Similar Documents at Fermi |
---|
Category:MONTHLY OPERATING ANALYSIS REPORT
MONTHYEARNRC-99-0095, Monthly Operating Rept for Sept 1999 for Fermi 2.With1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Fermi 2.With NRC-99-0067, Monthly Operating Rept for Aug 1999 for Fermi 2.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Fermi 2.With NRC-99-0065, Monthly Operating Rept for July 1999 for Fermi 2.With1999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Fermi 2.With NRC-99-0064, Monthly Operating Rept for June 1999 for Fermi 2.With1999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Fermi 2.With NRC-99-0062, Monthly Operating Rept for May 1999 for Fermi 2.With1999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Fermi 2.With NRC-99-0022, Monthly Operating Rept for Apr 1999 for Fermi 2.With1999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Fermi 2.With ML20205P9721999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Fermi 2 ML20204D0361999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Fermi 2 ML20205Q9621998-12-31031 December 1998 Revised Monthly Operating Rept for Dec 1998 for Fermi 2 NRC-99-0005, Monthly Operating Rept for Dec 1998 for Fermi 2.With1998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Fermi 2.With NRC-98-0153, Monthly Operating Rept for Nov 1998 for Fermi 2.With1998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Fermi 2.With NRC-98-0160, Monthly Operating Rept for Oct 1998 for Fermi 2.With1998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Fermi 2.With NRC-98-0139, Monthly Operating Rept for Sept 1998 for Fermi,Unit 2.With1998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Fermi,Unit 2.With NRC-98-0111, Monthly Operating Rept for Aug 1998 for Fermi 2.With1998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Fermi 2.With NRC-98-0109, Monthly Operating Rept for July 1998 for Fermi 21998-07-31031 July 1998 Monthly Operating Rept for July 1998 for Fermi 2 NRC-98-0097, Monthly Operating Rept for June 1998 for Fermi,Unit 21998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Fermi,Unit 2 NRC-98-0079, Monthly Operating Rept for May 1998 for Fermi 21998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Fermi 2 NRC-98-0076, Monthly Operating Rept for Apr 1998 for Fermi 21998-04-30030 April 1998 Monthly Operating Rept for Apr 1998 for Fermi 2 NRC-98-0072, Monthly Operating Rept for Mar 1998 for Fermi 21998-03-31031 March 1998 Monthly Operating Rept for Mar 1998 for Fermi 2 NRC-98-0050, Monthly Operating Rept for Feb 1998 for Fermi 21998-02-28028 February 1998 Monthly Operating Rept for Feb 1998 for Fermi 2 NRC-98-0019, Monthly Operating Rept for Jan 1998 for Fermi 21998-01-31031 January 1998 Monthly Operating Rept for Jan 1998 for Fermi 2 ML20205Q9601997-12-31031 December 1997 Revised Monthly Operating Rept for Dec 1997 for Fermi 2 NRC-98-0015, Monthly Operating Rept for Dec 1997 for Fermi 21997-12-31031 December 1997 Monthly Operating Rept for Dec 1997 for Fermi 2 NRC-97-0131, Monthly Operating Rept for Nov 1997 for Fermi 21997-11-30030 November 1997 Monthly Operating Rept for Nov 1997 for Fermi 2 NRC-97-0117, Monthly Operating Rept for Oct 1997 for Fermi 21997-10-31031 October 1997 Monthly Operating Rept for Oct 1997 for Fermi 2 NRC-97-0099, Monthly Operating Rept for Sept 1997 for Fermi 21997-09-30030 September 1997 Monthly Operating Rept for Sept 1997 for Fermi 2 ML20210V0441997-08-31031 August 1997 Monthly Operating Rept for Aug 1997 for Fermi 2 ML20210V0521997-07-31031 July 1997 Revised MOR for July 1997 for Fermi 2 NRC-97-0079, Monthly Operating Rept for Jul 1997 for Fermi 21997-07-31031 July 1997 Monthly Operating Rept for Jul 1997 for Fermi 2 NRC-97-0068, Monthly Operating Rept for June 1997 for Fermi,Unit 21997-06-30030 June 1997 Monthly Operating Rept for June 1997 for Fermi,Unit 2 NRC-97-0063, Monthly Operating Rept for May 1997 for Fermi 21997-05-31031 May 1997 Monthly Operating Rept for May 1997 for Fermi 2 NRC-97-0057, Monthly Operating Rept for Apr 1997 for Fermi 21997-04-30030 April 1997 Monthly Operating Rept for Apr 1997 for Fermi 2 NRC-97-0044, Monthly Operating Rept for Mar 1997 for Fermi 21997-03-31031 March 1997 Monthly Operating Rept for Mar 1997 for Fermi 2 NRC-97-0023, Monthly Operating Rept for Feb 1997 for Fermi 21997-02-28028 February 1997 Monthly Operating Rept for Feb 1997 for Fermi 2 ML20134L7851997-01-31031 January 1997 Monthly Operating Rept for Jan 1997 for Fermi 2 ML20134L8421996-12-31031 December 1996 Revised Monthly Operating Rept for Dec 1996 for Fermi 2 NRC-97-0011, Monthly Operating Rept for Dec 1996 for Fermi 21996-12-31031 December 1996 Monthly Operating Rept for Dec 1996 for Fermi 2 ML20134L8381996-11-30030 November 1996 Revised Monthly Operating Rept for Nov 1996 for Fermi 2 NRC-96-0139, Monthly Operating Rept for Nov 1996 for Fermi 21996-11-30030 November 1996 Monthly Operating Rept for Nov 1996 for Fermi 2 ML20134L8301996-10-31031 October 1996 Revised Monthly Operating Rept for Oct 1996 for Fermi 2 NRC-96-0102, Monthly Operating Rept for Oct 1996 for Fermi 21996-10-31031 October 1996 Monthly Operating Rept for Oct 1996 for Fermi 2 ML20134L8221996-09-30030 September 1996 Revised Monthly Operating Rept for Sept 1996 for Fermi 2 NRC-96-0080, Monthly Operating Rept for Sept 1996 for Fermi 21996-09-30030 September 1996 Monthly Operating Rept for Sept 1996 for Fermi 2 ML20134L8081996-08-31031 August 1996 Revised Monthly Operating Rept for Aug 1996 for Fermi 2 NRC-96-0077, Monthly Operating Rept for Aug 1996 for Fermi 21996-08-31031 August 1996 Monthly Operating Rept for Aug 1996 for Fermi 2 ML20134L8011996-07-31031 July 1996 Revised Monthly Operating Rept for Jul 1996 for Fermi 2 NRC-96-0073, Monthly Operating Rept for Ju1 1996 for Fermi 21996-07-31031 July 1996 Monthly Operating Rept for Ju1 1996 for Fermi 2 ML20134L7981996-06-30030 June 1996 Revised Monthly Operating Rept for June 1996 for Fermi 2 NRC-96-0070, Monthly Operating Rept for June 1996 for Fermi 21996-06-30030 June 1996 Monthly Operating Rept for June 1996 for Fermi 2 ML20134L7911996-05-31031 May 1996 Revised Monthly Operating Rept for May 1996 for Fermi 2 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217N4381999-10-25025 October 1999 Safety Evaluation Supporting Amend 17 to License DPR-9 ML20217P3551999-10-22022 October 1999 LER 99-S01-00:on 990922,loaded 9mm Handgun Was Discovered on Truck Cargo Area of Vehicle Inside Protected Area.Caused by Inadequate Vehicle Search.Guidance in Procedures & Security Training to Address Multiple Vehicle Searches Was Provided NRC-99-0095, Monthly Operating Rept for Sept 1999 for Fermi 2.With1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Fermi 2.With NRC-99-0067, Monthly Operating Rept for Aug 1999 for Fermi 2.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Fermi 2.With NRC-99-0065, Monthly Operating Rept for July 1999 for Fermi 2.With1999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Fermi 2.With NRC-99-0088, Detroit Edison Co Enrico Fermi Atomic Power Plant,Unit 1 Annual Rept for Period 980701-990630. with1999-06-30030 June 1999 Detroit Edison Co Enrico Fermi Atomic Power Plant,Unit 1 Annual Rept for Period 980701-990630. with NRC-99-0064, Monthly Operating Rept for June 1999 for Fermi 2.With1999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Fermi 2.With NRC-99-0062, Monthly Operating Rept for May 1999 for Fermi 2.With1999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Fermi 2.With ML20206J9301999-05-10010 May 1999 SER Concluding That Util Adequately Addressed Actions Requested in GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Powered-Operated Gate Valves ML20206G5081999-05-0505 May 1999 Safety Evaluation Approving Request for Relief PR-8,Rev 2 on Basis That Licensee Committed to Meet All Related Requirements of ASME OM-6 Std & PR-12 on Basis That Proposed Alternative Will Provide Acceptable Level of Safety NRC-99-0022, Monthly Operating Rept for Apr 1999 for Fermi 2.With1999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Fermi 2.With ML20205Q7141999-04-15015 April 1999 Safety Evaluation Supporting Amend 16 to License DPR-9 ML20205P9721999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Fermi 2 ML20204E0371999-03-17017 March 1999 Safety Evaluation Accepting Licensee Request for NRC Approval of Alternative Rv Weld Exam,Per Provisions of 10CFR50.55a(a)(3)(i) & 10CFR50.55a(g)(6)(ii)(A)(5) for Plant,Unit 2 for 40-month Period ML20204D0361999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Fermi 2 ML20198S3341999-01-0606 January 1999 Safety Evaluation Supporting Amend 15 to License DPR-9 NRC-99-0005, Monthly Operating Rept for Dec 1998 for Fermi 2.With1998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Fermi 2.With ML20207B7491998-12-31031 December 1998 1998 Annual Operating Rept for Fermi 2 ML20205Q9621998-12-31031 December 1998 Revised Monthly Operating Rept for Dec 1998 for Fermi 2 NRC-99-0021, 1998 Annual Financial Rept for Detroit Edison Co. with1998-12-31031 December 1998 1998 Annual Financial Rept for Detroit Edison Co. with NRC-98-0153, Monthly Operating Rept for Nov 1998 for Fermi 2.With1998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Fermi 2.With NRC-98-0160, Monthly Operating Rept for Oct 1998 for Fermi 2.With1998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Fermi 2.With ML20154R2331998-10-21021 October 1998 Safety Evaluation Supporting Amend 13 to License DPR-9 ML20154L1031998-10-14014 October 1998 Safety Evaluation Accepting Licensee Response to NRC Bulletin 95-002, Unexpected Clogging of Residual Heat Removal Pump Strainer While Operating in Suppression Pool Cooling Mode NRC-98-0139, Monthly Operating Rept for Sept 1998 for Fermi,Unit 2.With1998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Fermi,Unit 2.With ML20154H8161998-09-30030 September 1998 Rev 0 to COLR Cycle 7 for Fermi 2 ML20153B8811998-09-18018 September 1998 Safety Evaluation Accepting Request for Relief from Certain Requirements of ASME Boiler & Pressure Vessel Code,Section Xi,For Plant,Unit 2 ML20151X0651998-09-11011 September 1998 Safety Evaluation Re Inservice Testing Program Relief Request VR-63 for Plant NRC-98-0111, Monthly Operating Rept for Aug 1998 for Fermi 2.With1998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Fermi 2.With ML20153B7921998-08-31031 August 1998 Rev 0 to Fermi 1 Sar ML20237E1171998-08-25025 August 1998 Safety Evaluation Accepting Licensee Relief Requests for First 10-yr Interval Inservice Insp Nondestructive Exam Program ML20236X8611998-08-0505 August 1998 SER Related to Revised Feedwater Nozzle Analysis to Facility Operating License NPF-43,Enrico Fermi Nuclear Power Plant, Unit 2 NRC-98-0109, Monthly Operating Rept for July 1998 for Fermi 21998-07-31031 July 1998 Monthly Operating Rept for July 1998 for Fermi 2 ML20236K3261998-07-0101 July 1998 SER Accepting Licensee Response Related to Revised Feedwater Nozzle Analysis to License NPF-43 for Enrico Fermi Nuclear Power Plant,Unit 2 NRC-98-0097, Monthly Operating Rept for June 1998 for Fermi,Unit 21998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Fermi,Unit 2 NRC-98-0127, Annual Rept for Period 970701-9806301998-06-30030 June 1998 Annual Rept for Period 970701-980630 NRC-98-0079, Monthly Operating Rept for May 1998 for Fermi 21998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Fermi 2 NRC-98-0076, Monthly Operating Rept for Apr 1998 for Fermi 21998-04-30030 April 1998 Monthly Operating Rept for Apr 1998 for Fermi 2 NRC-98-0072, Monthly Operating Rept for Mar 1998 for Fermi 21998-03-31031 March 1998 Monthly Operating Rept for Mar 1998 for Fermi 2 NRC-98-0050, Monthly Operating Rept for Feb 1998 for Fermi 21998-02-28028 February 1998 Monthly Operating Rept for Feb 1998 for Fermi 2 NRC-98-0019, Monthly Operating Rept for Jan 1998 for Fermi 21998-01-31031 January 1998 Monthly Operating Rept for Jan 1998 for Fermi 2 ML20198L4241998-01-0808 January 1998 Safety Evaluation Accepting Proposed Rev 2 to Relief Request VR-51 Under Fermi 2 Pump & Valve Inservice Testing Program Per 10CFR50.55a(f)(6)(i) for First 10-yr Interval NRC-98-0015, Monthly Operating Rept for Dec 1997 for Fermi 21997-12-31031 December 1997 Monthly Operating Rept for Dec 1997 for Fermi 2 ML20217N3821997-12-31031 December 1997 Annual Operating Rept for 970101-1231 NRC-98-0053, 1997 Annual Financial Rept for Detroit Edison Company1997-12-31031 December 1997 1997 Annual Financial Rept for Detroit Edison Company ML20205Q9601997-12-31031 December 1997 Revised Monthly Operating Rept for Dec 1997 for Fermi 2 NRC-97-0141, Deficiency Rept Re Malfunction of EDG Number 11 Automatic Voltage Regulator (AVR) Printed Circuit Board Rev B,Due to Failure of Operational Amplifier U8 Chip.Avr Board Rev B Was Sent Offsite to Independent Engineering Facility1997-12-23023 December 1997 Deficiency Rept Re Malfunction of EDG Number 11 Automatic Voltage Regulator (AVR) Printed Circuit Board Rev B,Due to Failure of Operational Amplifier U8 Chip.Avr Board Rev B Was Sent Offsite to Independent Engineering Facility ML20197A9921997-12-15015 December 1997 Rev 0 to Efp,Unit 1 Fermi 1 Sar NRC-97-0131, Monthly Operating Rept for Nov 1997 for Fermi 21997-11-30030 November 1997 Monthly Operating Rept for Nov 1997 for Fermi 2 ML20248H1151997-10-31031 October 1997 Rev 1 to Colr,Cycle 6 for Fermi 2 1999-09-30
[Table view] |
Text
- - - _ _ _ .
- ????b.*lL,e l v.v Detroit ...-,
'Ec ' son E!E " Reacutee 1 16 % e.L.
April 15. 1991 NRC-91-0049 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555
Reference:
Fermi 2 NRC Docket No. 50-341 NRC Operating License No. NPF-43
Subject:
Monthly Operating Status Report for March, 1991 Enclosed for your information and use is the Fermi 2 Honthly Operating Statur. Report for March,1991. This report includes the Operating Data Report Aurage Daily Unit Power Level, and the Summary of Unit Shutdowns and Power Reductions identified in NRC Regulatory Guide 1.16 and Permt 2 Technical Specification 6.9.1.6.
If you have any questions, please contact Brian Stone, at (313) 586-5148.
Sincerely.
/*
Encloture cet A. B. Davis J. R. Eckert D. P. Hahn R. W. DeFayette W. G. Rogers J. F. Stang 9104220280 910331 POR ADOCK 05000341 R PDR Id4
. t OPERATING DATA REPORT DOCKET NO. 50-341 COMPLETED BY B. J. Stone DATE April 15, 1991 TELEPHONE (313) 586-5148 OPERATING STATUS
- 1. UNIT NAME: Fermi 2 l Notes: (1) Calculated using l
- 2. REPORTING PERIOD: March, 1991 IMDC of 1093 for period prior to 1 3 LICENSED THERMAL POWER (HWL):_ 323,3 l January 1, 1990. I s
- 4. NAMEPLATE RATING (GROSS MWe): 1154 I I
- 5. l DESIGN ELECT RATING (Not MWe)t 1013 l
- 6. HAX DEPENDABLE CAP (GROSS MWe): 1105 I l )
I 7 MAX DEPENDABLE CAP (Net MWe)t _ IO55 l
- 8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS NUMBER 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS:
- 9. POWER LEVEL TO WHICH RESTRICTEO, IF ANY (MWe Net): Approximately 900
-10. REASONS FOR RESTRICTION, IF ANY: Administrative limit due to concerns about main turbine blading. .
THIS MONTH YR TO DATE CUMULATIVE
- 11. HRS IN REPORTING PERIOD 744 2160 27,926
- 12. HRS-REACTOR WAS CRITICAL 675.4 2087 3 20,605.0
- 13. REACTOR RESERVE SHUTDOWN HRS 0 0 0
- 14. HOURS GENERATOR ON-LINE 663 7 2052.5 19,610.4
- 15. UNIT RESERVE SHUTDOWN HOURS 0 -0 _0
- 16. GROS 3 THERMAL ENERGY GEN (MWH) 1,938,864 5,567,791 57,398,985
~
- 17. GROSS' ELECT ENERGY GEN (MWH) 613,920 1,754,310 18,928,847-
- 18. NET ELECT ENERGY GEN (MWH) 583,132 1,668,752_ 18,080,056 -
- 19. UNIT SERVICE FAC70R- -89.21 95.03 70.22 i
- 20. UNIT AVAILABILITY FACTOR 89.21 95.03 70.22
- 21. UNIT CAP FACTOR (USING MDC NET) 74.3 73.23 60.16
- 22. UNIT CAP' FACTOR (USING DER NET) 70.7 70.68 -59.23 23.: UNIT FORCED-0UTAGE RATE 5.00 ,
0.18 10.84
- 24. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, DURATION OF EACH)
A -rerueling outage is scheduled to begin March 29, 1991. It is presently estimated that the outage will last 75 days. (breaker to breaker).
- 25. IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:
.26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION):
FORECAST ACHIEVED 1
INITIAL CRITICALITY N/A -N/A INITIAL ELECTRICITY N/A N/A COMMERCIAL OPERATION N/A N/A a_-._,_._...._,_..
AVERAGE DAILY LRilf POWER LEVEL
. DONET NO. 50-341 ,.
UNIT FERMI 2 DATE -April 15. 1991 COMPLETED BY. E. Dawson ;
~
TELEPHONE (313) 586-5027 Honth March, 1991 - i
-l DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE-DAILY POWER LEVEL (MWe-Net) (HWe-Net)-
1 905 17 925-2' 890- 18 ,
918 3-- L906 19 918 4 905- 20 922 5 901 21 901 6 893 22 917 7 905 23 885 8 916 24- 919 9 904 25' 925 10' 907- 26 920-11 909 27 895-
_12 '- 165 28 912-13 30 29 927 i
14- 636 30 0 15 906' 31- 0 16 ?816 ;
d
, ...4 . .,,.J.,.,#_.. .s. , , , , . . .U,\,mw ,, .._,,,,,,.,.,,,.,,.,,,,,,m,_, .._m
. . , , , - _ . , , , , . ,,_..,.7_,,m_.e.,',__.y , . , . . . . . . . y
,! !1 illlll1l! jlllIlll, ill 1 ll, I1ll{Ii]IiliIIii1i v r o c o t f f sc e A T -
e en rs E E N A
Ds ri or S E = -
sge t u MASE E O L E
ron.l ef i n ao.
rhe CTNL I AEI C
C P P _
VT t rse e g TDCF L S S 1 9 IN sot c a6a C I O E E TE e3t UFL) S T T 9
9 1 e 4
t 5
CV EE eeu5 k . G2 nsc=c3 euesa1 0O u DO n T aE E A
C A
C a - DGE saR eb e SNCL W I I e 6 OPC c R n nt g NOF( A D D 5 t 6 C N r t c i an II S N N 1 S 5 COE oe. nr o i TST) I I T2 t rm.aai rol ATR1 -
1 . ) & s M ui e REC 6 A .'
9 J 3 Nu a u u n. P rt T ru GAEP1 1 I NI .
e t EOC et co n gf P*E0 FOF N _
c . ? SI E caaodo n e i TES# -
G T EI E a RTEO A B ( UTR ef vt n mR I R I -
AC S uasr ae BDrTE B PCPD -
CA orh Mt c I aNR I U T V et esdu se HRTEU H D- U E
B ras eo o yt N.O N V N x H u=nt th esu EFEE( E RC5S D E t eac v c ) )
E N seoue5 cme )
5 6 T C i nnnf1 + eh 4 E H aieaf7 + rc ( ( (
L P wLcme1 5f s E P E M T w L Illll!iliiIili1lli A A O E A D C T wC D DE) P aS A wD5 S - m O OO( P CCDL CC SIE TUD llIIliijti1iliI$lI LLANE S A AwIC2 E) UuCTUE N 5D4 :NqTNDH O vO( 8 - DAAUOET I
T SC $ OMWACEO H
C (iIllIijiiii1lIIll T - - - - - -
U E D M1 23459 E R . A A R EO / / )
LN N N 3 R (
E 1 W 9 ! llItilililIilli N O 9 O P 1 n I m T D O4 A N h. DD N A c F T !
r CGC) w S a NA3 2 t s N w DIE ( m W OTS E O HT D TUE ) E )
T H EHH N S N U T NST I N I H N A E A S O !lilIIiiiii!lliili L C L M P NI P T F OL X I
T E I E NJ R N (T T& (
t O O S C P S) ' A C EE IG R E A2 GT RN 9 R E( U TI 9)
R LR SNEAN IO EI VEI IlI{iI ii Ll A RAI A
) FE RTLL RS 9 4 C YTA aP UG TNGR RNw DM 4 S NANORTOE
( 3 A ENITOSI(
wELATI T
!lIli!illililiIilt PTELANA w I NUURI RE E : UIFGEMEH P) NQAEEPDPT vt F S OEMRROAOO T( S
!jltlfi1i!iiliijlt E A - - - - - - .-
7 ABCDEFGH 1 1 2 9 9 )
1 / / 2 w 4 i E 2 0 (
3 m T 1 3
- r A / / D 0 e D 3 3 E 5 F 0 c L DU I; .tjii]1i1ilIii1i ED CE
. RH O E OC N M 1 2 FS A 0 0
) - : -
T N . -
E O 6 1 1 FS k T N ( 9 9 C I 5 s )
?
C N (
D U 1llllli!lIiI!!ij1I