RBG-16-225, Interim Deficiency Rept DR-107.Investigation Incomplete.Next Rept Will Be Provided by 831130

From kanterella
Jump to navigation Jump to search
Interim Deficiency Rept DR-107.Investigation Incomplete.Next Rept Will Be Provided by 831130
ML20081F638
Person / Time
Site: River Bend Entergy icon.png
Issue date: 10/25/1983
From: Booker J
GULF STATES UTILITIES CO.
To: Jay Collins
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
DR-107, RBG-16-225, NUDOCS 8311030180
Download: ML20081F638 (1)


Text

,{7 GULF STATES UTILITIES COMPANY POSTOFFICE BOX 2951 BEAUMONT, TEXAS 77704 ARtA COCE 409 838 6631 October 25, 1983 RBG-16,225 File Nos. G9.5, G9.25.1.1 Mr. John T. Collins, Regional' Administrator U. S. Nuclear Regulatory Commission Region IV, Office of Inspection and Enforcement

=

611 Ryan Plaza Drive, Suite 1000 Y[h ['_h [ M Arlington, Texas 76011 OCT 2 71983

Dear Mr. Collins:

River Bend Station Unit 1

~

U Docket No. 50-458 Interim Report /DR-107 With rega.c to DR-107,' Gulf States Utilities-Company has not completer 1 its investigation. ' An interim or final status

~~

report will be provided by November 30, 1983.

Sincerely,

~

F -

.E.Loobr Manager-Engineering, Nuclear Fuels & Licensing River Bend Nuclear Group

-fP50 JEB/PJD/kt cc: Director of Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555 NRC Resident. Inspector-Site s