March 2006 Monthly Operating Report for V.C. Summer Nuclear Station
ML061010238
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 04/06/2006
From: Archie J
South Carolina Electric & Gas Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
RC-06-0073
Download: ML061010238 (5)


Text

l Jeffrey B. Archie Vice President, Nuclear Operations 803.345.4214 A SCANA COMPANY April 6, 2006 Document Control Desk U. S. Nuclear Regulatory Commission Washiigton, DC 20555 Attention: Director, Office of Resource Management

Dear Stir / Madam:

Subject:

VIRGIL C. SUMMER NUCLEAR STATION DOCKET NO. 50/395 OPERATING LICENSE NO. NPF-12 MARCH MONTHLY OPERATING REPORT Enclosed is the March 2006 Monthly Operating Report for the Virgil C. Summer Nuclear Station Unit No. 1. This submittal is made in accordance with the requirements of Technical Specifications, Section 6.9.1.10.

If there are any questions, please call Mr. Robert convenience.

G. Sweet, (803) 345-4080, at your JBA/mbb Attachment c:

S. A. Byrne (email)

T. D. Gatlin (email)

J. H. Hamilton (email)

R. J. White (email)

W. D. Travers R. E. Martin G. A. Lippard (email)

NRC Resident Inspector (email)

K. M. Sutton Paulette Ledbetter (email)

W. R. Higgins (email)

INPO Records Center J&H Marsh & McLennan William G. Wendland (ANI)

Pat Haught (Westinghouse)

C. W. Adams (email)

NSRC (email)

CER (L-99-0350-1)

File (818.03-1, RR 4100)

DMS (RC-06-0073) 0--- -- 2 Jc - q SCE&G I Virgil C. Summer Nuclear Station

  • P. 0. Box 88
  • T (803) 345.5209
  • ww.sscna.som

Director, Office of Resource Management March Monthly Operating Report RC-OE-0073 Page l of 4 ATTACHMENT I AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.

UNIT DATE COMPLETED BY TELEPHONE March 2006 AVERAGE DAILY POWER LEVEL DAY DAY I

2 3

4 5

6 7

8 9

10 11 12 13 14 15 16 (Mwe-Net) 990 990 989 989 990 990 990 990 990 990 989 988 985 986 989 989 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 501395 V. C. SUMMER I April 5, 2006 T. V. Dao (803) 345-4812 AVERAGE DAILY POWER LEVEL (Mwe-Net) 989 989 989 989 989 988 988 988 989 989 989 990 989 989 989

Director, Office of Resource Management March Monthly Operating Report RC-06-0073 Page 2 of 4 ATTACHMENT II OPERATING DATA REPORT DOCKET NO.

UNIT DATE COMPLETED BY TELEPHONE 50/395 V. C. SUMMER I April 5, 2006 T. V. Dao (803) 345-4812 OPERATING STATUS 1

Reporting Period:

Gross Hours in Reporting Period:

2 Currently Authorized Power Level (MWt):

Max. Depend. Capacity (MWe-Net):

Design Electrical Rating (MWe-Net):

3 Power Level to Which Restricted (If Any) (MWe-Net):

4 Reasons for Restrictions:

March 2006 744 2900 966 972.7 N/A N/A THIS MONTH YR TO DATE CUMULATIVE 5

6 7

8 9

10 11 12 13 14 15 16 17 18 Number of Hours Reactor Critical Reactor Reserve Shutdown Hours Hours Generator On Line Unit Reserve Shutdown Hours Gross Thermal Energy Generated (MWH)

Gross Electrical Energy (MWH)

Net Electrical Energy Generated (MWH)

Reactor Service Factor Reactor Availability Factor Unit Service Factor Unit Availability Factor Unit Capacity Factor (Using MDC)

Unit Capacity Factor (Using Design)

Unit Forced Outage Rate 744.0 0.0 744.0 0.0 2155169 763510 735774 100.0 100.0 100.0 100.0 102.4 101.7 0.0 2160.0 0.0 2160.0 0.0 6256861 2217350 2133929 100.0 100.0 100.0 100.0 102.3 101.6 0.0 165258.4 0.0 163156.7 0.0 445223502 1514449-19 144849458 84.7 84.7 83.7 83.7 81.1 80.0 2.9 19 Shutdowns Scheduled Over Next 6 Months N/A (Type, Date, & Duration of Each):

20 If Shutdown at End of Report Period, Estimated Date of Startup:

N/A 21 Units in Test Status (Prior to Commercial Operation):

N/A

Director, Office of Resource Management March Monthly Operating Report RC-06-0073 Page 3 of 4 ATTACHMENT IlIl UNIT SHUTDOWNS AND POWER REDUCTION DOCKET NO.

50/395 UNIT V. C. SUMMER I DATE April 5, 2006 COMPLETED BY T. V. Dao TELEPHONE (803) 345-4E12 March 2006 NO.

DATE TYPE DURATION REASON METHOD CORRECTIVE ACTIONICOMMIENTS None 1

REASON A: Equipment Failure B: Maintenance or Test C: Refueling D: Regulatory Restriction E: Operator Training and License Examination F: Administrative G: Operational Error H: Other (Explain) 2 METHOD 1: Manual 2: Manual Trip/Scram 3: Automatic Trip/Scram 4: Continuation (Use Initial Date) 5: Power Reduction (Duration 0.0) 9: Other (Explain)

SUMMARY

Director, Office of Resource Management March Monthly Operating Report RC-06-0073 Page h of 4 ATTACHMENT IV NARRATIVE

SUMMARY

OF OPERATING EXPERIENCE DOCKET NO.

UNIT DATE COMPLETED BY TELEPHONE 50/395 V. C. SUMMER I April 5, 2006 T. V. Dao (803) 345-4812 March 2006 V. C. Slimmer Station operated at full power for the entire month of March.