Category:CORRESPONDENCE-LETTERS
MONTHYEARML20205L1831986-03-13013 March 1986 Comments on Proposed Rule 10CFR9.Rule Opposed Due to Opinion That Broad New Class of Secret Sessions or Meetings W/O Transcripts Will Be Created ML20151R5611986-01-30030 January 1986 Summarizes 851216 Mgt Meeting at Oak Ridge Operations Ofc to Review & Inspect Redress & Reclamation of Crbr Site.Drawings Reviewed,Discussions Held & Tour of Site Performed.Site Restoration Concluded to Be as Described in Plans & Specs ML20138Q8301985-12-0303 December 1985 Further Response to FOIA Request for Records Re Voluntary or Required Redress of Sites Where Const Was Terminated, Including Crbr & Legal Analysis.Forwards App E Documents.App D & E Documents Available in Pdr.Photographs Also Available ML20128B2801985-06-27027 June 1985 Updates DOE .Bids for Redress of Crbr Site Opened on 850604.Contract Awarded to Beaver Excavating Co,Canton, Oh,On 850613.Contractor Scheduled to Complete Site Redress on or Before 851216 ML20133C7371985-06-14014 June 1985 Further Response to FOIA Request for Documents Re Site Redress Where Plant Const Begun,Including Clinch River Facility & NRC Legal Analysis Re Redress.Forwards App B Documents.App C Document Withheld (Ref FOIA Exemption 5) ML20128R0001985-06-0606 June 1985 Partial Response to FOIA Request for Records Re Desirability of Voluntary or Required Redress of Nuclear Plant Sites Where Work Undertaken But Const No Longer Contemplated. Forwards Documents Listed in App a ML20133C6881985-05-0808 May 1985 FOIA Request for Documents Re Redress of Sites Where Nuclear Plant Const Begun & NRC Legal Analysis of Need for Site Redress W/ or W/O Current CP & LWA ML20107M8141984-11-0707 November 1984 Clarifies & Reaffirms Util Commitments Re Redress of Site in Accordance W/Util 840305 Final Site Redress Plan & NRC 840606 Approval of Plan ML20107H8031984-11-0606 November 1984 Reaffirms Commitments to Redress Site in Accordance W/ 840305 Final Site Redress Plan & NRC 840606 Approval Ltr. Related Correspondence ML20140C6121984-06-18018 June 1984 Advises That Time for Commission to Review ALAB-761 Expired. Commission Declined Review.Decision Became Final Agency Action on 840611.Served on 840618 ML20087B4361984-03-0808 March 1984 Confirms That ASLB Intends to Vacate Notice of 840314 Conference & Reschedule Later Date Due to Delay in Funding for Review of Redress Plan & Possible Lack of Availability of One ASLB Member.Certificate of Svc Encl ML20086T4631984-03-0505 March 1984 Forwards Site Redress Plan. Minor Clarifications & Corrections to Draft Plan Submitted 840227 Made in Response to NRC Comments ML20087A4141984-03-0202 March 1984 Forwards Page 15 Inadvertently Omitted from 840227 Transmittal of Draft Crbr Plant Redress Plan.Related Correspondence ML20080T9331984-03-0101 March 1984 Forwards Page 15 of Crbr Program Redress Plan,Inadvertently Omitted from 840227 Transmittal.Certificate of Svc Encl ML20128R0161984-02-29029 February 1984 Expresses Thanks for 840222 Review of Site Redress Planning. Concurs W/Conceptual Approach & 1-yr Period for Development of Final Site Redress Plan & Investigation of Potential Use of Site.Ml Lacy Encl ML20080S6661984-02-27027 February 1984 Forwards Draft Site Redress Plan,In Response to N Grace 831208 Request.Plan Will Be Finalized for Submission on 840302,following Receipt of Comments ML20079F9411984-01-13013 January 1984 Informs of Receipt & Storage,Through S&W Engineering,Of Spent Fuel Transfer Port Assembly Large Shield Plug.Due to Failure of Congress to Appropriate Addl Funding,Doe No Longer Seeking CP & Is Closing All Licensing Activities ML20083G3551984-01-10010 January 1984 Advises That Svc of DOE & Project Mgt Corp 831227 Notification Re Project Termination Affected Again on All Parties on Attached Svc List ML20083H2331983-11-15015 November 1983 Summarizes Current Status of SER Open Items Re Structural Response During Faulted Conditions & Beyond Dbas.Program Lacks Planned Analytical Support.Models to Support Experimental Efforts Should Be Developed ML20081B9721983-10-24024 October 1983 Summarizes 831004 Meeting W/Nrc,Acrs & Lnr Assoc Re Mgt of Crbr PRA Program.Viewgraphs & List of Meeting Attendees Encl ML20078A7571983-09-0707 September 1983 Forwards Evaluation Repts of Faults 1,2 & 3 Discovered on Site During Foundation Excavation.Faults Not Capable within Meaning of App a to 10CFR100.W/seven Photographs ML20076A8171983-08-17017 August 1983 Confirms Redirection for Shipping Applicant Voluminous Exhibits.Certificate of Svc Encl ML20076A7761983-08-17017 August 1983 Advises That Author Will Present Oral Argument on Behalf of Applicants & Forwards Motion Requesting Argument Be Rescheduled for 830928 ML20077J0781983-08-11011 August 1983 Forwards Pages from Transcript of Crbr CP 830810 Hearings Per ASLB Direction.Certificate of Svc Encl ML20081A5601983-08-11011 August 1983 Summarizes 830808 Informal Meeting on Contract Re PRA Review of Crbr (Task 4) & NRC Concerns Associated W/Technology for Energy Corp Deliverables Schedule ML20076H8811983-08-0909 August 1983 Expresses Appreciation for NRC Presentation on 10CFR21 & 10CFR50.55(e) Requirements.Info Should Be Most Useful to Personnel Involved in Project in Following Requirements ML20024E0391983-08-0505 August 1983 Forwards Errata Sheets for Applicant Prepared Testimony. Certificate of Svc Encl.Related Correspondence ML20077D1321983-07-25025 July 1983 Advises of Omission in Applicant 830722 Response Re CP Evidentiary Hearings.Hearings Did Not Commence on 830718 But Were Postponed Per 830713 Order.Order of 830719 Rescheduled Hearings for 830808-12.Certificate of Svc Encl ML20024D0291983-07-22022 July 1983 Forwards Clinch River Breeder Reactor Plant Sys Design Description - Nuclear Island HVAC Sys, as Example of Procedure Outlines Available for Performance of PRA ML20080A8311983-07-20020 July 1983 Opposes Plant Const Since Little Prior Experience Exists W/Breeder Reactor Design ML20024D5121983-07-19019 July 1983 Requests Specs for Electrical Power Cable Insulation to Be Used at Facility ML20077A5331983-07-19019 July 1983 Advises of Incorrectly Cited Ref on Page 1 of Attachment B & on Page 2 of Attachment C to .Certificate of Svc Encl ML20077H1911983-07-19019 July 1983 Responds to NRC Re Violations Noted in IE Insp Rept 50-537/83-05.Corrective actions:Westinghouse-Oak Ridge Audit Program Revised to Be Computerized Sys.Implementation Throughout Yr Will Be Measured by Planned Surveillances ML20072P1101983-07-15015 July 1983 Forwards Applicant Proposed Exhibit List for CP Hearings,For Review.Stipulation as to Authenticity & Admissibility Requested.Certificate of Svc Encl ML20024C1621983-07-0808 July 1983 Informs That Auxiliary Feedwater Sys Evaluation,Per PSAR App C,Section C.6.4 & App H,Section II.E.1.1,scheduled for Completion by mid-1985 ML20085A7291983-07-0606 July 1983 Forwards Rev 6 to Vol 2 to CRBRP-3, Assessment of Thermal Margin Beyond Design Base (Tmbdb) ML20105B9551983-07-0606 July 1983 Forwards Addl Info Per Request at 830610 Meeting on Programmatic Objectives Re Fuel Burnup.Fftf Operates W/Peak Burnup of Over 61,000 Megawatt Day/Mt.Burnup Occurred Under Temp & Power Conditions Similar to Crbr Conditions ML20079R7401983-06-23023 June 1983 Summarizes 830606 Meeting W/Crbr Project Personnel Re Schedule for Resolution of Confirmatory Items.All Identified Items & Preliminary Schedule Info Discussed.List of Attendees Encl ML20079R2661983-06-21021 June 1983 Lists Typographical & Transcription Errors in 830512 Deposition.Certificate of Svc Encl ML20024A6781983-06-20020 June 1983 Informs of Planned Optional Use of Mechanical Couplers for Reinforcing Bar Splice Sys in Nuclear Island Mat.Qa Program Will Be Established.Exception to ASME Code,Section III & Reg Guide 1.136 Requirements Encl ML20076J0951983-06-17017 June 1983 Summarizes Programmatic Objectives 830610 Meeting Re Fallbacks Identified in Chapter 4 of SER & Impact on Crbr Project.Viewgraphs & Supporting Documentation Encl ML20076J0511983-06-16016 June 1983 Advises That DOE Addressees Include Tj Garrish,L Silverstrom & Wd Luck.Rt Johnson & WE Bergholz Should Be Deleted from Svc List.Certificate of Svc Encl ML20023D9611983-05-27027 May 1983 Submits Agreements Reached at 830524 Meeting W/Crbr Project Re Pra.Description of Addl Tasks Needed to Integrate Plan I & II Efforts Encl ML20072B3431983-05-27027 May 1983 Forwards Crbr Erosion & Sediment Control Plan Rept, Providing Implementation Status of Control Plan Measures Currently Utilized ML20023D4031983-05-20020 May 1983 Forwards Amend 77 to PSAR ML20076D3151983-05-19019 May 1983 Forwards Rev 1 to Crbr Project Heat Transport Sys In-Containment Piping Reserve Seismic Margins & Rept Re Consequences of Leaks from Small Diameter Primary Heat Transport Sys Piping ML20076D2281983-05-17017 May 1983 Forwards Rev 5 to Vol 2 to Thermal Margin Beyond Design Base. Rev Incorporates Isotopic Inventory for Heterogeneous Core,Current Meteorology,Addl Organ Doses & More Realistic Pu Sparging Calculations ML20023C5821983-05-16016 May 1983 Submits Supplemental Info to 830401 Ltr Re Cable Separation by Confirming That Approx 75 Ft of DHR Svc & Steam Generator Auxiliary Heat Removal Sys Cable Will Be Run in Separate Conduits or Encl Raceways ML20079Q2881983-05-10010 May 1983 Forwards Corrected 830509 Response to NRDC & Sierra Club First Set of Interrogatories & Request to Produce Directed to Applicant.Original Document Not Identified as Response ML20024D9551983-05-0909 May 1983 Submits Estimate of LMFBR Safety & Licensing Review Needs Over Next Several Yrs.Preparation of Portions of FSAR Will Begin in 1984 1986-03-13
[Table view] Category:INTERNAL OR EXTERNAL MEMORANDUM
MONTHYEARML20137N2871986-01-0707 January 1986 Forwards Summary of Review of Monitored Retrievable Storage Conceptual Design Rept.Detailed Investigations Needed to Identify & Define Extent of Solution Cavities in Bedrock Beneath Site ML20138Q9041985-02-21021 February 1985 Submits Board Questions Re Identification of Alternate User for Site.Board Will Reschedule Conference Call or Establish New Procedure for Response to Questions IA-85-362, Submits Board Questions Re Identification of Alternate User for Site.Board Will Reschedule Conference Call or Establish New Procedure for Response to Questions1985-02-21021 February 1985 Submits Board Questions Re Identification of Alternate User for Site.Board Will Reschedule Conference Call or Establish New Procedure for Response to Questions ML20127C2941984-11-0707 November 1984 Comments on Applicant 841019 Motion to Dismiss Crbr Proceeding.Differences Between NRC Approved 840305 Crbr Site Redress Plan & Doe/Tva/Project Mgt Corp Site Redress Planning Task Force Rept Dtd Jan 1984 Encl ML20140C6121984-06-18018 June 1984 Advises That Time for Commission to Review ALAB-761 Expired. Commission Declined Review.Decision Became Final Agency Action on 840611.Served on 840618 ML20127B5921984-04-30030 April 1984 Submits Proposed Mods to 840305 Crbr Site Redress Plan. Redress Plan Should Be Revised to Reflect Alternative Use If Site Retained.Doe Should Rept Status of Site Prior to Starting Final Filling,Grading & Redress ML20138Q8991984-03-23023 March 1984 Requests That NRC Contact Be Identified & That Ode Be Advised Who Will Be Responsible for Followup Work Re Commission 820817 Memorandum & Order Concerning Site Redress.W/Three Oversize Encls ML20062G8321982-08-0606 August 1982 Clarifies Previous Response to ASLB Inquiries Re Computer Codes Used in Review of Site Suitability,Atmospheric Transport & Diffusion Calculations ML20062H2701982-07-28028 July 1982 Forwards Revised Crbr Rept,Initially Submitted on 820722 ML20058F7381982-07-26026 July 1982 Notification of 820805 Meeting W/Doe in Bethesda,Md to Discuss Crbr PSAR Chapter 9.3, Auxiliary Liquid Metal Sys. Proposed Agenda Encl ML20058E4481982-07-22022 July 1982 Forwards Crbr Plant Rept, Re Request for Authorization to Conduct Site Preparation Activities.Rept Identifies Technical & Policy Issues & Summarizes Background Info & Applicant Position.No Recommendations on Merit Made ML20058E4921982-07-20020 July 1982 Provides Cost Analysis of Crbr Proposal.Applicant Cost of Delay Estimate on Basis of 10% Real Discount Rate Evaluated. Table Depicting Present Worth Analysis of Anticipated Project Expenditures Encl ML20058A8581982-07-16016 July 1982 Notification of 820723 Meeting W/Doe in Bethesda,Md to Discuss Crbr Probabilistic Risk Assessment Review NUREG-0786, Summarizes ACRS 267th Meeting on 820708-10 Re NUREG-0786, Site Suitability Rept in Matter of Crbr. Crbr Can Be Designed So as to Present No Greater Risk than Lwr.Proposed Site Suitable1982-07-13013 July 1982 Summarizes ACRS 267th Meeting on 820708-10 Re NUREG-0786, Site Suitability Rept in Matter of Crbr. Crbr Can Be Designed So as to Present No Greater Risk than Lwr.Proposed Site Suitable ML20054M7621982-07-12012 July 1982 Forwards Commissioner Ahearne Questions for Applicants ML20054N0081982-07-0909 July 1982 Provides Status on NRC Preparation of Assessment of New Info Since Fes Issuance in 1977.NRC Still Evaluating New Info. Decision on Whether Suppl Needed to Be Made Shortly ML20055B2011982-07-0202 July 1982 Forwards Testimony in Facility Proceeding on Contention 6 Re Environ Impact of Fuel Cycle,Per 820623 Request ML20054L4271982-06-30030 June 1982 Notification of 820708 Meeting W/Doe in Bethesda,Md to Discuss Crbr Hydrology Review ML20054H7791982-06-22022 June 1982 Forwards Supplemental List of Questions on Steam Generator Design.Conference W/Applicant on Design Suggested ML20054H3931982-06-16016 June 1982 Notification of 820630 & 0701 Meetings W/Doe in Bethesda,Md to Discuss Smbdb Review ML20054F7331982-06-11011 June 1982 Forwards Site Sutitability Rept Re Site Suitability from Point of Radiological Health & Safety Concerns.Rept Supersedes NRC Mar 1977 Site Suitability Rept,Reflecting Changes in Info.Conclusions Remain Same.W/O Encl ML20055B2881982-06-10010 June 1982 Forwards Proposed Input to Chapter 9 & 10 to Crbr Fes Suppl. Info Reflects Comments Discussed Re Preliminary Draft ML20054E8061982-06-0909 June 1982 Notification of 820616-17 Meetings W/Doe in Bethesda,Md to Discuss Smbdb Review ML20054E7971982-06-0909 June 1982 Notification of 820622-24 Meetings W/Doe,Util & Project Mgt Corp in Oradell,Nj to Perform Seismic & Structural Engineering Audit of Calculations ML20054G0271982-06-0909 June 1982 Notification of Canceled 820616-17 Meetings W/Doe in Bethesda,Md to Discuss Smbdb Review ML20054H3371982-06-0808 June 1982 Comments on Gao Final Ltr Rept, Revising Crbr Steam Generator Testing Program Can Reduce Risk. DOE Rebuttal to Rept & Description of Test Program Encl.W/O Encl ML20054H3341982-06-0808 June 1982 Comments on Gao Final Ltr Rept, Revising Crbr Steam Generator Testing Program Can Reduce Risk. Also Forwards DOE Steam Generator Testing Program.W/O Encl ML20054F2771982-06-0808 June 1982 Notification of 820623 Meeting W/Doe in Bethesda,Md to Discuss Fuel Failure Monitoring Sys ML20055B2841982-06-0707 June 1982 Forwards Gao Final Ltr Rept Revising Crbr Steam Generator Testing Program Can Reduce Risk, in Response to Subcommittee on Oversight & Investigations,House Committee on Energy & Commerce Request.No Response Required ML20054M7861982-06-0202 June 1982 Notification of 820727 Meeting W/Doe in Madison,Pa to Discuss Chapter 5.5 Topics for Crbr.Agenda Encl ML20055B2901982-05-27027 May 1982 Discusses Proposed Changes to Chapter 11 of Fes Re Cost Estimates.Crbr Offers Least Cost Solution in Meeting Programmatic Objectives of LMFBR Program ML20055B2921982-05-10010 May 1982 Forwards Antitrust & Economic Analysis Branch Input to Accident Impact Section of Captioned Des ML20055B2931982-04-16016 April 1982 Responds to Interrogatories Set 19 Re Const Cost of Crbr ML20055B2941982-01-22022 January 1982 Comments on DOE Response to Question 9 of Applicant Responses to Questions Set Forth in Commission 811224 Order Re Estimate of Cost of Delay ML20133C7741981-12-0404 December 1981 Discusses Whether Requested Exemption to Allow Site Const in Advance of Environ Impact Analysis Would Significantly Affect Environ Under Nepa.Definition of Significant Discussed ML20065Q3961981-09-0202 September 1981 Advises That Listed Mods Made to Contac & Concept Computer Codes to Improve Usefulness & Accuracy of Concept Code 1986-01-07
[Table view] Category:MEMORANDUMS-CORRESPONDENCE
MONTHYEARML20137N2871986-01-0707 January 1986 Forwards Summary of Review of Monitored Retrievable Storage Conceptual Design Rept.Detailed Investigations Needed to Identify & Define Extent of Solution Cavities in Bedrock Beneath Site ML20138Q9041985-02-21021 February 1985 Submits Board Questions Re Identification of Alternate User for Site.Board Will Reschedule Conference Call or Establish New Procedure for Response to Questions IA-85-362, Submits Board Questions Re Identification of Alternate User for Site.Board Will Reschedule Conference Call or Establish New Procedure for Response to Questions1985-02-21021 February 1985 Submits Board Questions Re Identification of Alternate User for Site.Board Will Reschedule Conference Call or Establish New Procedure for Response to Questions ML20127C2941984-11-0707 November 1984 Comments on Applicant 841019 Motion to Dismiss Crbr Proceeding.Differences Between NRC Approved 840305 Crbr Site Redress Plan & Doe/Tva/Project Mgt Corp Site Redress Planning Task Force Rept Dtd Jan 1984 Encl ML20140C6121984-06-18018 June 1984 Advises That Time for Commission to Review ALAB-761 Expired. Commission Declined Review.Decision Became Final Agency Action on 840611.Served on 840618 ML20127B5921984-04-30030 April 1984 Submits Proposed Mods to 840305 Crbr Site Redress Plan. Redress Plan Should Be Revised to Reflect Alternative Use If Site Retained.Doe Should Rept Status of Site Prior to Starting Final Filling,Grading & Redress ML20138Q8991984-03-23023 March 1984 Requests That NRC Contact Be Identified & That Ode Be Advised Who Will Be Responsible for Followup Work Re Commission 820817 Memorandum & Order Concerning Site Redress.W/Three Oversize Encls ML20062G8321982-08-0606 August 1982 Clarifies Previous Response to ASLB Inquiries Re Computer Codes Used in Review of Site Suitability,Atmospheric Transport & Diffusion Calculations ML20062H2701982-07-28028 July 1982 Forwards Revised Crbr Rept,Initially Submitted on 820722 ML20058F7381982-07-26026 July 1982 Notification of 820805 Meeting W/Doe in Bethesda,Md to Discuss Crbr PSAR Chapter 9.3, Auxiliary Liquid Metal Sys. Proposed Agenda Encl ML20062E2281982-07-26026 July 1982 Staff Requirements Memo Re 820721 Affirmation/Discussion Session Approving Order Directing DOE to Respond by 820728 to Allegations in Petition for Investigation,Filed by NRDC on Sierra Club ML20058E4481982-07-22022 July 1982 Forwards Crbr Plant Rept, Re Request for Authorization to Conduct Site Preparation Activities.Rept Identifies Technical & Policy Issues & Summarizes Background Info & Applicant Position.No Recommendations on Merit Made ML20058E4921982-07-20020 July 1982 Provides Cost Analysis of Crbr Proposal.Applicant Cost of Delay Estimate on Basis of 10% Real Discount Rate Evaluated. Table Depicting Present Worth Analysis of Anticipated Project Expenditures Encl ML20058A8581982-07-16016 July 1982 Notification of 820723 Meeting W/Doe in Bethesda,Md to Discuss Crbr Probabilistic Risk Assessment Review NUREG-0786, Summarizes ACRS 267th Meeting on 820708-10 Re NUREG-0786, Site Suitability Rept in Matter of Crbr. Crbr Can Be Designed So as to Present No Greater Risk than Lwr.Proposed Site Suitable1982-07-13013 July 1982 Summarizes ACRS 267th Meeting on 820708-10 Re NUREG-0786, Site Suitability Rept in Matter of Crbr. Crbr Can Be Designed So as to Present No Greater Risk than Lwr.Proposed Site Suitable ML20054M7621982-07-12012 July 1982 Forwards Commissioner Ahearne Questions for Applicants ML20054N0081982-07-0909 July 1982 Provides Status on NRC Preparation of Assessment of New Info Since Fes Issuance in 1977.NRC Still Evaluating New Info. Decision on Whether Suppl Needed to Be Made Shortly ML20055B2011982-07-0202 July 1982 Forwards Testimony in Facility Proceeding on Contention 6 Re Environ Impact of Fuel Cycle,Per 820623 Request ML20054L4271982-06-30030 June 1982 Notification of 820708 Meeting W/Doe in Bethesda,Md to Discuss Crbr Hydrology Review ML20054H7791982-06-22022 June 1982 Forwards Supplemental List of Questions on Steam Generator Design.Conference W/Applicant on Design Suggested ML20054H3931982-06-16016 June 1982 Notification of 820630 & 0701 Meetings W/Doe in Bethesda,Md to Discuss Smbdb Review ML20054F7331982-06-11011 June 1982 Forwards Site Sutitability Rept Re Site Suitability from Point of Radiological Health & Safety Concerns.Rept Supersedes NRC Mar 1977 Site Suitability Rept,Reflecting Changes in Info.Conclusions Remain Same.W/O Encl ML20055B2881982-06-10010 June 1982 Forwards Proposed Input to Chapter 9 & 10 to Crbr Fes Suppl. Info Reflects Comments Discussed Re Preliminary Draft ML20054E8061982-06-0909 June 1982 Notification of 820616-17 Meetings W/Doe in Bethesda,Md to Discuss Smbdb Review ML20054E7971982-06-0909 June 1982 Notification of 820622-24 Meetings W/Doe,Util & Project Mgt Corp in Oradell,Nj to Perform Seismic & Structural Engineering Audit of Calculations ML20054G0271982-06-0909 June 1982 Notification of Canceled 820616-17 Meetings W/Doe in Bethesda,Md to Discuss Smbdb Review ML20054H3371982-06-0808 June 1982 Comments on Gao Final Ltr Rept, Revising Crbr Steam Generator Testing Program Can Reduce Risk. DOE Rebuttal to Rept & Description of Test Program Encl.W/O Encl ML20054H3341982-06-0808 June 1982 Comments on Gao Final Ltr Rept, Revising Crbr Steam Generator Testing Program Can Reduce Risk. Also Forwards DOE Steam Generator Testing Program.W/O Encl ML20054F2771982-06-0808 June 1982 Notification of 820623 Meeting W/Doe in Bethesda,Md to Discuss Fuel Failure Monitoring Sys ML20055B2841982-06-0707 June 1982 Forwards Gao Final Ltr Rept Revising Crbr Steam Generator Testing Program Can Reduce Risk, in Response to Subcommittee on Oversight & Investigations,House Committee on Energy & Commerce Request.No Response Required ML20054M7861982-06-0202 June 1982 Notification of 820727 Meeting W/Doe in Madison,Pa to Discuss Chapter 5.5 Topics for Crbr.Agenda Encl ML20055B2901982-05-27027 May 1982 Discusses Proposed Changes to Chapter 11 of Fes Re Cost Estimates.Crbr Offers Least Cost Solution in Meeting Programmatic Objectives of LMFBR Program ML20055B2921982-05-10010 May 1982 Forwards Antitrust & Economic Analysis Branch Input to Accident Impact Section of Captioned Des ML20055B2931982-04-16016 April 1982 Responds to Interrogatories Set 19 Re Const Cost of Crbr ML20055B2941982-01-22022 January 1982 Comments on DOE Response to Question 9 of Applicant Responses to Questions Set Forth in Commission 811224 Order Re Estimate of Cost of Delay ML20133C7741981-12-0404 December 1981 Discusses Whether Requested Exemption to Allow Site Const in Advance of Environ Impact Analysis Would Significantly Affect Environ Under Nepa.Definition of Significant Discussed ML20065Q3961981-09-0202 September 1981 Advises That Listed Mods Made to Contac & Concept Computer Codes to Improve Usefulness & Accuracy of Concept Code 1986-01-07
[Table view] |
Text
.
0
[A M0 o.
. UNITED STATES E" N NUCLEAR REGULATORY COMMISSION f ;e ADVISORY COMMITTEE ON REACTOR SAFEGUARDS
- WASHINGTON, D. C. 20555 a o
%*****/ July 13,1982 1
Honorable Nunzio J. Palladino Chairman ~
U.S. Nuclear Regulatory Commission Washington, D.C. 20555 l
Dear Dr. Palladino:
i
SUBJECT:
ACRS REPORT ON THE SUITABILITY OF iHE CLINCH RIVER BREEDER REACTOR PLANT SITE During its 267th meeting, July 8-10, 1982, the ACRS reviewed NUREG-0786,
" Site Suitability Report in the Matter of Clinch River Breeder Reactor Plant" and considered the suitability of the proposed site for such a plant.
The matter was also discussed on June 24, 1982 at a joint meeting of the Subcommittees on Clinch River Breeder Reactor and Site Evaluation. During both meetings, we had the benefit of input from representatives of the NRC Staff and the Department of Energy (Applicant). We also had the benefit of the documents listed below, as well as a direct discussion with the author of Reference 4.
The proposed Clinch River Breeder Reactor (CRBR) plant site is located in Roane County in east-central Tennessee, approximately 25 miles west of Knoxville and within the city limits of Oak Ridge, Tennessee. The site consists of approximately 1,364 land acres on a peninsula formed by a meander in the Clinch River. It is bounded on three sides by the River and on the north by the Department of Energy's (00E) Oak Ridge Reservation. The site property is owned by the Federal Government, and the portions of the site required for constructing and operating the plant will fall under the custody of DOE.
The CRBR plant will be a single-unit electric power plant with a liquid sodium-cooled loop-type breeder reactor utilizing a fuel of mixed uranium-plutonium oxides. With the initial reactor core, the design power will be 975 MWt, and the net output will be 350 MWe.
DOE has requested a Limited Work Authorization (LWA-1) to begin nonsafety-related site preparation activities. It is required in 10 CFR 50.10 that, before an LWA-1 can be granted, an Atomic Safety and Licensing Board (ASLB) must determine that there is reasonable assurance that the proposed site is a suitable location from a radiological health and safety standpoint for a nuclear power reactor of the general size and type proposed. Our review was made in response to an NRC Staff request in connection with the required ASLB determination. The NRC Staff carefully defined the scope of the review to consider whether the site is suitable for a reactor "of the general size and type" of the CRBR; the current design of the CRBR plant itself was not evaluated.
8208040467 820726 PDR ADOCK 05000537 PDR A
Honorable Nunzio J. Palladino July 13,1982 Among the topics considered in this review were the location and distribu-tion of population around the site; the geology, seismology, and hydrology of the site; an assumed Site Suitability Source Term; and the risks to be expected fcom a plant of the CRBR type.
As part of its approach to trying to make the risks from an LMFBR comparable with those from a light water reactor (LWR), the NRC Staff provided review criteria for CRBR core disruptive accidents. We believe that this appears to be a reasonable first approach but also believe that at the construction permit stage substantive assurance will be needed that such criteria are being met. We wish to note that we do not necessarily agree with all the LMFBR Design Criteria specified in Appendix A of NUREG-0786.
The NRC Staff appears to have accepted the Applicant's assertion that a CRBR type plant would not represent an undue hazard to the K-25 Plant. We recommend that the Staff confirm through an independent assessment that the potential effects of a CRBR type plant on the K-25 plant are acceptable.
With regard to the seismic design of this plant, we believe it is important that the combination of seismic design basis and margins in the seismic design be such that this accident source represents an acceptably low contribution to the overall risk from the plant. We believe this matter will warrant detailed examination at the construction permit stage to assure that necessary margins are available for all important systems and compon-ents.
The NRC Staff has concluded that the CRBR plant can be designed and con-structed in such a manner that it will present no greater risk to the health and safety of the public than an LWR plant meeting current safety criteria.
We believe that the proposed site is suitable for such a plant.
Sincerely,
\.
P. Shewmon Chai rman References
- 1. U.S. Nuclear Regulatory Commission, " Site Suitability Report in the Matter of Clinch River Breeder Reactor Plant," NUREG-0786, dated June 1982, Revision to March 4,1977 Report
- 2. Letter from J. R. Longenecker, DOE, to P. Boehnert, ACRS, concerning earthquake recursion relationships, dated July 7,1982
- 3. Handout from NRC Staff (undated) titled, " Review Criteria for CRBR Core Disruptive Accidents"
- 4. Letter from T. B. Cochran, National Resources Defense Council to P. Shewmon, ACRS, dated July 7,1982
--