Similar Documents at Fermi |
---|
Category:LICENSEE EVENT REPORT (SEE ALSO AO
MONTHYEARNRC-94-0025, LER 93-014-01:on 931225,turbine Generator Tripped When Mechanical Overspeed Device Was Activated.Caused by Severe Vibration.Corrective Action:Assessment of Structural Integrity of Pedestal Was conducted.W/940425 Ltr1994-04-25025 April 1994 LER 93-014-01:on 931225,turbine Generator Tripped When Mechanical Overspeed Device Was Activated.Caused by Severe Vibration.Corrective Action:Assessment of Structural Integrity of Pedestal Was conducted.W/940425 Ltr NRC-93-0058, LER 93-008-00:on 930518,discovered That Recorder T50-R802A Could Not Be Considered Operable Per TS 3.3.7.5.Caused by Personnel Error.Lessons Learned Will Be Incorporated Into Training Programs & Plant procedures.W/930618 Ltr1993-06-18018 June 1993 LER 93-008-00:on 930518,discovered That Recorder T50-R802A Could Not Be Considered Operable Per TS 3.3.7.5.Caused by Personnel Error.Lessons Learned Will Be Incorporated Into Training Programs & Plant procedures.W/930618 Ltr NRC-93-0055, LER 93-007-00:on 930420,reactor Tripped on Intermediate Range Monitor Upscale During Reactor Pressure & Feedwater Transient.Caused by Personnel Error.Affected Pressure Transmitters replaced.W/930520 Ltr1993-05-20020 May 1993 LER 93-007-00:on 930420,reactor Tripped on Intermediate Range Monitor Upscale During Reactor Pressure & Feedwater Transient.Caused by Personnel Error.Affected Pressure Transmitters replaced.W/930520 Ltr NRC-91-0058, LER 91-008-00:on 910424,reactor Bldg HVAC Tripped,Div I SGTS Auto Started & Div I Control Ctr HVAC Shifted to Recirculation Mode Due to Mispositioned Trip Output Logic switch.W/910524 Ltr1991-05-24024 May 1991 LER 91-008-00:on 910424,reactor Bldg HVAC Tripped,Div I SGTS Auto Started & Div I Control Ctr HVAC Shifted to Recirculation Mode Due to Mispositioned Trip Output Logic switch.W/910524 Ltr NRC-91-0069, LER 90-012-01:on 901016,HPIC Steam Line Flow Transmitter Failed Due to Short Circuit Across Capacitor Plates.Circuit Boards Replaced & Failure Analysis Performed by Rosemount,Inc.W/910524 Ltr1991-05-24024 May 1991 LER 90-012-01:on 901016,HPIC Steam Line Flow Transmitter Failed Due to Short Circuit Across Capacitor Plates.Circuit Boards Replaced & Failure Analysis Performed by Rosemount,Inc.W/910524 Ltr NRC-91-0055, LER 91-006-00:on 910410,balance of Plant Breaker Opened Causing Reactor Bldg HVAC Isolation.Caused by Component Failures.Nprds Search Conducted for Similiar Problems. W/910510 Ltr1991-05-10010 May 1991 LER 91-006-00:on 910410,balance of Plant Breaker Opened Causing Reactor Bldg HVAC Isolation.Caused by Component Failures.Nprds Search Conducted for Similiar Problems. W/910510 Ltr NRC-91-0004, LER 90-013-00:on 901228,determined That Inadequate Control Could Occur During Air Grab Sampling Process.Caused by Lack of Proper Administrative Controls in Sampling Procedure. Sample Suction added.W/910128 Ltr1991-01-28028 January 1991 LER 90-013-00:on 901228,determined That Inadequate Control Could Occur During Air Grab Sampling Process.Caused by Lack of Proper Administrative Controls in Sampling Procedure. Sample Suction added.W/910128 Ltr NRC-90-0144, LER 90-007-00:on 900829,control Ctr Ventilation Shifted to Recirculation Due to Blown Fuse.Caused by Design Deficiency in Div 1 & 2 Radiation Monitor Trip Circuitry.Design Change Implemented to Eliminate Trip Relay logic.W/900928 Ltr1990-09-28028 September 1990 LER 90-007-00:on 900829,control Ctr Ventilation Shifted to Recirculation Due to Blown Fuse.Caused by Design Deficiency in Div 1 & 2 Radiation Monitor Trip Circuitry.Design Change Implemented to Eliminate Trip Relay logic.W/900928 Ltr NRC-90-0107, LER 88-034-01:on 880831,RWCU Outboard Isolation Valve Closed,Causing RWCU Pumps to Trip.Caused by Loss of Continuity to Relay Due to Deposits Built Up on Surface of Contacts.Relay in Isolation Circuits replaced.W/900622 Ltr1990-06-22022 June 1990 LER 88-034-01:on 880831,RWCU Outboard Isolation Valve Closed,Causing RWCU Pumps to Trip.Caused by Loss of Continuity to Relay Due to Deposits Built Up on Surface of Contacts.Relay in Isolation Circuits replaced.W/900622 Ltr NRC-90-0087, LER 90-002-01:on 900202,determined That Area Radiation Surveillance Procedure 44.080.301 Listed Incorrect Values for Alarm Setpoints.Caused by Unavailable Setpoint Calculations.Procedure revised.W/900608 Ltr1990-06-0808 June 1990 LER 90-002-01:on 900202,determined That Area Radiation Surveillance Procedure 44.080.301 Listed Incorrect Values for Alarm Setpoints.Caused by Unavailable Setpoint Calculations.Procedure revised.W/900608 Ltr NRC-90-0075, LER 87-045-02:on 870908,operator Removed Fuse Which Deenergized Dc Control Power to Bus 72C,resulting in Loss of Power Supply to Swing Bus & to LPCI Loop Selection Valves. Caused by Design Flaw.Design Change initiated.W/900518 Ltr1990-05-18018 May 1990 LER 87-045-02:on 870908,operator Removed Fuse Which Deenergized Dc Control Power to Bus 72C,resulting in Loss of Power Supply to Swing Bus & to LPCI Loop Selection Valves. Caused by Design Flaw.Design Change initiated.W/900518 Ltr NRC-90-0073, LER 90-003-00:on 900410,Div I Reactor Protection Sys Power Supply Failure & Subsequent MSIV Closure.Caused by Coil Burn Up.Relays Replaced & MG Sets Returned to svc.W/900508 Ltr1990-05-0808 May 1990 LER 90-003-00:on 900410,Div I Reactor Protection Sys Power Supply Failure & Subsequent MSIV Closure.Caused by Coil Burn Up.Relays Replaced & MG Sets Returned to svc.W/900508 Ltr NRC-90-0048, LER 89-037-01:on 891220,determined That Tech Spec Stroke Time Testing for Outboard Reactor Water Sample Line Isolation Valve Not Performed Prior to Expiration on 891125. Caused by Personnel Error.Procedure revised.W/900322 Ltr1990-03-22022 March 1990 LER 89-037-01:on 891220,determined That Tech Spec Stroke Time Testing for Outboard Reactor Water Sample Line Isolation Valve Not Performed Prior to Expiration on 891125. Caused by Personnel Error.Procedure revised.W/900322 Ltr NRC-90-0027, LER 89-034-01:on 891208,two Members of Fire Watch Did Not Complete Assigned Hourly Rounds from 891002-1207 in Reactor & Auxiliary Bldgs.Both Individuals Terminated & Fire Stations Equipped W/Unique Bar code.W/900221 Ltr1990-02-21021 February 1990 LER 89-034-01:on 891208,two Members of Fire Watch Did Not Complete Assigned Hourly Rounds from 891002-1207 in Reactor & Auxiliary Bldgs.Both Individuals Terminated & Fire Stations Equipped W/Unique Bar code.W/900221 Ltr NRC-90-0021, LER 90-001-00:on 900108,annunciator 2D5 Alarmed for Div II ECCS Testability Logic/Power Failure.Caused by Blown Fuse. Fuse Installed During Course of Troubleshooting W/No Subsequent Problems noted.W/900207 Ltr1990-02-0707 February 1990 LER 90-001-00:on 900108,annunciator 2D5 Alarmed for Div II ECCS Testability Logic/Power Failure.Caused by Blown Fuse. Fuse Installed During Course of Troubleshooting W/No Subsequent Problems noted.W/900207 Ltr NRC-90-0019, LER 89-028-01:on 891028,eight Safety Relief Valves Failed Set Pressure Tolerance Test.Cause Under Review by Util & Generically by BWR Owners Group Safety Relief Valve Set Point Drift Committee.Valves Removed & cleaned.W/900131 Ltr1990-01-31031 January 1990 LER 89-028-01:on 891028,eight Safety Relief Valves Failed Set Pressure Tolerance Test.Cause Under Review by Util & Generically by BWR Owners Group Safety Relief Valve Set Point Drift Committee.Valves Removed & cleaned.W/900131 Ltr NRC-90-0018, LER 89-039-00:on 891226,Div I Emergency Equipment Cooling Water & Svc Water Sys Automatically Started Due to Partial Load Shed of Bus 72E.Caused by Personnel Error. Accountability Meeting Held on 900117.W/900125 Ltr1990-01-25025 January 1990 LER 89-039-00:on 891226,Div I Emergency Equipment Cooling Water & Svc Water Sys Automatically Started Due to Partial Load Shed of Bus 72E.Caused by Personnel Error. Accountability Meeting Held on 900117.W/900125 Ltr NRC-90-0008, LER 89-037-00:on 891220,determined That Tech Spec Stroke Time Testing for Outboard Reactor Water Sample Line Isolation Valve Not Performed.Caused by Personnel Error. Critique of Event Being developed.W/900119 Ltr1990-01-19019 January 1990 LER 89-037-00:on 891220,determined That Tech Spec Stroke Time Testing for Outboard Reactor Water Sample Line Isolation Valve Not Performed.Caused by Personnel Error. Critique of Event Being developed.W/900119 Ltr NRC-90-0007, LER 89-036-00:on 891218,control Room Operator Inadvertently Depressed Closed Push Buttons on Inboard MSIVs A,B & C & Reactor Scram Resulted.Caused by Operator Error.Operator Involved Was Removed from Licensed duties.W/900117 Ltr1990-01-17017 January 1990 LER 89-036-00:on 891218,control Room Operator Inadvertently Depressed Closed Push Buttons on Inboard MSIVs A,B & C & Reactor Scram Resulted.Caused by Operator Error.Operator Involved Was Removed from Licensed duties.W/900117 Ltr ML19354E0971990-01-12012 January 1990 LER 89-038-00:on 891223,reactor Scrammed When Fire Occurred in Vicinity of High Pressure Turbine.Caused by Oil Soaked Inlagging Pads & Ignited When Turbine Casing Heated Up to Oil Flashpoint.Insulation Pads replaced.W/900122 Ltr NRC-90-0005, LER 89-035-00:on 891210,steam Jet Air Ejectors Placed in Svc W/O Required Surveillance Completed & Required Grab Sample Not Started Until 891213.Caused by Personnel Error.Off Gas Sys Operating Procedure Will Be revised.W/900111 Ltr1990-01-11011 January 1990 LER 89-035-00:on 891210,steam Jet Air Ejectors Placed in Svc W/O Required Surveillance Completed & Required Grab Sample Not Started Until 891213.Caused by Personnel Error.Off Gas Sys Operating Procedure Will Be revised.W/900111 Ltr NRC-90-0004, LER 89-030-00:on 891026,Channel C Level 1 & 2 Replacement Transmitter Found to Be Installed Incorrectly & Condition Recognized on 891210,when Level 2 Trip Unit Was Reading Upscale.Caused by Personnel error.W/900109 Ltr1990-01-0909 January 1990 LER 89-030-00:on 891026,Channel C Level 1 & 2 Replacement Transmitter Found to Be Installed Incorrectly & Condition Recognized on 891210,when Level 2 Trip Unit Was Reading Upscale.Caused by Personnel error.W/900109 Ltr NRC-90-0002, LER 89-033-00:on 891207,volt-ohm Meter Connected to Incorrect Terminal,Causing Div II of Emergency Equipment Cooling Water Sys to Actuate.Caused by Personnel Error.Sys Secured & Channel Test Successfully completed.W/900108 Ltr1990-01-0808 January 1990 LER 89-033-00:on 891207,volt-ohm Meter Connected to Incorrect Terminal,Causing Div II of Emergency Equipment Cooling Water Sys to Actuate.Caused by Personnel Error.Sys Secured & Channel Test Successfully completed.W/900108 Ltr NRC-90-0003, LER 89-034-00:on 891208,review of Key Card Transactions Showed That Fire Watch Personnel Missed Assigned Hourly Fire Watch from 891020-1207.Fire Watch Person Discharged.Plan Re Improvement of Fire Watches developed.W/900108 Ltr1990-01-0808 January 1990 LER 89-034-00:on 891208,review of Key Card Transactions Showed That Fire Watch Personnel Missed Assigned Hourly Fire Watch from 891020-1207.Fire Watch Person Discharged.Plan Re Improvement of Fire Watches developed.W/900108 Ltr NRC-89-0261, LER 89-028-00:on 891129,ESF Actuations Occurred During Set Up for Surveillance.Caused by Blown Fuse.Blown Fuse Replaced & Affected Sys Returned to Normal Operation Following Completion of surveillance.W/891228 Ltr1989-12-28028 December 1989 LER 89-028-00:on 891129,ESF Actuations Occurred During Set Up for Surveillance.Caused by Blown Fuse.Blown Fuse Replaced & Affected Sys Returned to Normal Operation Following Completion of surveillance.W/891228 Ltr NRC-89-0260, LER 89-021-01:on 890906,35 of 237 Containment Isolation Valves Exceeded Administrative Allowable Leakage Rate When Tested.Caused by Normal Wear & Degradation During Specified Time Interval.Valves Cleaned & repaired.W/891221 Ltr1989-12-21021 December 1989 LER 89-021-01:on 890906,35 of 237 Containment Isolation Valves Exceeded Administrative Allowable Leakage Rate When Tested.Caused by Normal Wear & Degradation During Specified Time Interval.Valves Cleaned & repaired.W/891221 Ltr NRC-89-0255, LER 89-031-00:on 891120,both Div II Emergency Equipment Cooling Water (EECW) & Emergency Equipment Svc Water Sys Pumps Tripped Immediately.Caused by Inadequacies in Stated Procedures.Procedures revised.W/891220 Ltr1989-12-20020 December 1989 LER 89-031-00:on 891120,both Div II Emergency Equipment Cooling Water (EECW) & Emergency Equipment Svc Water Sys Pumps Tripped Immediately.Caused by Inadequacies in Stated Procedures.Procedures revised.W/891220 Ltr NRC-89-0259, LER 89-017-01:on 890810,new Analysis of Feedwater Line Break Scenario Assumes Failure of Feedwater Startup Control Valve in Open Position.Review of Pipe Break Documentation Conducted.Updated FSAR Change to Be submitted.W/891215 Ltr1989-12-15015 December 1989 LER 89-017-01:on 890810,new Analysis of Feedwater Line Break Scenario Assumes Failure of Feedwater Startup Control Valve in Open Position.Review of Pipe Break Documentation Conducted.Updated FSAR Change to Be submitted.W/891215 Ltr NRC-89-0256, LER 89-022-01:on 890923 & 24,reactor Protection Sys Logic Actuations Occurred When Fuse C71A-F15B Blew.On 890928, Reactor Bldg HVAC Isolated.Caused by Personnel Error. Procedures Will Be revised.W/891215 Ltr1989-12-15015 December 1989 LER 89-022-01:on 890923 & 24,reactor Protection Sys Logic Actuations Occurred When Fuse C71A-F15B Blew.On 890928, Reactor Bldg HVAC Isolated.Caused by Personnel Error. Procedures Will Be revised.W/891215 Ltr NRC-89-0258, LER 89-025-00:on 891115,low Level 2 Signal Unintentionally Induced During Reactor Pressure Vessel Hydrostatic Pressure Test.Caused by Personnel Error.Personnel Counseled on Notifying & Coordinating Instrument lineups.W/891215 Ltr1989-12-15015 December 1989 LER 89-025-00:on 891115,low Level 2 Signal Unintentionally Induced During Reactor Pressure Vessel Hydrostatic Pressure Test.Caused by Personnel Error.Personnel Counseled on Notifying & Coordinating Instrument lineups.W/891215 Ltr NRC-89-0251, LER 89-019-01:on 890819,discovered That Div I Recirculation Fan Not Rotating Which Resulted in Decrease in Control Room Air Pressure.Caused by Lack of Lubrication in Bearings. Lubrication Program Improvements evaluated.W/891130 Ltr1989-11-30030 November 1989 LER 89-019-01:on 890819,discovered That Div I Recirculation Fan Not Rotating Which Resulted in Decrease in Control Room Air Pressure.Caused by Lack of Lubrication in Bearings. Lubrication Program Improvements evaluated.W/891130 Ltr NRC-89-0249, LER 89-029-00:on 891023,half Scram Signal Received When Power Was Lost on Reactor Protection Sys Bus B,Resulting in Several ESFs Actuation.Caused by Location of Breaker Operating Switch in High Traffic area.W/891122 Ltr1989-11-22022 November 1989 LER 89-029-00:on 891023,half Scram Signal Received When Power Was Lost on Reactor Protection Sys Bus B,Resulting in Several ESFs Actuation.Caused by Location of Breaker Operating Switch in High Traffic area.W/891122 Ltr NRC-89-0246, LER 89-028-00:on 891020,eight safety-related Valves Failed Set Pressure Test.Cause Under Review.All Valves Removed for Testing Being Refurbished,Cleaned,Retested & Recertified to Be within Plant Accepted tolerances.W/891120 Ltr1989-11-20020 November 1989 LER 89-028-00:on 891020,eight safety-related Valves Failed Set Pressure Test.Cause Under Review.All Valves Removed for Testing Being Refurbished,Cleaned,Retested & Recertified to Be within Plant Accepted tolerances.W/891120 Ltr NRC-89-0244, LER 89-024-00:on 891019,recognized That Secondary Containment Dampers Not Tested as Required by Tech Spec 3.6.5.2.Caused by Operations Personnel Error.Event Critique to Be Included in Required Reading program.W/891120 Ltr1989-11-20020 November 1989 LER 89-024-00:on 891019,recognized That Secondary Containment Dampers Not Tested as Required by Tech Spec 3.6.5.2.Caused by Operations Personnel Error.Event Critique to Be Included in Required Reading program.W/891120 Ltr NRC-89-0194, LER 89-027-00:on 891015,reactor Bldg Hvac,Control Ctr HVAC & Drywell Floor & Equipment Drain Sumps Isolated & Standby Gas Treatment Sys & Noninterrruptalbe Control Air Compressors Started.Caused by Personnel error.W/891114 Ltr1989-11-14014 November 1989 LER 89-027-00:on 891015,reactor Bldg Hvac,Control Ctr HVAC & Drywell Floor & Equipment Drain Sumps Isolated & Standby Gas Treatment Sys & Noninterrruptalbe Control Air Compressors Started.Caused by Personnel error.W/891114 Ltr NRC-89-0193, LER 89-026-00:on 891010,control Ctr HVAC Shifted to Recirculation Mode of Operaton Due to Short Circuit.Caused by Failure of Lamp Filament When Being Tightened.Fuse & Lamp Replaced & Sys Returned to Normal operation.W/891109 Ltr1989-11-0909 November 1989 LER 89-026-00:on 891010,control Ctr HVAC Shifted to Recirculation Mode of Operaton Due to Short Circuit.Caused by Failure of Lamp Filament When Being Tightened.Fuse & Lamp Replaced & Sys Returned to Normal operation.W/891109 Ltr NRC-89-0192, LER 87-045-01:on 870908,fuse Removed Which Deenergized Dc Control Power to Bus 72C & Resulted in Loss of Power Supply to Swing Bus & LPCI Loop Selection Valves.Caused by Design Error.Undervoltage Relay Added & Training held.W/891106 Ltr1989-11-0606 November 1989 LER 87-045-01:on 870908,fuse Removed Which Deenergized Dc Control Power to Bus 72C & Resulted in Loss of Power Supply to Swing Bus & LPCI Loop Selection Valves.Caused by Design Error.Undervoltage Relay Added & Training held.W/891106 Ltr NRC-89-0190, LER 89-023-00:on 890924,personnel Inadvertently Caused Trip of Essential Safety Sys Buses 64B & 64C.Caused by Failure of Personnel Involved to Review Applicable Prints Prior to Performing Test.Event Reviewed w/personnel.W/891024 Ltr1989-10-24024 October 1989 LER 89-023-00:on 890924,personnel Inadvertently Caused Trip of Essential Safety Sys Buses 64B & 64C.Caused by Failure of Personnel Involved to Review Applicable Prints Prior to Performing Test.Event Reviewed w/personnel.W/891024 Ltr NRC-89-0189, LER 89-022-00:on 890923 & 24,reactor Protection Sys Logic Actuations Occurred When Fuse Blew.On 890928,reactor Bldg HVAC Isolated When Jumper Lifted Per Incorrect Work Plan Instruction.Caused by Personnel error.W/891023 Ltr1989-10-23023 October 1989 LER 89-022-00:on 890923 & 24,reactor Protection Sys Logic Actuations Occurred When Fuse Blew.On 890928,reactor Bldg HVAC Isolated When Jumper Lifted Per Incorrect Work Plan Instruction.Caused by Personnel error.W/891023 Ltr NRC-89-0186, LER 89-016-01:on 890711,Div 1 of RHR Svc Water Sys Declared Inoperable Due to Low Nitrogen Pressure for Cooling Tower Fan Brake.Caused by Leak in One Hose.Leaking Hose Replaced & Nitrogen Pressure restored.W/891006 Ltr1989-10-0606 October 1989 LER 89-016-01:on 890711,Div 1 of RHR Svc Water Sys Declared Inoperable Due to Low Nitrogen Pressure for Cooling Tower Fan Brake.Caused by Leak in One Hose.Leaking Hose Replaced & Nitrogen Pressure restored.W/891006 Ltr NRC-89-0185, LER 89-021-00:on 890906,local Leak Rate Testing of Containment Isolation Valves & Penetrations Exceeded Tech Spec Limit.Caused by Excessive Containment Isolation Valve Leakage Due to Degradation of valve.W/891006 Ltr1989-10-0606 October 1989 LER 89-021-00:on 890906,local Leak Rate Testing of Containment Isolation Valves & Penetrations Exceeded Tech Spec Limit.Caused by Excessive Containment Isolation Valve Leakage Due to Degradation of valve.W/891006 Ltr 1994-04-25
[Table view] Category:RO)
MONTHYEARNRC-94-0025, LER 93-014-01:on 931225,turbine Generator Tripped When Mechanical Overspeed Device Was Activated.Caused by Severe Vibration.Corrective Action:Assessment of Structural Integrity of Pedestal Was conducted.W/940425 Ltr1994-04-25025 April 1994 LER 93-014-01:on 931225,turbine Generator Tripped When Mechanical Overspeed Device Was Activated.Caused by Severe Vibration.Corrective Action:Assessment of Structural Integrity of Pedestal Was conducted.W/940425 Ltr NRC-93-0058, LER 93-008-00:on 930518,discovered That Recorder T50-R802A Could Not Be Considered Operable Per TS 3.3.7.5.Caused by Personnel Error.Lessons Learned Will Be Incorporated Into Training Programs & Plant procedures.W/930618 Ltr1993-06-18018 June 1993 LER 93-008-00:on 930518,discovered That Recorder T50-R802A Could Not Be Considered Operable Per TS 3.3.7.5.Caused by Personnel Error.Lessons Learned Will Be Incorporated Into Training Programs & Plant procedures.W/930618 Ltr NRC-93-0055, LER 93-007-00:on 930420,reactor Tripped on Intermediate Range Monitor Upscale During Reactor Pressure & Feedwater Transient.Caused by Personnel Error.Affected Pressure Transmitters replaced.W/930520 Ltr1993-05-20020 May 1993 LER 93-007-00:on 930420,reactor Tripped on Intermediate Range Monitor Upscale During Reactor Pressure & Feedwater Transient.Caused by Personnel Error.Affected Pressure Transmitters replaced.W/930520 Ltr NRC-91-0058, LER 91-008-00:on 910424,reactor Bldg HVAC Tripped,Div I SGTS Auto Started & Div I Control Ctr HVAC Shifted to Recirculation Mode Due to Mispositioned Trip Output Logic switch.W/910524 Ltr1991-05-24024 May 1991 LER 91-008-00:on 910424,reactor Bldg HVAC Tripped,Div I SGTS Auto Started & Div I Control Ctr HVAC Shifted to Recirculation Mode Due to Mispositioned Trip Output Logic switch.W/910524 Ltr NRC-91-0069, LER 90-012-01:on 901016,HPIC Steam Line Flow Transmitter Failed Due to Short Circuit Across Capacitor Plates.Circuit Boards Replaced & Failure Analysis Performed by Rosemount,Inc.W/910524 Ltr1991-05-24024 May 1991 LER 90-012-01:on 901016,HPIC Steam Line Flow Transmitter Failed Due to Short Circuit Across Capacitor Plates.Circuit Boards Replaced & Failure Analysis Performed by Rosemount,Inc.W/910524 Ltr NRC-91-0055, LER 91-006-00:on 910410,balance of Plant Breaker Opened Causing Reactor Bldg HVAC Isolation.Caused by Component Failures.Nprds Search Conducted for Similiar Problems. W/910510 Ltr1991-05-10010 May 1991 LER 91-006-00:on 910410,balance of Plant Breaker Opened Causing Reactor Bldg HVAC Isolation.Caused by Component Failures.Nprds Search Conducted for Similiar Problems. W/910510 Ltr NRC-91-0004, LER 90-013-00:on 901228,determined That Inadequate Control Could Occur During Air Grab Sampling Process.Caused by Lack of Proper Administrative Controls in Sampling Procedure. Sample Suction added.W/910128 Ltr1991-01-28028 January 1991 LER 90-013-00:on 901228,determined That Inadequate Control Could Occur During Air Grab Sampling Process.Caused by Lack of Proper Administrative Controls in Sampling Procedure. Sample Suction added.W/910128 Ltr NRC-90-0144, LER 90-007-00:on 900829,control Ctr Ventilation Shifted to Recirculation Due to Blown Fuse.Caused by Design Deficiency in Div 1 & 2 Radiation Monitor Trip Circuitry.Design Change Implemented to Eliminate Trip Relay logic.W/900928 Ltr1990-09-28028 September 1990 LER 90-007-00:on 900829,control Ctr Ventilation Shifted to Recirculation Due to Blown Fuse.Caused by Design Deficiency in Div 1 & 2 Radiation Monitor Trip Circuitry.Design Change Implemented to Eliminate Trip Relay logic.W/900928 Ltr NRC-90-0107, LER 88-034-01:on 880831,RWCU Outboard Isolation Valve Closed,Causing RWCU Pumps to Trip.Caused by Loss of Continuity to Relay Due to Deposits Built Up on Surface of Contacts.Relay in Isolation Circuits replaced.W/900622 Ltr1990-06-22022 June 1990 LER 88-034-01:on 880831,RWCU Outboard Isolation Valve Closed,Causing RWCU Pumps to Trip.Caused by Loss of Continuity to Relay Due to Deposits Built Up on Surface of Contacts.Relay in Isolation Circuits replaced.W/900622 Ltr NRC-90-0087, LER 90-002-01:on 900202,determined That Area Radiation Surveillance Procedure 44.080.301 Listed Incorrect Values for Alarm Setpoints.Caused by Unavailable Setpoint Calculations.Procedure revised.W/900608 Ltr1990-06-0808 June 1990 LER 90-002-01:on 900202,determined That Area Radiation Surveillance Procedure 44.080.301 Listed Incorrect Values for Alarm Setpoints.Caused by Unavailable Setpoint Calculations.Procedure revised.W/900608 Ltr NRC-90-0075, LER 87-045-02:on 870908,operator Removed Fuse Which Deenergized Dc Control Power to Bus 72C,resulting in Loss of Power Supply to Swing Bus & to LPCI Loop Selection Valves. Caused by Design Flaw.Design Change initiated.W/900518 Ltr1990-05-18018 May 1990 LER 87-045-02:on 870908,operator Removed Fuse Which Deenergized Dc Control Power to Bus 72C,resulting in Loss of Power Supply to Swing Bus & to LPCI Loop Selection Valves. Caused by Design Flaw.Design Change initiated.W/900518 Ltr NRC-90-0073, LER 90-003-00:on 900410,Div I Reactor Protection Sys Power Supply Failure & Subsequent MSIV Closure.Caused by Coil Burn Up.Relays Replaced & MG Sets Returned to svc.W/900508 Ltr1990-05-0808 May 1990 LER 90-003-00:on 900410,Div I Reactor Protection Sys Power Supply Failure & Subsequent MSIV Closure.Caused by Coil Burn Up.Relays Replaced & MG Sets Returned to svc.W/900508 Ltr NRC-90-0048, LER 89-037-01:on 891220,determined That Tech Spec Stroke Time Testing for Outboard Reactor Water Sample Line Isolation Valve Not Performed Prior to Expiration on 891125. Caused by Personnel Error.Procedure revised.W/900322 Ltr1990-03-22022 March 1990 LER 89-037-01:on 891220,determined That Tech Spec Stroke Time Testing for Outboard Reactor Water Sample Line Isolation Valve Not Performed Prior to Expiration on 891125. Caused by Personnel Error.Procedure revised.W/900322 Ltr NRC-90-0027, LER 89-034-01:on 891208,two Members of Fire Watch Did Not Complete Assigned Hourly Rounds from 891002-1207 in Reactor & Auxiliary Bldgs.Both Individuals Terminated & Fire Stations Equipped W/Unique Bar code.W/900221 Ltr1990-02-21021 February 1990 LER 89-034-01:on 891208,two Members of Fire Watch Did Not Complete Assigned Hourly Rounds from 891002-1207 in Reactor & Auxiliary Bldgs.Both Individuals Terminated & Fire Stations Equipped W/Unique Bar code.W/900221 Ltr NRC-90-0021, LER 90-001-00:on 900108,annunciator 2D5 Alarmed for Div II ECCS Testability Logic/Power Failure.Caused by Blown Fuse. Fuse Installed During Course of Troubleshooting W/No Subsequent Problems noted.W/900207 Ltr1990-02-0707 February 1990 LER 90-001-00:on 900108,annunciator 2D5 Alarmed for Div II ECCS Testability Logic/Power Failure.Caused by Blown Fuse. Fuse Installed During Course of Troubleshooting W/No Subsequent Problems noted.W/900207 Ltr NRC-90-0019, LER 89-028-01:on 891028,eight Safety Relief Valves Failed Set Pressure Tolerance Test.Cause Under Review by Util & Generically by BWR Owners Group Safety Relief Valve Set Point Drift Committee.Valves Removed & cleaned.W/900131 Ltr1990-01-31031 January 1990 LER 89-028-01:on 891028,eight Safety Relief Valves Failed Set Pressure Tolerance Test.Cause Under Review by Util & Generically by BWR Owners Group Safety Relief Valve Set Point Drift Committee.Valves Removed & cleaned.W/900131 Ltr NRC-90-0018, LER 89-039-00:on 891226,Div I Emergency Equipment Cooling Water & Svc Water Sys Automatically Started Due to Partial Load Shed of Bus 72E.Caused by Personnel Error. Accountability Meeting Held on 900117.W/900125 Ltr1990-01-25025 January 1990 LER 89-039-00:on 891226,Div I Emergency Equipment Cooling Water & Svc Water Sys Automatically Started Due to Partial Load Shed of Bus 72E.Caused by Personnel Error. Accountability Meeting Held on 900117.W/900125 Ltr NRC-90-0008, LER 89-037-00:on 891220,determined That Tech Spec Stroke Time Testing for Outboard Reactor Water Sample Line Isolation Valve Not Performed.Caused by Personnel Error. Critique of Event Being developed.W/900119 Ltr1990-01-19019 January 1990 LER 89-037-00:on 891220,determined That Tech Spec Stroke Time Testing for Outboard Reactor Water Sample Line Isolation Valve Not Performed.Caused by Personnel Error. Critique of Event Being developed.W/900119 Ltr NRC-90-0007, LER 89-036-00:on 891218,control Room Operator Inadvertently Depressed Closed Push Buttons on Inboard MSIVs A,B & C & Reactor Scram Resulted.Caused by Operator Error.Operator Involved Was Removed from Licensed duties.W/900117 Ltr1990-01-17017 January 1990 LER 89-036-00:on 891218,control Room Operator Inadvertently Depressed Closed Push Buttons on Inboard MSIVs A,B & C & Reactor Scram Resulted.Caused by Operator Error.Operator Involved Was Removed from Licensed duties.W/900117 Ltr ML19354E0971990-01-12012 January 1990 LER 89-038-00:on 891223,reactor Scrammed When Fire Occurred in Vicinity of High Pressure Turbine.Caused by Oil Soaked Inlagging Pads & Ignited When Turbine Casing Heated Up to Oil Flashpoint.Insulation Pads replaced.W/900122 Ltr NRC-90-0005, LER 89-035-00:on 891210,steam Jet Air Ejectors Placed in Svc W/O Required Surveillance Completed & Required Grab Sample Not Started Until 891213.Caused by Personnel Error.Off Gas Sys Operating Procedure Will Be revised.W/900111 Ltr1990-01-11011 January 1990 LER 89-035-00:on 891210,steam Jet Air Ejectors Placed in Svc W/O Required Surveillance Completed & Required Grab Sample Not Started Until 891213.Caused by Personnel Error.Off Gas Sys Operating Procedure Will Be revised.W/900111 Ltr NRC-90-0004, LER 89-030-00:on 891026,Channel C Level 1 & 2 Replacement Transmitter Found to Be Installed Incorrectly & Condition Recognized on 891210,when Level 2 Trip Unit Was Reading Upscale.Caused by Personnel error.W/900109 Ltr1990-01-0909 January 1990 LER 89-030-00:on 891026,Channel C Level 1 & 2 Replacement Transmitter Found to Be Installed Incorrectly & Condition Recognized on 891210,when Level 2 Trip Unit Was Reading Upscale.Caused by Personnel error.W/900109 Ltr NRC-90-0002, LER 89-033-00:on 891207,volt-ohm Meter Connected to Incorrect Terminal,Causing Div II of Emergency Equipment Cooling Water Sys to Actuate.Caused by Personnel Error.Sys Secured & Channel Test Successfully completed.W/900108 Ltr1990-01-0808 January 1990 LER 89-033-00:on 891207,volt-ohm Meter Connected to Incorrect Terminal,Causing Div II of Emergency Equipment Cooling Water Sys to Actuate.Caused by Personnel Error.Sys Secured & Channel Test Successfully completed.W/900108 Ltr NRC-90-0003, LER 89-034-00:on 891208,review of Key Card Transactions Showed That Fire Watch Personnel Missed Assigned Hourly Fire Watch from 891020-1207.Fire Watch Person Discharged.Plan Re Improvement of Fire Watches developed.W/900108 Ltr1990-01-0808 January 1990 LER 89-034-00:on 891208,review of Key Card Transactions Showed That Fire Watch Personnel Missed Assigned Hourly Fire Watch from 891020-1207.Fire Watch Person Discharged.Plan Re Improvement of Fire Watches developed.W/900108 Ltr NRC-89-0261, LER 89-028-00:on 891129,ESF Actuations Occurred During Set Up for Surveillance.Caused by Blown Fuse.Blown Fuse Replaced & Affected Sys Returned to Normal Operation Following Completion of surveillance.W/891228 Ltr1989-12-28028 December 1989 LER 89-028-00:on 891129,ESF Actuations Occurred During Set Up for Surveillance.Caused by Blown Fuse.Blown Fuse Replaced & Affected Sys Returned to Normal Operation Following Completion of surveillance.W/891228 Ltr NRC-89-0260, LER 89-021-01:on 890906,35 of 237 Containment Isolation Valves Exceeded Administrative Allowable Leakage Rate When Tested.Caused by Normal Wear & Degradation During Specified Time Interval.Valves Cleaned & repaired.W/891221 Ltr1989-12-21021 December 1989 LER 89-021-01:on 890906,35 of 237 Containment Isolation Valves Exceeded Administrative Allowable Leakage Rate When Tested.Caused by Normal Wear & Degradation During Specified Time Interval.Valves Cleaned & repaired.W/891221 Ltr NRC-89-0255, LER 89-031-00:on 891120,both Div II Emergency Equipment Cooling Water (EECW) & Emergency Equipment Svc Water Sys Pumps Tripped Immediately.Caused by Inadequacies in Stated Procedures.Procedures revised.W/891220 Ltr1989-12-20020 December 1989 LER 89-031-00:on 891120,both Div II Emergency Equipment Cooling Water (EECW) & Emergency Equipment Svc Water Sys Pumps Tripped Immediately.Caused by Inadequacies in Stated Procedures.Procedures revised.W/891220 Ltr NRC-89-0259, LER 89-017-01:on 890810,new Analysis of Feedwater Line Break Scenario Assumes Failure of Feedwater Startup Control Valve in Open Position.Review of Pipe Break Documentation Conducted.Updated FSAR Change to Be submitted.W/891215 Ltr1989-12-15015 December 1989 LER 89-017-01:on 890810,new Analysis of Feedwater Line Break Scenario Assumes Failure of Feedwater Startup Control Valve in Open Position.Review of Pipe Break Documentation Conducted.Updated FSAR Change to Be submitted.W/891215 Ltr NRC-89-0256, LER 89-022-01:on 890923 & 24,reactor Protection Sys Logic Actuations Occurred When Fuse C71A-F15B Blew.On 890928, Reactor Bldg HVAC Isolated.Caused by Personnel Error. Procedures Will Be revised.W/891215 Ltr1989-12-15015 December 1989 LER 89-022-01:on 890923 & 24,reactor Protection Sys Logic Actuations Occurred When Fuse C71A-F15B Blew.On 890928, Reactor Bldg HVAC Isolated.Caused by Personnel Error. Procedures Will Be revised.W/891215 Ltr NRC-89-0258, LER 89-025-00:on 891115,low Level 2 Signal Unintentionally Induced During Reactor Pressure Vessel Hydrostatic Pressure Test.Caused by Personnel Error.Personnel Counseled on Notifying & Coordinating Instrument lineups.W/891215 Ltr1989-12-15015 December 1989 LER 89-025-00:on 891115,low Level 2 Signal Unintentionally Induced During Reactor Pressure Vessel Hydrostatic Pressure Test.Caused by Personnel Error.Personnel Counseled on Notifying & Coordinating Instrument lineups.W/891215 Ltr NRC-89-0251, LER 89-019-01:on 890819,discovered That Div I Recirculation Fan Not Rotating Which Resulted in Decrease in Control Room Air Pressure.Caused by Lack of Lubrication in Bearings. Lubrication Program Improvements evaluated.W/891130 Ltr1989-11-30030 November 1989 LER 89-019-01:on 890819,discovered That Div I Recirculation Fan Not Rotating Which Resulted in Decrease in Control Room Air Pressure.Caused by Lack of Lubrication in Bearings. Lubrication Program Improvements evaluated.W/891130 Ltr NRC-89-0249, LER 89-029-00:on 891023,half Scram Signal Received When Power Was Lost on Reactor Protection Sys Bus B,Resulting in Several ESFs Actuation.Caused by Location of Breaker Operating Switch in High Traffic area.W/891122 Ltr1989-11-22022 November 1989 LER 89-029-00:on 891023,half Scram Signal Received When Power Was Lost on Reactor Protection Sys Bus B,Resulting in Several ESFs Actuation.Caused by Location of Breaker Operating Switch in High Traffic area.W/891122 Ltr NRC-89-0246, LER 89-028-00:on 891020,eight safety-related Valves Failed Set Pressure Test.Cause Under Review.All Valves Removed for Testing Being Refurbished,Cleaned,Retested & Recertified to Be within Plant Accepted tolerances.W/891120 Ltr1989-11-20020 November 1989 LER 89-028-00:on 891020,eight safety-related Valves Failed Set Pressure Test.Cause Under Review.All Valves Removed for Testing Being Refurbished,Cleaned,Retested & Recertified to Be within Plant Accepted tolerances.W/891120 Ltr NRC-89-0244, LER 89-024-00:on 891019,recognized That Secondary Containment Dampers Not Tested as Required by Tech Spec 3.6.5.2.Caused by Operations Personnel Error.Event Critique to Be Included in Required Reading program.W/891120 Ltr1989-11-20020 November 1989 LER 89-024-00:on 891019,recognized That Secondary Containment Dampers Not Tested as Required by Tech Spec 3.6.5.2.Caused by Operations Personnel Error.Event Critique to Be Included in Required Reading program.W/891120 Ltr NRC-89-0194, LER 89-027-00:on 891015,reactor Bldg Hvac,Control Ctr HVAC & Drywell Floor & Equipment Drain Sumps Isolated & Standby Gas Treatment Sys & Noninterrruptalbe Control Air Compressors Started.Caused by Personnel error.W/891114 Ltr1989-11-14014 November 1989 LER 89-027-00:on 891015,reactor Bldg Hvac,Control Ctr HVAC & Drywell Floor & Equipment Drain Sumps Isolated & Standby Gas Treatment Sys & Noninterrruptalbe Control Air Compressors Started.Caused by Personnel error.W/891114 Ltr NRC-89-0193, LER 89-026-00:on 891010,control Ctr HVAC Shifted to Recirculation Mode of Operaton Due to Short Circuit.Caused by Failure of Lamp Filament When Being Tightened.Fuse & Lamp Replaced & Sys Returned to Normal operation.W/891109 Ltr1989-11-0909 November 1989 LER 89-026-00:on 891010,control Ctr HVAC Shifted to Recirculation Mode of Operaton Due to Short Circuit.Caused by Failure of Lamp Filament When Being Tightened.Fuse & Lamp Replaced & Sys Returned to Normal operation.W/891109 Ltr NRC-89-0192, LER 87-045-01:on 870908,fuse Removed Which Deenergized Dc Control Power to Bus 72C & Resulted in Loss of Power Supply to Swing Bus & LPCI Loop Selection Valves.Caused by Design Error.Undervoltage Relay Added & Training held.W/891106 Ltr1989-11-0606 November 1989 LER 87-045-01:on 870908,fuse Removed Which Deenergized Dc Control Power to Bus 72C & Resulted in Loss of Power Supply to Swing Bus & LPCI Loop Selection Valves.Caused by Design Error.Undervoltage Relay Added & Training held.W/891106 Ltr NRC-89-0190, LER 89-023-00:on 890924,personnel Inadvertently Caused Trip of Essential Safety Sys Buses 64B & 64C.Caused by Failure of Personnel Involved to Review Applicable Prints Prior to Performing Test.Event Reviewed w/personnel.W/891024 Ltr1989-10-24024 October 1989 LER 89-023-00:on 890924,personnel Inadvertently Caused Trip of Essential Safety Sys Buses 64B & 64C.Caused by Failure of Personnel Involved to Review Applicable Prints Prior to Performing Test.Event Reviewed w/personnel.W/891024 Ltr NRC-89-0189, LER 89-022-00:on 890923 & 24,reactor Protection Sys Logic Actuations Occurred When Fuse Blew.On 890928,reactor Bldg HVAC Isolated When Jumper Lifted Per Incorrect Work Plan Instruction.Caused by Personnel error.W/891023 Ltr1989-10-23023 October 1989 LER 89-022-00:on 890923 & 24,reactor Protection Sys Logic Actuations Occurred When Fuse Blew.On 890928,reactor Bldg HVAC Isolated When Jumper Lifted Per Incorrect Work Plan Instruction.Caused by Personnel error.W/891023 Ltr NRC-89-0186, LER 89-016-01:on 890711,Div 1 of RHR Svc Water Sys Declared Inoperable Due to Low Nitrogen Pressure for Cooling Tower Fan Brake.Caused by Leak in One Hose.Leaking Hose Replaced & Nitrogen Pressure restored.W/891006 Ltr1989-10-0606 October 1989 LER 89-016-01:on 890711,Div 1 of RHR Svc Water Sys Declared Inoperable Due to Low Nitrogen Pressure for Cooling Tower Fan Brake.Caused by Leak in One Hose.Leaking Hose Replaced & Nitrogen Pressure restored.W/891006 Ltr NRC-89-0185, LER 89-021-00:on 890906,local Leak Rate Testing of Containment Isolation Valves & Penetrations Exceeded Tech Spec Limit.Caused by Excessive Containment Isolation Valve Leakage Due to Degradation of valve.W/891006 Ltr1989-10-0606 October 1989 LER 89-021-00:on 890906,local Leak Rate Testing of Containment Isolation Valves & Penetrations Exceeded Tech Spec Limit.Caused by Excessive Containment Isolation Valve Leakage Due to Degradation of valve.W/891006 Ltr 1994-04-25
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217N4381999-10-25025 October 1999 Safety Evaluation Supporting Amend 17 to License DPR-9 ML20217P3551999-10-22022 October 1999 LER 99-S01-00:on 990922,loaded 9mm Handgun Was Discovered on Truck Cargo Area of Vehicle Inside Protected Area.Caused by Inadequate Vehicle Search.Guidance in Procedures & Security Training to Address Multiple Vehicle Searches Was Provided NRC-99-0095, Monthly Operating Rept for Sept 1999 for Fermi 2.With1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Fermi 2.With NRC-99-0067, Monthly Operating Rept for Aug 1999 for Fermi 2.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Fermi 2.With NRC-99-0065, Monthly Operating Rept for July 1999 for Fermi 2.With1999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Fermi 2.With NRC-99-0088, Detroit Edison Co Enrico Fermi Atomic Power Plant,Unit 1 Annual Rept for Period 980701-990630. with1999-06-30030 June 1999 Detroit Edison Co Enrico Fermi Atomic Power Plant,Unit 1 Annual Rept for Period 980701-990630. with NRC-99-0064, Monthly Operating Rept for June 1999 for Fermi 2.With1999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Fermi 2.With NRC-99-0062, Monthly Operating Rept for May 1999 for Fermi 2.With1999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Fermi 2.With ML20206J9301999-05-10010 May 1999 SER Concluding That Util Adequately Addressed Actions Requested in GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Powered-Operated Gate Valves ML20206G5081999-05-0505 May 1999 Safety Evaluation Approving Request for Relief PR-8,Rev 2 on Basis That Licensee Committed to Meet All Related Requirements of ASME OM-6 Std & PR-12 on Basis That Proposed Alternative Will Provide Acceptable Level of Safety NRC-99-0022, Monthly Operating Rept for Apr 1999 for Fermi 2.With1999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Fermi 2.With ML20205Q7141999-04-15015 April 1999 Safety Evaluation Supporting Amend 16 to License DPR-9 ML20205P9721999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Fermi 2 ML20204E0371999-03-17017 March 1999 Safety Evaluation Accepting Licensee Request for NRC Approval of Alternative Rv Weld Exam,Per Provisions of 10CFR50.55a(a)(3)(i) & 10CFR50.55a(g)(6)(ii)(A)(5) for Plant,Unit 2 for 40-month Period ML20204D0361999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Fermi 2 ML20198S3341999-01-0606 January 1999 Safety Evaluation Supporting Amend 15 to License DPR-9 NRC-99-0005, Monthly Operating Rept for Dec 1998 for Fermi 2.With1998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Fermi 2.With ML20207B7491998-12-31031 December 1998 1998 Annual Operating Rept for Fermi 2 ML20205Q9621998-12-31031 December 1998 Revised Monthly Operating Rept for Dec 1998 for Fermi 2 NRC-99-0021, 1998 Annual Financial Rept for Detroit Edison Co. with1998-12-31031 December 1998 1998 Annual Financial Rept for Detroit Edison Co. with NRC-98-0153, Monthly Operating Rept for Nov 1998 for Fermi 2.With1998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Fermi 2.With NRC-98-0160, Monthly Operating Rept for Oct 1998 for Fermi 2.With1998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Fermi 2.With ML20154R2331998-10-21021 October 1998 Safety Evaluation Supporting Amend 13 to License DPR-9 ML20154L1031998-10-14014 October 1998 Safety Evaluation Accepting Licensee Response to NRC Bulletin 95-002, Unexpected Clogging of Residual Heat Removal Pump Strainer While Operating in Suppression Pool Cooling Mode NRC-98-0139, Monthly Operating Rept for Sept 1998 for Fermi,Unit 2.With1998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Fermi,Unit 2.With ML20154H8161998-09-30030 September 1998 Rev 0 to COLR Cycle 7 for Fermi 2 ML20153B8811998-09-18018 September 1998 Safety Evaluation Accepting Request for Relief from Certain Requirements of ASME Boiler & Pressure Vessel Code,Section Xi,For Plant,Unit 2 ML20151X0651998-09-11011 September 1998 Safety Evaluation Re Inservice Testing Program Relief Request VR-63 for Plant NRC-98-0111, Monthly Operating Rept for Aug 1998 for Fermi 2.With1998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Fermi 2.With ML20153B7921998-08-31031 August 1998 Rev 0 to Fermi 1 Sar ML20237E1171998-08-25025 August 1998 Safety Evaluation Accepting Licensee Relief Requests for First 10-yr Interval Inservice Insp Nondestructive Exam Program ML20236X8611998-08-0505 August 1998 SER Related to Revised Feedwater Nozzle Analysis to Facility Operating License NPF-43,Enrico Fermi Nuclear Power Plant, Unit 2 NRC-98-0109, Monthly Operating Rept for July 1998 for Fermi 21998-07-31031 July 1998 Monthly Operating Rept for July 1998 for Fermi 2 ML20236K3261998-07-0101 July 1998 SER Accepting Licensee Response Related to Revised Feedwater Nozzle Analysis to License NPF-43 for Enrico Fermi Nuclear Power Plant,Unit 2 NRC-98-0097, Monthly Operating Rept for June 1998 for Fermi,Unit 21998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Fermi,Unit 2 NRC-98-0127, Annual Rept for Period 970701-9806301998-06-30030 June 1998 Annual Rept for Period 970701-980630 NRC-98-0079, Monthly Operating Rept for May 1998 for Fermi 21998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Fermi 2 NRC-98-0076, Monthly Operating Rept for Apr 1998 for Fermi 21998-04-30030 April 1998 Monthly Operating Rept for Apr 1998 for Fermi 2 NRC-98-0072, Monthly Operating Rept for Mar 1998 for Fermi 21998-03-31031 March 1998 Monthly Operating Rept for Mar 1998 for Fermi 2 NRC-98-0050, Monthly Operating Rept for Feb 1998 for Fermi 21998-02-28028 February 1998 Monthly Operating Rept for Feb 1998 for Fermi 2 NRC-98-0019, Monthly Operating Rept for Jan 1998 for Fermi 21998-01-31031 January 1998 Monthly Operating Rept for Jan 1998 for Fermi 2 ML20198L4241998-01-0808 January 1998 Safety Evaluation Accepting Proposed Rev 2 to Relief Request VR-51 Under Fermi 2 Pump & Valve Inservice Testing Program Per 10CFR50.55a(f)(6)(i) for First 10-yr Interval NRC-98-0015, Monthly Operating Rept for Dec 1997 for Fermi 21997-12-31031 December 1997 Monthly Operating Rept for Dec 1997 for Fermi 2 ML20217N3821997-12-31031 December 1997 Annual Operating Rept for 970101-1231 NRC-98-0053, 1997 Annual Financial Rept for Detroit Edison Company1997-12-31031 December 1997 1997 Annual Financial Rept for Detroit Edison Company ML20205Q9601997-12-31031 December 1997 Revised Monthly Operating Rept for Dec 1997 for Fermi 2 NRC-97-0141, Deficiency Rept Re Malfunction of EDG Number 11 Automatic Voltage Regulator (AVR) Printed Circuit Board Rev B,Due to Failure of Operational Amplifier U8 Chip.Avr Board Rev B Was Sent Offsite to Independent Engineering Facility1997-12-23023 December 1997 Deficiency Rept Re Malfunction of EDG Number 11 Automatic Voltage Regulator (AVR) Printed Circuit Board Rev B,Due to Failure of Operational Amplifier U8 Chip.Avr Board Rev B Was Sent Offsite to Independent Engineering Facility ML20197A9921997-12-15015 December 1997 Rev 0 to Efp,Unit 1 Fermi 1 Sar NRC-97-0131, Monthly Operating Rept for Nov 1997 for Fermi 21997-11-30030 November 1997 Monthly Operating Rept for Nov 1997 for Fermi 2 ML20248H1151997-10-31031 October 1997 Rev 1 to Colr,Cycle 6 for Fermi 2 1999-09-30
[Table view] |
Text
. . . . . . . . . .
?
Dougies H. Glpson
[ c<uer yo F rewjert Nuclear Ge . n100 Detroit r.,m a MO Nort
~
Edison on()aw~h ;n D u<e H4)huri 10CFR50.73 April 25, 1994 NRC-94-0025 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555
References:
- 1) Fermi 2 NRC Docket No. 50-341 NRC License No. NPF-43
- 2) NRC-94-0006, Licensing Event Report (LER) No.93-014, dated January 24, 1994
Subject:
Licensee Event Report (LER) No.93-014, Revision 1 Please find enclosed LER No.93-014, Revision 1, dated April 25, 1994, for a reportable event that occurred on December 25, 1993 A copy of this LER is also being sent to the Regional Administrator, USNRC Region III.
If you have any questions, please contact John A. Tibal, Principal Compliance Engineer, at (313) 586-4289 Sincerely, 1 Y'
Enclosure:
NRC Forms 366, 366A cc: T. G. Colburn J. B. Martin M. P. Phillips K. R. Riemer P. L. Torpey Wayne County Emergency Management Division 9404290114 940425 ,l PDR ADOCK 05000341 S PDR
-- .- - _ . ~ , _
4 NRC F ORM 366 U.S. NUCL5AR REGULATORY COMMISSION APPROVED BY OMO NO. 3150-0104 6%
EXPIRES S/31/95 I STIM Af f D HURDEN P[ q HI SR.:WF' TO GOMDL.Y Wit H THE LICENSEE EVENT REPORT (LER) ECZrJEMSOJN ZESo7,7,mlS,%%
AND hl CORD 3 MANAGE MENT liHANCH (MNAU 7714n U S NUCN AR Hf GULATORY COMM:55 ION. WASHINGTON, IC 70Mn M01, AND TO THR FAM RWOiM RFDUCTON PRCM CT pisc om.t, O( F CE or (See f everse for required nurnber of dig:ts/ characters for each block) MANAGE Mf N7 AND BUDGET, WAf:H:NGTON. DC wm F ACILITy NAME (1)
DOCM L I NUMBL R (2) PAGI (3)
Fermi 2 05000 341 1 OF 7 TITLE ly Automatic Reactor Shutdown Following Failure of the Main Turbine EVENT DATE (5)~ LER HUMBER (6' REPORT NUMBER (7) OTHER F ACILITIES INVOLVED (8)
MOUf NhAL ALV6 TON "" # l #1I #"
MONTH DAY YEAH YEAR g MONTH DAY YEAH g
& Autuiy NAML
~
DOCKET NUMai R 12 25 , 93 93 ~ 014 01 04 25 94 5 0 OPERATING THIS REPORT IS SUBMITTED PURSUANT TO THE REQUIREMENTS OF 10 CFR 6: (Check one or more) (11)
MODE (9) 1 20 402(b) 20 405(c) X 50 73faH2)(iv) 73 71(b)
POWER 20 405(a)(1)0) 50 30(cH1) 50 73(a)(2)(v) 73.71(c)
L EVEL (10) 93% 20 405(a)(1)(n) 50 36(c)(2) 50.73(a)(2)(vil) OTHER 20 405(a)D)(in) 50 73(aH2)0) 50.73(a)(2)(vin)(A) M "*/'^^M"ad 20 40S(a)(f)0v) 50.73(a)(2)(n) 50.73(a)(2)(voi)(B) 20 405(a)(1)(v) 50.73(a)(2)(m) 50.73(a)(2)(x)
LICENSEE CONTACT FOR THIS LER (12) s M.n numou NuYat H pnuuc. A<.a coa.n John A. Tibai, Compliance Engineer (313) 586-4289 COMPLETE ONE LINE FOR EACH COMPONENT FAILURE DESCRIBED IN THIS REPORT (13) cAusE sem u couPmi N T MANuf Actunt H
[ CAUM SYS R AA COMPONENT MANUF AGURf R B TA TRB E275 Y SUPPLEMENTAL REPORT EXPECTED (14) EXPECTED MON TH DAY RAH yt s
" SUBMISSION p r.. www rwrcrco w.urdoN Data X DATE (15)
ABSTRACT (Limrt to 1400 tpaces i e., approximately 15 single 4 paced typewntten bnes) (16) s On December 25, 1993 at 1315 hours0.0152 days <br />0.365 hours <br />0.00217 weeks <br />5.003575e-4 months <br /> an automatic reactor shutdown occurred when the main turbine tripped off line. The turbine generator tripped when the mechanical overspeed device was activated. This was due to high l vibration levels and was not due to an actual overspeed condition. The turbine generator unit and associated support systems sustained significant damage. All safety systems and isolations performed as designed during the event. An Unusual Event was declared at 1352 hours0.0156 days <br />0.376 hours <br />0.00224 weeks <br />5.14436e-4 months <br />. This was upgraded to an Alert at 1357 hours0.0157 days <br />0.377 hours <br />0.00224 weeks <br />5.163385e-4 months <br />. A fire at the main generator brush rig area was j extinguished by the plant fire brigade using hand held extinguishers.
The cause of the high turbine vibration was due to the failure of the number 9 blade, on the 8th stage, turbine end of the low pressure section number 3 The root cause or this failure continues to be under investigation.
Turbine / generator repairs will be determined based on the results of the investigation. Other corrective actions needed to return the plant to power operation are being formulated and implemented.
Sc ,onu u is m x- , m + n w e n w _. . e . ,.n ~ n
9 N
REOUIRED NUMBER OF DIGITS / CHARACTERS FOR EACH BLOCK BLOCK NUMBER OF NUMDER DIGITS / CHARACTERS 1 UP TO 46 FACILITY NAME 3 IN ADDITION TO 05000 DOC E M BER-3 VARIES PAGE NUMBER 4 UP TO 76 TITLE 5 EVENT DATE-2 PER BLOCK 7 TOTAL 2 FOR YEAR 6 LER NUMBER 3 FOR SEQUENTIAL NUMBER 2 FOR REVISION NUMBER 7 ^
2 PER BLOCK -
UP TO 18 -- FACILITY NAME OTHER FACluTIES INVOLVED B TOTAL - DOCKET NUMBER 3 IN ADDITION TO 05000 9 1 OPERATING MODE 10 3 POWER LEVEL l' REQUIREMENTS OF 10 CFR CHECK BOX THAT APPLIES UP TO 50 FOR NAME 12 LICENSEE CONTACT 14 FOR TELEPHONE CAUSE VARIES -
2 FOR SYSTEM 13 4 FOR COMPONENT EACH COMPONENT FAILURE 4 FOR MANUFACTURER NPRDS VARIES I# SUPPLEMENTAL REPORT EXPECTED CHECK BOX THAT APPLIES 15 2 PE BLOCK i
l l
l L
NRC FORM 366A u.S. NUCLEAR REGULATORY CoMMISSloN APPROVED BY UMB NO. 31bo-0104 m 92)
, EXPIRES 5/31/95 ESTIMATED BVADEN PEA FIESPONSE TO COMPLY WITH TH!S LICENSEE EVENT REPORT (LER) C5CMsLEE'al"al& E "OQ u$2ME TEXT CONTINUATION @u"E*c5Ei$'"k"E,"d"E"" #'$$5'D' $
THE PAPEAwoAK REDUCTION PACUECY (31500104h OFFICE OF MANAGhMENT AND BUDGET, WASH NGTON, DC 20503 FACILITY hAME (1) DOCKET NUMBEH (2) LE H NUMBER (6) PAGE g3) ygg blOVENhAu hey @oN Fermi 2 05000 341 2 oF 7 93 - 014 -
01 ru, tu -. aoa. . , w.a. m. . maw n., a unc 1,,, wm o n Initial Plant Conditions:
Operational Condition: 1 - Power Operation Reactor Power: 93 5 Percent Reactor Pressure: 1020 psig Reactor Temperature: 535 degrees Fahrenheit Description of Event:
On December 25, 1993 at 1315 hours0.0152 days <br />0.365 hours <br />0.00217 weeks <br />5.003575e-4 months <br /> an automatic reactor shutdown [JC]
occurred in response to a main turbine [TA] trip. The specific cause of the reactor automatic shutdown was fast closure of the turbine control [JJ) valves. The main turbine generator [TB] tripped off line due to activation of the mechanical overspeed trip device. This was caused by very high vibration levels and not by an actual overspeed condition. Control room operators [ Utility-Licensed] heard a loud noise from the turbine deck followed by heavy rumbling. A number of alarms were received in the control room [NA] including the seismic monitoring alarm, turbine vibration alarms
[VA], turbine tripped alarm and alarms from turbine auxiliary systems.
Control Room operators noted that the oil supply pressure to the main turbine indicated 0 psig.
Twenty five (25) seconds into the event the main steam isolation valves (MSIV)[ISV) automatically closed due to high condenser [SG) pressure (Group 1 isolation). A Group 13 isolation (Drywell Sumps) [WK] occurred when '
reactor water level decreased to level 3, which normally occurs during an automatic shutdown from power operation. Reactor pressure was controlled by manually opening safety relief valves [RV) and water level was controlled by manual operation of the reactor core isolation cooling (RCIC)[BN] and standby feedwater (SBFW)[SK] systems.
The Nuclear Shift Supervisor [ Utility-Licensed] declared an Unusual Event at 1352 hours0.0156 days <br />0.376 hours <br />0.00224 weeks <br />5.14436e-4 months <br /> based on fire alarms and potential fire hazards from turbine lubricating oil. The emergency classification was upgraded to an Alert at 1357 hours0.0157 days <br />0.377 hours <br />0.00224 weeks <br />5.163385e-4 months <br /> based on a report of a fire on the second floor of the turbine building in the area of the lubricating oil reservoir. The fire brigade was assembled and assistance, although not utilized, was requested from the-local fire department. At 1400 hours0.0162 days <br />0.389 hours <br />0.00231 weeks <br />5.327e-4 months <br /> it was determined that a fire in the lubricat.ing oil area had not occurred. The previous communication to the control room operators had been misunderstood. The misunderstood communication was attributed to the difficulty of communicating with hand held radios while wearing self contained breathing equipment. At 1405 hours0.0163 days <br />0.39 hours <br />0.00232 weeks <br />5.346025e-4 months <br /> a small fire was identified in the generator brush rig area. This was l extinguished with portable fire extinguishers.
NRC FORM 366A (5 92)
~ . .
l
'NRc FORM 366A U.S. NUCLEAR REGULATORY CoMMISSloN APPROVED BY oMB No. 3150-0104 m2;
, EXPIRES 5/31/95 )
EST! MATED BURDEN PER RESPONSE TO COMPty WiTH TH!S I LICENSEE EVENT REPORT (LER) '"5$7^JOcMa'Eno"5 c EE?OL5RM TEXT CONTINUATION @$cORgSo cMgu A M MNB rg ,
L M %"lsm ," M R @ t ""*'
F ACluTY NAME p) DOCKET NUMBER (2) LIR NUMBER (t) pAog g3; g LEQutNTiA. HLv3CN NUMBER NUMBER Fermi 2 05000 341 93 -
014 3oF7 01 rvT w ma, so ca v w.w. .ama,a an., a mc 1a,n m o n A review of the event determined that the initial fire alarms v .*e caused by a rapid hydrogen burn around the generator. The source of hyorogen was that used to cool the Internals of the generator. The automatic fire supnression systems operated as designed.
Significant damage was sustained by the turbine / generator and the auxiliary systems. The exciter rotor (TL] had become disconnected from the turbine / generator shaft. A hole measuring approximately 18" x 30" was found ;
in the northwest corner of the number 3 low pressure turbine hood. General Service Water [KG) and Turbine Building Closed Cooling Water [KB] Systems, which cool hydrogen [LJ] in the main generator and air within the exciter, respectively, were breached. Approximately 550,000 gallons of water from these two systems and the fire suppression system flooded the radwaste building [NE] and turbine building [NM] basement areas disabling the radwaste systems.
The turbine lubricating oil system [TD] also suffered significant damap.
An estimated 17,000 gallons of turbine lubricating oil was spilled onta the turbine building floor areas and mixed with water in these areas.
The main condenser also sustained damage. An unknown number of condenser tubes were severed resulting in approximately 250,000 gallons of circulating water flowing into the condenser hotwell. This water was subsequently discharged through the condensate polishing demineralizers, compromising the effectiveness of the demineralizers. The water was discharged to the condensate storage tank [KA] as the hotwell level control system functioned >
to compensate for increasing hotwell water level. Reactor water quality deteriorated as the RCIC and SBFW systems utilized water from the condensate storage tank to maintain reactor water level.
All safety systems [JE] and isolations performed as designed. All safety systems were available throughout the event. Standby gas treatment [WF] was manually started in response to the loss of the reactor building HVAC [VA]
system.
At 1722 hours0.0199 days <br />0.478 hours <br />0.00285 weeks <br />6.55221e-4 months <br /> the Emergency Director downgraded the emergency status to an Unusual Event based on stable plant conditions. The Unusual Event was terminated at 2052 hours0.0238 days <br />0.57 hours <br />0.00339 weeks <br />7.80786e-4 months <br /> based on the plant being in a stable condition.
On December 26, 1993, while preparing to place the reactor into cold shutdown, reactor recirculation discharge [AD] valve B3105-F031B failed to close. Had the reactor coolant level dropped to level 2 during the December 25, 1993 event, the low pressure coolant injection [(LPCI)(BO)]
full flow may not have been available. LER 93-015 was submitted to address this valve failure.
NRC FORM 366A p 92} ,
l l
MRC FORM 366A U.S. NUCLEAR REGULATORY CoMMISSloN 5 93 APPROVED BY oMD No. 3150 0104 EXPIRES 5/31/95 ESTIMATED BURDEN PER FiESPONSE TO COMPLY W'TH TMS LICENSEE EVENT REPORT (LER) E CT*2SE E T 1"RIE E L TUO E d CT$ ,
TEXT CONTINUATION E"$" S cy^uM"7 8MC"rfSj 72;M@l o J THE PAPERWORK REDUCTION PRCUECT (3150C0% OFFICE OF (
M ANAGEMENT AND BVDGET, WASH lNGTON. DC 20503 l f ACILITY NAME (1) l DOCKET NUMBER (2) LE R NUMBER (4) PAGE (3)
M QuLN11A. HEWuGN NLJMBER NUMBER Fermi 2 05000 341 - -
93 014 01 itxT or more space as reqwrea. uso esorsonar cones or NRc Form assa) (17) 1 The plant was placed in cold shutdown at 2251 hours0.0261 days <br />0.625 hours <br />0.00372 weeks <br />8.565055e-4 months <br /> on December 26, 1993 Cause of Event The reactor scram was caused by the closure of the turbine control valves when the main turbine generator (HTG) tripped off line. The turbine trip was caused by the activation of the mechanical overspeed trip device.
Activation of the mechanical overspeed trip device was due to severe vibration and not from an actual overspeed condition. The high vibration of the main turbine was the result of the failure of the number 9 blade on the 8th stage, turbine end of low pressure section number 3 The root cause of the blade failure has not yet been determined.
Analysis of Event: '
An automatic reactor shutdown was initiated by the closure of the main turbine control valves. A turbine trip was initiated by the activation of the mechanical overspeed trip mechanism. Analysis of the turbine vibration data determined that this trip was initiated due to high vibration on the main turbine unit and was not due to an actual overspeed condition. ,
Reactor and safety system responses following the automatic shutdown, including the low level 3 actuation were normal. The turbine failure did '
not result in any abnormal release of radioactive material. i A comparison of the event against the UFSAR turbine missile analysis was made by Engineering and it was determined that this event was bounded by the UFSAR analysis.
The dynamic response of the reactor / auxiliary building to the MTG failure induced excitation was measured by earthquake recording devices located in ;
the reactor / auxiliary building. The data from these devices show that the l reactor / auxiliary building was not significantly excited or displaced by the I MTG failure event.
There are three triaxial passive peak shock recorders installed in the following reactor / auxiliary building locations; High Pressure Coolant i Injection (HPCI) room floor (El. 540'-0"), relay room floor (El. 613'-6"), l and refueling floor (El. 684'-6"). These devices are capable of recording {
accelerations in the frequency range of 2-25 Hz and fully characterize the I structural dynamic environment in the reactor / auxiliary building. Data from l
NRC FORM 366A (S.92)
. . 1 NRC FORM 366A u.S. NUCLEAR REGULATORY CoMMISSloN APPROVED BY oMB No. 3150-0104 la2, EXPIRES 5/31/95 ESTlMATED DURDEN PER RESPONSE TO COMPLY W'TH THl3
'Z7Z8&S'ERDEsME bC',Nr$0T *"
LICENSEE EVENT REPORT (LER) C TEXT CONTINUATION M u S *c E M $ "*M
- E S"T E c ""C E i.YS i E THE PAPERWORK REDUCTION PROJECT (3150-0104, OFFICE OF MWAGEMEh.T AND BUDGET, WASHtNGTON, DC 20503 FAClWTY NAME (1) DOCKE1 NUMBER (2) LER NUMBf R (41 PAGE (3) q MQUENilA. REVSON )
NUMBER NUMBER i 05000 Fermi 2 341 93 -
014 -
01 runa n, ,o.c. ,, ,.e<.a. u.. . sana n., a unc r- um <m the relay room and refueling room recorders show no significant response resulted from the turbine event.
There are also two triaxial accelerometers located on the HPCI room floor ;
and at the top of the reactor pedestal. The accelographs indicated three ;
short duration acceleration excursions. The first and second were separated by approximately 2 seconds and the second and third were separated by approximately one minute. Engineering analysis determined these were not l
structurally significant. Further, there is no evidence that the four inch seismic isolation gap between the turbine and auxiliary building was infringed on during the turbine event.
An independent review of the data was conducted by an outside consultant.
They determined that the instrumentation response was due to a shock impulse. A shock impulse imparts short duration, high amplitude, and low energy into a structure, whereas, an earthquake imparts long duration, broad frequencies, and high energy into a structure. Industry standards recognize shock impulses do not cause significant structural stresses. The report concluded that the shock wave length resulting from the turbine event was small compared to the building, and therefore produced local high accelerations, but the short duration, low energy, and small deformations associated with these high frequency accelerations did not compromise the structural integrity of the Reactor / Auxiliary building or che equ!pment therein.
Although planned walkdowns to examine the plant structures have not been fully completed, those structural items which have been inspected did not exhibit any evidence of loss of structural integrity.
- Engineering has examint;d all accessible areas of the turbine pedestal. -3 Based on their examination they have concluded that the turbine pedestal I structural integrity remains intact.
Engineering is also examining the turbine support steel structure. Initial results found some cracks and tear of base metal in stiffeners in the low -
pressure section number 3 bearing box. These will be repaired.
The fire protection system performance during the event was reviewed by Engineering. Although there was some damage to the fire suppression system, the system responded as designed.
NRc roRu mA paa
I NRC FORM 366A U.S. NUCLEAR REGULATORY CoMMISSloN APPROVED BY oMB No. 3150-0104 p2' EXPlRES S/31/95 )
ESTIMATED BURDEN PER RESPONSE TO COMPLY WTH TH!S LICENSEE EVENT REPORT (LER) ETNOca'ES'lERD$ $$ArYiOQidETr2 TEXT CONTINUATION "# " "
Qu"E*C $$$ wSs#"o"E*E"' N ant Eds THE PAPERWORK REDUCTION PROJECT (31504104L OFFICE OF MANAGEMEPli AND BUDGET, WASHINGTOtt DC 20503 FACILITY NAME (1) DOCKET NUMBER (2) LER NUMBER (4) PAGE (3)
M#Ub h b^*' Nb* BON YEAR NUMBER NUMBER 05000 341 6 OF 7 Fermi 2 93 014 -
01 m T g, ,,,o,. .,.c. ,.y,.a ,,.. . ,,o, . or wC F ,,,, m, o 7, An assessment of the effects of poor reactor water quality on fuel and vessel internals is in progress. Preliminary results indicate that there is no immediate or short term impact on vessel structural integrity. Long term affects on the vessel structual integrity are being assessed. The interim report also noted that there may be future problems associated with the Jet Pump Holddown Beams. Detroit Edison has decided to replace these during the current outage. In addition, preliminary review of the impact of poor water
.iality indicates that the zircaloy components of fuel, including fuel rod cladding, spacers and channels, should be insignificant. Inspection of some fuel assemblies, control rod drives, and control rod blades will be conducted to further assess for water chemistry concerns.
Corrective Actions:
An assessment of the structural integrity of the turbin'e pedestal was conducted. The structural integrity of the pedestal was verified to be intact. No structural repairs will be necessary.
Flood water located in the turbine building basement and radwaste building basement floors has been removed. Approximately 1.5 million gallons of water has been processed and discharged. This includes stored, high quality water which deteriorated in quality when it mixed with untreated water during the event.
betroit Edison will complete those actions agreed to by the NRC and Detroit 5',11 son management and specified in the Confirmatory Action Letter dated December 28, 1993 These actions will be completed prior to returning the unit to power operations.
Engineering has completed an inspection of the turbine building structure.
They have concluded that the turbine building was not structurally compromised (i.e., it maintained its structural integrity) as a result of the turbine event. Some cosmetic repairs will be made. However, these repairs have no impact on structural integrity.
An investigation of the event was initiated by the Plant Manager. A turbine-generator assessment team (TGAT) was given the responsibility to determine the root cause of the main turbine generator trip and develop a plan for damage assessment, repair options, reassembly, startup, and monitoring turbine performance following implementation of the corrective action. Specifically the TGAT will:
NRC FORM 366A ($ S2)
NRC FORM 366A U.S. NUCLEAR REGULA1oRY COMMISSloN APPROVED BY oMB No. 3150-0104 i 15-92>
EXPIRES 5/31/95 j 4 (STIMATED 'URDEN PER RESPONSE TO COMPi,Y WITH TMTS LICENSEE EVENT REPORT (LER) E 0 @"J L tf8Fn'fG Unli s $ $ 0 0 ,NrOF% ? 2 TEXT CONTINUATION ^' "' " 8 "*"^"'"' "" " (MNoa mn u s NUCtEAR REGULATORY COMM SSf0N. WASH NGTON. DC 20555 CD01c AND TO THE FAPERWORK REDUCTION PRCUECT p1534904h OFFICE OF MANAGEMENT AND BUDGET, WASHINGTON, DC 20SC3 FACILITY NAME (1) DOCKt'T NUMBER (2) LER HUMBER (5) PAGE p)
LkQUt.NitAL HE Vi$ TON NUV0ER NUMBER' 05000 Fermi 2 341 93 -
014 -
01 7N7 iLx1 pt more spece a regwed, use adstronar copies or Mtc f orm 36&y (17)
Develop a sequence of events leading to the failure.
Determine the root cause of the turbine / generator failure.
Develop lessons learned Publish a final report.
The assessment of the effects of the poor water quality on the fuel and reactor vessel internals is in progress. Preliminary results indicate that it would be prudent to replace the jet pump hold down beams. This will be done during the current outage. In addition, inspection of some fuel assemblies, control rod drives, and control rod blades will be done to further assess water chemistry concerns.
Walkdown of systems located in the turbine building to as'sess any damage and identify needed repairs is in progress.
A review of the response of the Emergency Response Organization and the Fire Brigade is being conducted and lessons learned are being developed.
Previous Similar Events:
None i
l i
NAC FORM 366A (5-02) k