NRC 2005-0156, Request for Withholding of Proprietary Information from Public Disclosure

From kanterella
Jump to navigation Jump to search
Request for Withholding of Proprietary Information from Public Disclosure
ML060040018
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 12/20/2005
From: Koehl D
Nuclear Management Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NRC 2005-0156
Download: ML060040018 (2)


Text

Committed to Nuclear Excellen Point Beach Nuclear Plant Operated by Nuclear Management Company, LLC December 20, 2005 NRC 2005-0156 10 CFR 2.390 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 Point Beach Nuclear Plant, Units 1 and 2 Dockets 50-266 and 50-301 License Nos. DPR-24 and DPR-27 Reauest for Withholding of Proprietary Information from Public Disclosure

Reference:

Letter from NMC to NRC dated November 18, 2005 (NRC 2005-0148)

In the referenced letter, Nuclear Management Company, LLC (NMC), provided revised Westinghouse Report WEP-05-168, Revision 1-NP, "Point Beach Unit 1, Cycle 29 - Reactor Vessel Upper Closure Head Volume Best-Estimate Mean Fluid Temperature", dated June 20, 2005.

During subsequent discussions between NRC staff and NMC personnel, the staff requested additional justification supporting the withholding of the value for the mean fluid temperature of the reactor vessel upper closure head volume. The enclosure to this letter provides Westinghouse document LTR-RCDA-873-NP Attachment, dated December 14, 2005, which contains the requested additional justification.

Since the document listed above contains additional justification regarding the withholding of information proprietary to Westinghouse Electric Company, it is supported by an affidavit signed by Westinghouse, the owner of the information. The affidavit sets forth the basis on which the information may be withheld from public disclosure by the Commission and addresses with specificity, for each, the considerations listed in paragraph (b)(4) of Section 2.390 of the Commission's regulations.

Accordingly, it is respectfully requested that the information, which is proprietary to Westinghouse, be withheld from public disclosure in accordance with 10 CFR 2.390.

Correspondence with respect to the above document, or the supporting Westinghouse affidavit, should reference the appropriate authorization letter (CAW-05-2087) and be addressed to J. A. Gresham, Manager of Regulatory Compliance and Plant Licensing, Westinghouse Electric Company, P.O. Box 355, Pittsburgh, Pennsylvania 15230-0355.

6590 Nuclear Road

  • Two Rivers, Wisconsin 54241 Telephone: 920.755.2321

Document Control Desk Page 2 This letter contains no new commitments and no revisions to existing commitments.

I declare under penalty of perjury that the foregoing is true and correct. Executed on December 20, 2005.

Dennis L. Koehl Site Vice-President, Point Beach Nuclear Plant Nuclear Management Company, LLC cc:

Project Manager, Point Beach Nuclear Plant, USNRC Regional Administrator, Region III, USNRC Resident Inspector, Point Beach Nuclear Plant, USNRC