PY-CEI-NRR-1307, Requests Extension to 910628 to Submit Simulation Facility Certification
| ML20066H595 | |
| Person / Time | |
|---|---|
| Site: | Perry |
| Issue date: | 02/12/1991 |
| From: | Lyster M CENTERIOR ENERGY |
| To: | NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM) |
| References | |
| PY-CEI-NRR-1307, TAC-75335, NUDOCS 9102210201 | |
| Download: ML20066H595 (1) | |
Text
__ ________ _ _ _
1 CENTERf0R q
ENERGY ~
PERRY NUCLEAR POWER PLANT Mall Address; Michael D. Lyster P.O. BOX 97
'10 CENTER ROAD
' PERRY, OHIO 44081 VICE PRESIDENT - NUCLEAR PERRY, OHIO - 44081
. (216) 259-3737 -
February. 12, 1991 PY-CEI/NRR-1307 L
-U.S.
Nuclear Regulatory Commission Document' Control Desk Washington, D. C.
20555 i
Perry Nuclear Power Plant Docket No. 50-440 10 CFR 55.45(b)(2)(iii)
Exemption Request (TAC #75335)
- Gentlemen:
By letters dated November 21, 1989-(PY-CEI/NRR-1072L) and January 30, 1990
-i (PY-CEI/NRR-1128L), a request for-exemption was made f rom the filing date for NRC Form 474 " Simulation Facility Certification." 10 CFR 55.45(b)(2)(iii) sets a filing,date for Form 474 of. March 26, 1991. The letters noted that
- despite our accelerated production schedule, the replacement simulator will
-not be-in'a certifiable state of completion-by March 26, but that we expected
'to be able to file the certification form ontor about May 17, 1991 following
-completion of acceptance testing at the vendors facility.
'At that time, Lit was anticipated that licensed operator testing would be
-conducted in August, therefore Form 474 needed to be filed by the end of May.
.Since'that time, operator testing schedules-have been finalized, and the first operator test dates af ter March 26, 1991 will be in February _1992, thereby-lessening the.need for filing the certification form in May. A recent project status evaluation identified that the simulator factory acceptance test schedule had slipped; however, since the need for a May filing date has changed, it is requested that any_ issued exemption provide an additional time
. period before the filing is: required.
- Accordingly, Lit is requested that the' expiration date of any issuedLexemption be June 28, 1991. This' requested date provides for a prompt certification filing and a recognition of unforeseen occurrences in ongoing preacceptance testing of the simulator.
tIf you have any questions, please feel free to call.
Sincerely, g
Michael D. Lyster-MDL:BSF:njc cc:.USNRC Project Manager USNRC Resident Office USNRC Region III' Operatng tonoc"in Cesond Electne mom notrg pp[
wmm 9102210201 910212 a
2O' PDR ADOCK 0S000440