring System (Pdms) Details from Technical Specifications2024-05-24024 May 2024 Application to Remove Power Distribution Monitoring System (Pdms) Details from Technical Specifications RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests RS-24-026, License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 5.6.5, Core Operating Limits Report (COLR)2024-04-25025 April 2024 License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 5.6.5, Core Operating Limits Report (COLR) RS-24-034, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2024-04-10010 April 2024 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report RS-24-024, Response to Request for Additional Information Regarding Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds2024-03-22022 March 2024 Response to Request for Additional Information Regarding Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds RS-23-117, Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information2023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information RS-23-114, Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds2023-11-0101 November 2023 Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds RS-23-100, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-10-13013 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-108, Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles2023-10-11011 October 2023 Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles RS-23-105, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2023-10-10010 October 2023 Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections RS-23-093, License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 3.7.15, Spent Fuel Pool Boron Concentration, 3.7.16, Spent Fuel.2023-09-29029 September 2023 License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 3.7.15, Spent Fuel Pool Boron Concentration, 3.7.16, Spent Fuel. RS-23-094, Relief Request I4R-24, Alternative for Post-Peening Reexamination Frequency for Reactor Pressure Vessel Head Penetration Nozzle Number 752023-09-29029 September 2023 Relief Request I4R-24, Alternative for Post-Peening Reexamination Frequency for Reactor Pressure Vessel Head Penetration Nozzle Number 75 RS-23-091, Relief Request I4R-25, Alternative Requirements for Reactor Pressure Vessel Inservice Inspection Intervals2023-09-26026 September 2023 Relief Request I4R-25, Alternative Requirements for Reactor Pressure Vessel Inservice Inspection Intervals RS-23-083, Withdrawal - Proposed Alternatives Related to the Steam Generators2023-06-27027 June 2023 Withdrawal - Proposed Alternatives Related to the Steam Generators RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations RS-23-075, Application for Technical Specification Improvement to Extend the Completion Time for Condition B of Technical Specification 3.5.1, Accumulators, Using the Consolidated Line Item Improvement Process2023-06-0707 June 2023 Application for Technical Specification Improvement to Extend the Completion Time for Condition B of Technical Specification 3.5.1, Accumulators, Using the Consolidated Line Item Improvement Process RS-23-056, Response to Request for Additional Information to Braidwood Station, Unit 1, and Byron Station, Unit 1, for Steam Generator License Renewal Response to Commitment 102023-04-20020 April 2023 Response to Request for Additional Information to Braidwood Station, Unit 1, and Byron Station, Unit 1, for Steam Generator License Renewal Response to Commitment 10 RS-23-055, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2023-04-10010 April 2023 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.2032023-02-28028 February 2023 Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 RS-23-038, Response to Request for Additional Information for the Byron Proposal to Reinsert an Accident Tolerant Fuel Lead Test Assembly2023-02-27027 February 2023 Response to Request for Additional Information for the Byron Proposal to Reinsert an Accident Tolerant Fuel Lead Test Assembly RS-23-040, Constellation Energy Generation, LLC, Supplemental Information - Proposed Alternatives Related to the Steam Generators2023-02-21021 February 2023 Constellation Energy Generation, LLC, Supplemental Information - Proposed Alternatives Related to the Steam Generators RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 RS-22-123, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator2022-12-0707 December 2022 Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator RS-22-126, Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2022-11-30030 November 2022 Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI RS-22-110, Supplemental Information - Proposed Alternatives Related to the Steam Generators and Request.2022-09-20020 September 2022 Supplemental Information - Proposed Alternatives Related to the Steam Generators and Request. RS-22-097, License Amendment Request to Reinsert an Accident Tolerant Fuel Lead Test Assembly2022-08-31031 August 2022 License Amendment Request to Reinsert an Accident Tolerant Fuel Lead Test Assembly RS-22-093, Advisement of Leadership Changes for Constellation Energy Generation, LLC and Submittal of Updated Standard Practice Procedures Plans2022-08-18018 August 2022 Advisement of Leadership Changes for Constellation Energy Generation, LLC and Submittal of Updated Standard Practice Procedures Plans RS-22-086, R. E. Ginna Nuclear Power Plant - Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam.2022-08-10010 August 2022 R. E. Ginna Nuclear Power Plant - Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam. RS-22-084, Response to Request for Additional Information Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator .2022-06-17017 June 2022 Response to Request for Additional Information Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator . RS-22-074, Response to Request for Additional Information - Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds .2022-05-20020 May 2022 Response to Request for Additional Information - Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds . RS-22-073, Supplemental Information Regarding License Amendment Request -Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube.2022-05-19019 May 2022 Supplemental Information Regarding License Amendment Request -Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube. RS-22-057, Constellation Radiological Emergency Plan Addendum Revision2022-04-21021 April 2022 Constellation Radiological Emergency Plan Addendum Revision RS-22-037, License Amendment Request - Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control2022-04-21021 April 2022 License Amendment Request - Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control RS-22-051, Constellation Energy Generation, LLC - Update to Correspondence Addressees and Service Lists2022-04-12012 April 2022 Constellation Energy Generation, LLC - Update to Correspondence Addressees and Service Lists RS-22-047, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2022-04-0808 April 2022 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors RS-22-050, Supplemental Information - Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds2022-04-0808 April 2022 Supplemental Information - Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds RS-22-049, Constellation Energy Generation, LLC, Supplemental Information to Correct Typographical Errors in Constellation'S Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for2022-04-0404 April 2022 Constellation Energy Generation, LLC, Supplemental Information to Correct Typographical Errors in Constellation'S Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for V RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations RS-22-014, Application to Adopt TSTF-246, RTS Instrumentation, 3.3.1 Condition F Completion Time2022-03-24024 March 2022 Application to Adopt TSTF-246, RTS Instrumentation, 3.3.1 Condition F Completion Time RS-22-041, Withdrawal of License Amendment Request to Revise Technical Specifications 5.6.5, Core Operating Limits Report (COLR) to Add References to NRC Approved Topical Report with Administrative Changes2022-03-22022 March 2022 Withdrawal of License Amendment Request to Revise Technical Specifications 5.6.5, Core Operating Limits Report (COLR) to Add References to NRC Approved Topical Report with Administrative Changes RS-22-036, Supplemental Information - Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds2022-03-10010 March 2022 Supplemental Information - Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds 2024-09-13
[Table view] |
Text
Exelon Generation www.exeloncorp .com 4300 Winfield Road Warrenville, I L 60555 10 CFR 50 .55a RS-05-023 March 7, 2005 U .S. Nuclear Regulatory Commission ATTN : Document Control Desk Washington, DC 20555-0001 Byron Station, Units 1 and 2 Facility Operating License Nos . NPF-37 and NPF-66 NRC Docket Nos. 50-454 and 50-455
Subject:
Second Interval Inservice Inspection Program Relief Request 13R-01 In accordance with 10 CFR 50.55a, "Codes and standards," paragraph (a)(3)(i), Exelon Generation Company, LLC (EGC), is requesting relief from the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code,Section XI, "Rules for Inservice Inspection of Nuclear Power Plant Components," on the basis that the proposed alternative provides an acceptable level of quality and safety .
Specifically, relief is being sought to reduce the duration of the Byron Station, Unit 2 second inservice inspection (ISI) interval in order to create a common third ISI interval for Byron Station Unit 1 and Unit 2. In addition, relief is requested to reduce the first containment inservice inspection (CISI) interval for Byron Station, Units 1 and 2, which will permit subsequent CISI interval dates to be synchronized with the future ISI Intervals for both units. The net effect of this request is to establish one common interval for both the ISI and CISI Programs at Byron Station, Units 1 and 2. The details of the request for relief are enclosed .
EGC requests approval of this request by September 2005 in order to support the Byron Station, Unit 2 conversion to the common, third ISI interval start date. Should you have any questions concerning this letter, please contact David J . Chrzanowski at (630) 657-2816 .
Respectfully, osephA.Bauer Manager, Licensing
Enclosure:
Relief Request Number 13R-01
ISI Program Plan Byron Station Units I & 2 RELIEF REQUEST NUMBER : 13R-01 (Page 1 of 5)
COMPONENT IDENTIFICATION Code Class: 1, 2, 3, MC, and CC
Reference:
IWA-2430 IWA-2432 Examination Category : All Item Number: All
==
Description:==
Synchronization of Ten-Year ISI Intervals between Unit 1 and Unit 2 for Class 1, 2, and 3. In addition, alignment of Containment Inservice Inspection (CISI) Ten-Year Intervals for Class MC and CC with the synchronized Unit 1 and 2 Ten-Year ISI Interval .
Component Number: All Class 1, 2, 3, MC, and CC Components CODE REQUIREMENT The following Code requirements are paraphrased from the 2001 Edition through the 2003 Addenda of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code Section XI, "Rules for Inservice Inspection of Nuclear Power Plant Components ."
Paragraph IWA-2430(b), "Inspection Intervals," requires the inspection interval to be determined by calendar years following placement of the plant into commercial service.
Paragraph IWA-2432, "Inspection Program B," requires that each inspection interval consist of a ten-year duration, except as modified by IWA-2430(d) which permits the inspection interval to be reduced or extended by as much as one year, provided that successive intervals are not altered by more than one year from the original pattern of intervals.
BASIS FOR RELIEF Pursuant to 10 CFR 50 .55a(a)(3)(i), relief is requested from the ten-year interval requirements contained within IWA-2430(b) and (d) and IWA-2432 for the Byron Station, Unit 2 ISI Program and the Byron Station Units 1 and 2 CISI Programs on the basis that the proposed alternative would provide an acceptable level of quality and safety .
Specifically, relief is being sought to reduce the duration of the Byron Station, Unit 2 second ISI interval in order to create a common ISI interval for Byron Station Unit 1 and Unit 2 . In addition, relief is requested to reduce the first CISI interval for Byron Station Unit 1 and Unit 2, which will permit subsequent CISI interval dates to be synchronized with the future ISI intervals for both units. The net effect of this request is to establish one common interval for both the ISI and CISI Programs at Byron Station Units 1 and 2.
Exelon Generation Company, LLC.
ISI Program Plan Byron Station Units I & 2 RELIEF REQUEST NUMBER : 13R-0 1 (Page 2 of 5)
BASIS FOR RELIEF (Continued)
Currently, the Byron Station, Unit 1 Second ISI Interval is scheduled to end on September 15, 2005 and the same Byron Station, Unit 2 Interval will end on August 21, 2007 . This creates about a two year gap between the two units' ISI Programs which may likely result in different governing code editions, different program requirements, and the need for different parallel implementing procedures .
Reducing the duration of the Second ISI Interval for Byron Station, Unit 2 by approximately two years will permit the commencement of its Third ISI Interval to coincide with the start of the Third ISI Interval for Byron Station, Unit 1 and hence will establish a joint inspection interval with common start and end dates moving forward. This will assure both ISI Programs use the same code edition and addenda for the next and successive intervals and will likewise establish common implementing procedures for both units.
Any examination methods unique to and specifically required in the Byron Station, Unit 2 Third Period under the previous ISI Interval Code (i.e., ASME Section XI, 1989 Edition), that will likewise be required in the next ISI Interval, will be scheduled and completed in the First Period of this subsequent interval . The examinations will be conducted and credited under the rules of the code of record applicable to the new interval . These examinations originally unique to the Third Period of the previous interval will henceforth be conducted in the First Period of all subsequent ISI intervals, and deferral to the end of future intervals will not be available. This method of scheduling will maintain the original sequence of examinations and thus will not affect the frequency of examination.
The second part of this relief request is to similarly affect the CISI Program interval dates.
CISI Programs were initially required by regulation (i .e ., 10 CFR 50.55a) as amended within a Final Rule (61 FR 41303) issued on August 8, 1996 . Accordingly, the Byron Station CISI Program was prepared and implemented in accordance with the 1992 Edition through the 1992 Addenda of Subsections IWE, "Requirements for Class MC and Metallic Liners of Class CC Components of Light-Water Cooled Plants," and IWL, "Requirements for Class CC Concrete Components of Light-Water Cooled Plants," of ASME Section XI as modified by the regulation at that time . Further relief has since been requested and approved by the NRC on September 18, 2000, to utilize the 1998 Edition of Section XI for the Subsections IWE and IWL CISI Programs at Byron Station Unit 1 and Unit 2 .
All examinations and tests required by the CISI Program to date have been implemented in accordance with the established schedule . For the IWE portion of the program, all the examinations scheduled for the first and second inspection periods have been completed .
Additionally, the first five-year examinations have been completed for the IWL portion of the program. All of these examinations and tests performed to date have satisfied the acceptance standards contained within Articles IWE-3000 and IWL-3000, without exception.
Currently, there are no containment surfaces or components requiring designation as augmented examination areas.
Exelon Generation Company, LLC
ISI Program Plan Byron Station Units 1 & 2 RELIEF REQUEST NUMBER : 13R-01 (Page 3 of 5)
BASIS FOR RELIEF (Continued)
Reducing the duration of the first CISI Interval for Byron Station Unit 1 and Unit 2 by approximately three years will permit commencement of the next (Le, second) CISI Interval for Class MC and CC components to coincide with the start of the joint third ISI Interval for (lass 1, 2, and 3 components as established above. This will result in both the ISI and CISI Programs being under the same code edition and addenda for the next and successive intervals. For the rolling five year IWL frequency applicable to Class CC components that are subject to Subsection IT/L requirements, the current schedule will be maintained, and the ections will be conducted in accordance with the ASME code of record for Byron Station at the time of examination.
The supplementary information contained within Section 2 .2 of former Final Rule (67 FR 60520) dated September 26, 2002, contains statements supporting the proposed alternative for modifying the CISI Interval . Specifically, the information pointed out that 10 CFR 50 .55a(g)(4)(ii) does not prohibit licensees from updating to a later edition and addenda of the ASME Code midway through a ten-year IWE and IWL examination interval .
Additionally, the information advised that Licensees wishing to synchronize their 120-month intervals may submit a request in accordance with Section 50 .55a(a)(3) to obtain authorization to extend or reduce 120-month intervals .
Using the common interval date justified above based on the current Unit 1 ISI Program dated September 16, 2005, the code of record for the third interval ISI and second interval CISI Programs is to be set on September 15, 2004 (i .e ., 12 months prior to the start of the successive interval in accordance with 10 CFR 50.55a(g)(4)(ii)) . On September 15, 2004, the latest edition and addenda of the code incorporated by reference in 10 CFR 50.55a(b)(2) of the regulation was the 1998 Edition through the 2000 Addenda . On October 1, 2004, approximately two weeks later, regulations were amended in the Federal Register to incorporate the 2001 edition through the 2003 addenda of Section X1 .
While this 10 CFR 50.55a amendment was issued less than 12-months prior to the new interval start date, Byron Station will utilize the 2001 Edition through the 2003 Addenda of Section XI to develop the ISI Program update for the third ISI interval and second CISI interval . This use of the later edition and addenda is permitted by 10 CFR 50.55a(g)(4)(iv) and will be subject to the limitations and modifications within 10 CFR 50 .55a(b)(2) of the regulation .
In conclusion, Exelon Generation Company, LLC concludes that authorizing the proposed alternative as described herein provides an acceptable level of quality and safety, and does not adversely impact the health and safety of the public .
Exelon Generation Company, LLC
ISI Program Plan Byron Station Units I & 2 RELIEF REQUEST NUMBER : 13R-0 1 (Page 4 of 5)
PROPOSED ALTERNATIVE As an alternative to the full ten-year interval duration requirements of IWA-2430(b) and (d) and IWA-2432 for the Unit 2 Second ISI Interval and for the Units 1 and 2 First CISI Intervals, Byron Station proposes to modify the interval dates of the Unit 2 Second ISI Interval and of the Units 1 and 2 First CISI Intervals. This will permit the subsequent ISI and CISI Programs to share a common inspection interval and to implement common code editions for Class 1, 2, 3, MC, and CC components . The common code of record for the third interval ISI programs and second interval CISI programs will be the 2001 edition through the 2003 addenda of ASME Section XI .
As a result of these interval modifications, the start date of the Third Interval ISI Programs and the Second Interval CISI Programs will be September 16, 2005 for both Byron Station Units 1 and 2 . Using this date, the Byron Station, Unit 1 Fall 2006 refueling outage (131 R14) and the Byron Station, Unit 2 Fall 2005 refueling outage (B2R12) will be the first refueling outages of the next intervals. The intervals will be scheduled in 10-year increments from this point forward with the modifications allowed by IWA-2430 fully available to future intervals and periods of the adjusted Programs (Byron Station, Unit 2 ISI ; Byron Station, Unit 1 CIS[ ;
and Byron Station, Unit 2 CISI) based on this new common interval date replacing the sequence established by the commercial service dates of the respective units. The Byron Station, Unit 1 ISI Program, for which the common interval is based, will maintain its current schedule under the requirements of IWA-2430 .
All inspection periods for Class 1, 2, 3, and MC components will commence for the next interval based on the modified common interval start date . Any examination methods unique to and specifically required in the third period under the previous interval, that will likewise be required in the next interval, will be scheduled and completed in the first period of the subsequent interval . The examinations will be conducted and credited under the rules of the new code of record (i .e ., 2001 edition through the 2003 addenda) . These examinations originally unique to the third period of the previous interval will henceforth be conduct in the first period of all subsequent ISI intervals, and deferral to the end of future intervals will not be available .
In addition, the rolling five year IWL frequency applicable to Class CC components that are subject to Subsection IWL requirements will be maintained as currently scheduled . The date of the first examination performed prior to September 9, 2001, to satisfy 10 CFR 50 .55a(g)(6)(ii)(B)(2), at that time titled "Expedited examination of containment," will be maintained in establishing the subsequent five year rolling frequency. These inspections will be conducted in accordance with the ASME Code of Record for Byron Station at the time of examination .
Exelon generation Company, LLC
IS! Program Plan Byron Station Units I & 2 RELIEF REQUEST NUMBER : 13R-01 (Page 5 of 5)
APPLICABLE TIME PERIOD Relief is requested to modify the end dates of the Byron Station, Unit 2 Second ISI Interval and of the Byron Station Units 1 and 2 First CISI Intervals and the start/end dates of all subsequent ISI and CISI intervals for Byron Station Unit 1 and Unit 2.
Exelon Generation Company, LLC