Press Release-14-054: NRC Approves Power Uprate for Peach Bottom Atomic Power Station
ML14237A561
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 08/25/2014
From:
Office of Public Affairs
To:
References
Press Release-14-054
Download: ML14237A561 (1)


Text

No: 14-054 August 25, 2014 CONTACT: Scott Burnell, 301-415-8200 NRC Approves Power Uprate For Peach Bottom Atomic Power Station The Nuclear Regulatory Commission has approved a request by Exelon Generation Co. to increase the generating capacity of Peach Bottom Atomic Power Station, Units 2 and 3, by 12.4 percent each.

The NRC staff determined Exelon could safely increase the reactors output primarily by upgrading certain plant systems and components. NRC staff also reviewed Exelons evaluations showing the plants design can handle the increased power level.

The NRCs safety evaluation of the plants proposed power uprate focused on several areas, such as the nuclear steam supply systems, instrumentation and control systems, electrical systems, accident evaluations, radiological consequences, operations and training, testing, and technical specification changes. For added confidence in the analysis, the NRC staff also conducted independent confirmatory calculations and audits of selected areas.

The power uprate authorizes Peach Bottom, located approximately 18 miles south of Lancaster, Pa., to increase each boiling water reactors generating capacity by approximately 140 megawatts electric. Exelon plans to implement Unit 2s uprate during the fall 2014 refueling outage and Unit 3s uprate during the fall 2015 refueling outage.