PM-86-128, Monthly Operating Rept for Apr 1986

From kanterella
Jump to navigation Jump to search
Monthly Operating Rept for Apr 1986
ML20207C923
Person / Time
Site: Shoreham File:Long Island Lighting Company icon.png
Issue date: 04/30/1986
From: Kelly D, Steiger W
LONG ISLAND LIGHTING CO.
To:
NRC OFFICE OF RESOURCE MANAGEMENT (ORM)
References
PM-86-128, NUDOCS 8607210455
Download: ML20207C923 (4)


Text

I -e SHOREHAM NUCLEAR POWER STATION AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50-322 1

.. UNIT DATE 5/2/86 i

COMPLETED BY D. Kelly TELEPHONE (516) 929-8300 MONTH April 1986 DAY AVERACE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net) (MWe-Net) 0 37 0 l 1

0 18 0 2

0 39 0 3

4 0 20 0 5 0 21 0 6 0 22 0 7 0 23 0 8 0 24 0 9 0 25 0 10 0 26 0 11 0 27 0 12 0 28 0 13 0 29 0 14 0 30 0 15 0 31 16 0 SPF 51 205.91-5, Rev. O l

l 8607210455 860430 PDR ADOCK 00000322 R PDR

.L $

r/r .

SHORERAM NUCLEAR POWER STATION OPERATING DATA REPORT DOCKET NO. 50-322 UNIT I DATE 5/2/86 i D. Kelly COMPLETED BY TELEPHONE (516)929-8300 OPERATING STATUS Reporting Period: 4/86 Gross Hours in Reporting Period 0 1.

2. Currently Authorized Power Level (MWt): 121.8 Max. Depend. Capacity (MWe-Net): 839 Design Electrical Rating (MVe-Met): 844
3. Power Level to which Restricted (if any) (MWe-Net): NA 4 Reasons for Restriction (if any):

This month Yr to Date Cumulative Nu=ber of Hours Reactor wa s Critical. . .. . . . . . . 0 0 0 5.

6. Reac to r Re se rve Shutdown Hours. . . . . . . . . . . . . . . . 0 0 0
7. Hours Generator on Line....................... 0 0 0 S. Unit Re se rve Shut d own Hours. . . . . . . . . . . . . . . . . . . 0 0 0
9. Gros s The rmal Ene rgy Generat ed (MWH). . . . . . . . . . 0 0 0
10. Gross Electrical Energy Generated (MWH)....... 0 0 0
11. Net Electrical Energy Generated (MWH)......... 0 0 0
12. Reacter Service Facter........................ NA
13. Reactor Availability Factor................... NA
14. Unit Service Facter........................... NA
15. Unit Availability Factor...................... NA
16. Unit Ca pacity Fac to r (Using MDC). . . . . . . . . . . . . . NA
17. Unit Capacity Factor (Using Design MWe)....... NA
18. Unit Forced Outage Rate....................... NA
19. Shutdowns Scheduled Over Next 6 Months (Type, Date, And Duration of Each):
20. If Shut Down at end of Report Period, Estimated Date of Startup: NA
21. Units in Test Status (Prior to Commercial Operation): FORECAST ACHIEVED INITIAL CRITICALITY 2/13/85 2/15/85 INITIAL ELECTRICITY 6/1/86 COMMERCIAL OPERATION 12/1/86 SPF 51.005 01-6, Rev. 6

i i k o' Sil0REllAM NUCLEAR POWER STATION ."

UNIT SiluTDOWNS AND POWER REDUCTIONS 50-322 DOCKET NO.

UNIT NAME I DATE 5/2/86 l

COMPLETED BY D. Kelly April 1986 REPORT HONTil HETii0D OF TYPE SilUTTING DOWN DURATION Tile REACTOR OR F: FORCED CORRECTIVE ACTIONS / COMMENTS (Il0URS) REASON (1) REDUCING POWER (2)

NO. DATE S: SCllEDULED none J

SUMMARY

Preparations for stsctup continued during the raonth of April.

SPF 51.995.91-7, key. p

Y' ~ ~. .

,J '

(. n n .. ~ ~ ~ -

f gg LONG ISLAND LIGHTING COM PANY

$HOREH AM NUCLE AR POWE R ST ATION

  • P O. BOX 628
  • WADING RIVE R, N: W YORK 11792

}>,=.w- u.u .m ,.e ew. is .-

TE L.1516) 929 8300 May 2, 1986 PM-86-128 Director, Office of Resource Management U. S. Nuclear Regulatory Commission Washington, D. C. 20555 Dear Sir In accordance with Technical Specifications Section 6. 9.1. 8, enclosed is a copy of the Shoreham Nuclear Power Station April Monthly Operating Report which summarizes the operating statistics and shutdown experience of the Plant.

If you have any questions, please contact us.

Very truly yours, ni*/

~

/ //

msn st CE.'Ste' r, Jr.

Plant Ma ager WES/km Enclosure ec: Dr. Thomas Murley, Regional Administrator John Berry , Senior Resident Inspector Institute of Nuclear Power Operations, Records Center American Nuclear Insurers SR-A43.700 1