ML13207A372 | |
Person / Time | |
---|---|
Site: | Fermi |
Issue date: | 07/25/2013 |
From: | Rad Z DTE Electric Company |
To: | Hironori Peterson Operations Branch III |
References | |
NRC-13-0041 | |
Download: ML13207A372 (2) | |
Similar Documents at Fermi | |
---|---|
Category:Letter type:NRC
MONTHYEARNRC-24-0064, Supplement to License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance2024-10-31031 October 2024
[Table view]Supplement to License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance NRC-24-0058, Status of License Renewal Commitments2024-10-0303 October 2024 Status of License Renewal Commitments NRC-24-0057, Update to NRC 24-0041: Technical Specification (TS) 5.6.7 – Post Accident Monitoring Report2024-09-0303 September 2024 Update to NRC 24-0041: Technical Specification (TS) 5.6.7 – Post Accident Monitoring Report NRC-24-0053, Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30, 20242024-08-30030 August 2024 Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30, 2024 NRC-24-0050, Inservice Inspection-Nondestructive Examination (ISI-NDE) Program for the Fourth 10-Year Inspection Interval2024-08-12012 August 2024 Inservice Inspection-Nondestructive Examination (ISI-NDE) Program for the Fourth 10-Year Inspection Interval NRC-24-0048, Submittal of Inservice Inspection Summary Report2024-08-0606 August 2024 Submittal of Inservice Inspection Summary Report NRC-24-0046, Fenni 2 Power Plant - Approval of the National Pollutant Discharge Elimination System Permit Application for Reissuance2024-07-25025 July 2024 Fenni 2 Power Plant - Approval of the National Pollutant Discharge Elimination System Permit Application for Reissuance NRC-24-0020, Submittal of Revision 51 to the Fermi 2 Radiological Emergency Response Preparedness Plan2024-07-24024 July 2024 Submittal of Revision 51 to the Fermi 2 Radiological Emergency Response Preparedness Plan NRC-24-0044, Enrico Fermi 1 License Expiration - 10 CFR 50.51 (Continuation of License)2024-07-10010 July 2024 Enrico Fermi 1 License Expiration - 10 CFR 50.51 (Continuation of License) NRC-24-0041, Technical Specification (TS) 5.6.7 - Post Accident Monitoring Report2024-06-21021 June 2024 Technical Specification (TS) 5.6.7 - Post Accident Monitoring Report NRC-24-0042, Regulat01y Issues Summaty (RIS) 24-01 Preparation and Scheduling of Operator Licensing Examinations to Submit Fonn 536, Operator Licensing Examination Data2024-06-18018 June 2024 Regulat01y Issues Summaty (RIS) 24-01 Preparation and Scheduling of Operator Licensing Examinations to Submit Fonn 536, Operator Licensing Examination Data NRC-24-0040, Verification of No Significant Hazards Considerations for License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance Supplement Provided in NRC-24-00332024-06-0606 June 2024 Verification of No Significant Hazards Considerations for License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance Supplement Provided in NRC-24-0033 NRC-24-0033, DTE Electric Company - Final Response to Request for Additional Information for License Amendment Request Regarding Risk Informed Approach to Performance ECCS Strainer Performance2024-05-30030 May 2024 DTE Electric Company - Final Response to Request for Additional Information for License Amendment Request Regarding Risk Informed Approach to Performance ECCS Strainer Performance NRC-24-0017, 2023 Annual Radioactive Effluent Release Report and 2023 Radiological Environmental Operating Report2024-04-29029 April 2024 2023 Annual Radioactive Effluent Release Report and 2023 Radiological Environmental Operating Report NRC-24-0032, Transmittal of the Core Operating Limits Report for Cycle 232024-04-25025 April 2024 Transmittal of the Core Operating Limits Report for Cycle 23 NRC-24-0027, Partial Response to Request for Additional Information for License Amendment Request Regarding Risk Informed Approach to Performance ECCS Strainer Performance2024-04-24024 April 2024 Partial Response to Request for Additional Information for License Amendment Request Regarding Risk Informed Approach to Performance ECCS Strainer Performance NRC-24-0031, Retake Exam Outline Submittal Letter2024-04-22022 April 2024 Retake Exam Outline Submittal Letter NRC-24-0018, 2023 Annual Non-Radiological Environmental Operating Report2024-04-0909 April 2024 2023 Annual Non-Radiological Environmental Operating Report NRC-24-0015, Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report2024-03-31031 March 2024 Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report NRC-24-0001, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Rev. 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, TSTF-439, Rev. 2, Eliminate Second Completion2024-03-21021 March 2024 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Rev. 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, TSTF-439, Rev. 2, Eliminate Second Completion NRC-24-0019, Submittal of 2023 Safety Relief Valve Challenge Report, Main Steam Bypass Lines Report, and ECCS Cooling Performance Evaluation Model Changes or Errors Report2024-03-14014 March 2024 Submittal of 2023 Safety Relief Valve Challenge Report, Main Steam Bypass Lines Report, and ECCS Cooling Performance Evaluation Model Changes or Errors Report NRC-24-0023, NRC-24-0023, Post Exam Package Submittal Letter to NRC2024-03-0707 March 2024 NRC-24-0023, Post Exam Package Submittal Letter to NRC NRC-24-0008, Levels and Sources of Property Insurance Coverage2024-02-15015 February 2024 Levels and Sources of Property Insurance Coverage NRC-24-0009, Request for NRC to Suspend Regulatory Audit of License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance for Fermi Unit 22024-02-0606 February 2024 Request for NRC to Suspend Regulatory Audit of License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance for Fermi Unit 2 NRC-24-0002, Clarification for Request for Additional Information Responses for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.122024-01-12012 January 2024 Clarification for Request for Additional Information Responses for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 NRC-24-0007, Report of Changes to Quality Assurance Program for Radioactive Material Packages2024-01-12012 January 2024 Report of Changes to Quality Assurance Program for Radioactive Material Packages NRC-23-0079, Transmittal of Revision 1 of the Core Operating Limits Report for Cycle 222023-12-14014 December 2023 Transmittal of Revision 1 of the Core Operating Limits Report for Cycle 22 NRC-23-0077, Submittal of Revision 50 to the Fermi 2 Radiological Emergency Response Preparedness Plan2023-12-0404 December 2023 Submittal of Revision 50 to the Fermi 2 Radiological Emergency Response Preparedness Plan NRC-23-0075, Request for Exemption from Enhanced Weapons, Firearms Background Checks and Security Event Notification Implementation2023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks and Security Event Notification Implementation NRC-23-0073, Guarantee of Payment of Deferred Premiums2023-11-29029 November 2023 Guarantee of Payment of Deferred Premiums NRC-23-0071, Response to Request for Additional Information (RAI) for Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating2023-10-13013 October 2023 Response to Request for Additional Information (RAI) for Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating NRC-23-0062, Response to Request for Additional Information for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.122023-10-12012 October 2023 Response to Request for Additional Information for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 NRC-23-0068, Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating2023-09-28028 September 2023 Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating NRC-23-0064, Additional Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-09-11011 September 2023 Additional Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0057, Independent Spent Fuel Storage Installation Cask Registration2023-08-31031 August 2023 Independent Spent Fuel Storage Installation Cask Registration NRC-23-0054, Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30 20232023-08-31031 August 2023 Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30 2023 NRC-23-0056, Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval2023-08-31031 August 2023 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval NRC-23-0061, Clarification for NRC-23-0059, Response to Request for Additional Information for Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water..2023-08-30030 August 2023 Clarification for NRC-23-0059, Response to Request for Additional Information for Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water.. NRC-23-0059, Response to Request for Additional Information Exigent License Amendment Request for Technical Specification 3.7.2,Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-08-25025 August 2023 Response to Request for Additional Information Exigent License Amendment Request for Technical Specification 3.7.2,Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0060, Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-08-25025 August 2023 Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0053, Independent Spent Fuel Storage Installation Cask Registration2023-08-23023 August 2023 Independent Spent Fuel Storage Installation Cask Registration NRC-23-0050, Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-08-10010 August 2023 Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0048, Independent Spent Fuel Storage Installation Cask Registration2023-08-0101 August 2023 Independent Spent Fuel Storage Installation Cask Registration NRC-23-0049, Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-07-24024 July 2023 Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0043, Independent Spent Fuel Storage Installation, Cask Registration2023-06-27027 June 2023 Independent Spent Fuel Storage Installation, Cask Registration NRC-23-0020, License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance2023-06-13013 June 2023 License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance NRC-23-0039, Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-06-0606 June 2023 Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0030, Inservice Inspection-Nondestructive Examination (ISI-NDE) Program for the Fourth 10-Year Inspection Interval2023-06-0505 June 2023 Inservice Inspection-Nondestructive Examination (ISI-NDE) Program for the Fourth 10-Year Inspection Interval NRC-23-0029, Snubber Program for the Fourth 10-Year Testing Interval2023-06-0505 June 2023 Snubber Program for the Fourth 10-Year Testing Interval NRC-23-0037, 56542-EN 56542 - Fermi2023-05-26026 May 2023 56542-EN 56542 - Fermi 2024-09-03 Category:Licensee Event Report (LER) MONTHYEAR05000341/LER-2024-002, Primary Containment Isolation Valve Declared Inoperable for a Period Prohibited by Technical Specifications2024-05-16016 May 2024
[Table view]Primary Containment Isolation Valve Declared Inoperable for a Period Prohibited by Technical Specifications 05000341/LER-2024-001, Automatic RPS Scram on High RPV Pressure While Attempting to Lower Generator Output During RF-222024-05-15015 May 2024 Automatic RPS Scram on High RPV Pressure While Attempting to Lower Generator Output During RF-22 05000341/LER-2023-002, Technical Specification Completion Time Exceeded Due to Repairs on the MDCT Fan D2023-09-15015 September 2023 Technical Specification Completion Time Exceeded Due to Repairs on the MDCT Fan D 05000341/LER-2023-001-01, Loss of Mechanical Draft Cooling Tower Fan Brakes During High Speeds Leads to Loss of Safety Function and Inoperability2023-06-23023 June 2023 Loss of Mechanical Draft Cooling Tower Fan Brakes During High Speeds Leads to Loss of Safety Function and Inoperability 05000341/LER-2023-001, Loss of Mechanical Draft Cooling Tower Fan Brakes During High Speeds Leads to Loss of Safety Function and Inoperability2023-05-22022 May 2023 Loss of Mechanical Draft Cooling Tower Fan Brakes During High Speeds Leads to Loss of Safety Function and Inoperability 05000341/LER-2022-004, Containment Isolation Valve Actuator Found Disconnected from Its Bonnet Resulting in Condition Prohibited by Technical Specifications2022-10-31031 October 2022 Containment Isolation Valve Actuator Found Disconnected from Its Bonnet Resulting in Condition Prohibited by Technical Specifications 05000341/LER-2022-003, Turbine Trip and Subsequent Reactor Trip Due to Mayflies2022-08-23023 August 2022 Turbine Trip and Subsequent Reactor Trip Due to Mayflies 05000341/LER-2022-002, Unexpected High Pressure Coolant Injection Turbine Trip2022-07-0606 July 2022 Unexpected High Pressure Coolant Injection Turbine Trip 05000341/LER-2022-001, Reactor Scram on Low Reactor Pressure Vessel Level2022-04-0404 April 2022 Reactor Scram on Low Reactor Pressure Vessel Level 05000341/LER-2021-002-01, Unplanned Inoperability of High Pressure Coolant Injection System Due to an Inverter Circuit Failure2022-03-15015 March 2022 Unplanned Inoperability of High Pressure Coolant Injection System Due to an Inverter Circuit Failure 05000341/LER-2021-003, High Pressure Coolant Injection Inoperable Due to Contact Oxidation2021-12-29029 December 2021 High Pressure Coolant Injection Inoperable Due to Contact Oxidation 05000341/LER-2021-002, Unplanned Inoperability of High Pressure Coolant Injection System Due to an Inverter Circuit Failure2021-10-21021 October 2021 Unplanned Inoperability of High Pressure Coolant Injection System Due to an Inverter Circuit Failure 05000341/LER-2017-0052017-11-0303 November 2017 Non-Functional Mechanical Draft Cooling Tower Fan Brakes Leads to HPCI Being Declared Inoperable and Loss of Safety Function, LER 17-005-00 for Fermi 2 Regarding Non-Functional Mechanical Draft Cooling Tower Fan Brakes Leads to HPCI Being Declared Inoperable and Loss of Safety Function 05000341/LER-2017-0042017-10-0909 October 2017 Inadequate Procedural Cuidance for Residual I feat Removal Complex Ventilation Systems Leads to Condition Prohibited by Technical Specifications and Loss if Safety Function, LER 17-004-00 for Fermi 2 Regarding Inadequate Procedural Guidance for Residual Heat Removal Complex Ventilation Systems Leads to Condition Prohibited by Technical Specifications and Loss of Safety Function 05000341/LER-2017-0032017-07-21021 July 2017 Division 2 Residual Heat Removal Service Water System (RHRSW) Inoperable Due to an Inoperable RHRSW Flow Control Valve, LER 17-003-00 for Fermi 2 Regarding Division 2 Residual Heat Removal Service Water System (RHRSW) Inoperable Due to an Inoperable RHRSW Flow Control Valve NRC-17-0040, (LER) SER 17-S01-00 for Fermi 2 Regarding Unescorted Access Granted for Individual Subsequent to Being Denied Unescorted Access at Another Nuclear Facility2017-05-15015 May 2017 (LER) SER 17-S01-00 for Fermi 2 Regarding Unescorted Access Granted for Individual Subsequent to Being Denied Unescorted Access at Another Nuclear Facility 05000341/LER-2017-0022017-03-16016 March 2017 High Water Level Indications at Low Reactor Pressures Causes Some Functions of High Pressure Coolant Injection System and Reactor Core Isolation Cooling System to be Inoperable, LER 17-002-00 for Fermi 2 Regarding High Water Level Indications at Low Reactor Pressures Causes Some Functions of High Pressure Coolant Injection System and Reactor Core Isolation Cooling System to be Inoperable 05000341/LER-2017-0012017-03-0606 March 2017 Loss of Reactor Protection System Scram Function During Main Steam Isolation Valve and Turbine Stop Valve Channel Functional Tests due to Use of a Test Box, LER 17-001-00 for Fermi 2 Regarding Loss of Reactor Protection System Scram Function During the Main Steam Isolation Valve and Turbine Stop Valve Channel Functional Tests due to Use of a Test Box 05000341/LER-2016-0012017-01-23023 January 2017 Turbine Stop Valve Closure and Turbine Control Valve Fast Closure Reactor Protection System Functions Considered Inoperable Due to Open Turbine Bypass Valves, LER 16-001-01 for Fermi 2 Regarding Turbine Stop Valve Closure and Turbine Control Valve Fast Closure Reactor Protection System Functions Considered Inoperable Due to Open Turbine Bypass Valves ML16138A3352016-05-17017 May 2016 ASP Screening Analysis - Reject Fermi Unit 2 (341-15-002) 05000341/LER-2016-0022016-03-22022 March 2016 Both Residual Heat Removal Low Pressure Coolant Injection Divisions Inoperable Due to Inoperable Injection Valve, LER 16-002-00 for Fermi 2, Regarding Both Residual Heat Removal Low Pressure Coolant Injection Divisions Inoperable Due to Inoperable Injection Valve NRC-13-0041, Submittal of Initial License Operator Examination2013-07-25025 July 2013 Submittal of Initial License Operator Examination NRC-09-0004, LER 08-S02-00 for Fermi 2 Regarding Fitness for Duty (FFD) Drug Testing Results in Reinstated Access Authorization Being Revoked2009-01-26026 January 2009 LER 08-S02-00 for Fermi 2 Regarding Fitness for Duty (FFD) Drug Testing Results in Reinstated Access Authorization Being Revoked NRC-08-0062, LER 08-S01-00 for Fermi 2 Regarding Unescorted Access Revoked Upon Discovery of Adverse Information2008-09-29029 September 2008 LER 08-S01-00 for Fermi 2 Regarding Unescorted Access Revoked Upon Discovery of Adverse Information ML0509505552004-12-17017 December 2004 Final Precursor Analysis - Fermi Grid Loop NRC-04-0083, LER 04-S02-00, Fermi 2 Unescorted Access Revoked Upon Discovery of Adverse Information in Background Check2004-11-0808 November 2004 LER 04-S02-00, Fermi 2 Unescorted Access Revoked Upon Discovery of Adverse Information in Background Check NRC-03-0020, LER 03-S01-00, Fermi 2, Unescorted Access Granted Prior to Verification of Fitness for Duty Drug Testing Results2003-03-0505 March 2003 LER 03-S01-00, Fermi 2, Unescorted Access Granted Prior to Verification of Fitness for Duty Drug Testing Results 2024-05-16 |
Text
10 CFR 55.40 July 25, 2013 NRC-13-0041 Mr. Hironori Peterson Chief, Operations Branch Division of Reactor Safety Region III U. S. Nuclear Regulatory Commission 2443 Warrenville Road, Suite 210 Lisle, Illinois 60532-4352
References:
- 1) Fermi 2 NRC Docket No. 50-341 NRC License No. NPF-43
- 2) NRC letter dated March 11, 2013, "Fermi Power Plant Confirmation of Initial License Examination"
Subject:
Fermi 2 Initial License Operator Examination Enclosed please find the following examination material in preparation for the Fermi 2 Initial License Operator Examination scheduled to occur during the week of September 9, 2013:
" Modified Examination Outlines (modified during the examination development process)
" Seventy-five (75) written examination items for the Reactor Operator examination
" Twenty-five (25) written examination items for the Senior Reactor Operator examination
" Eleven (11) Plant Systems related Job Performance Measures
. Eight (8) Administrative topic Job Performance Measures
. Two (2) Simulator Scenarios
" Supporting Reference Material
- Quality Verification Checklists from NUREG 1021, Revision 9.
USNRC NRC-13-0041 Page 2 The examination material was developed using the appropriate guidance contained in NUREG 1021, "Operator Licensing Examination Standards for Power Reactors,"
Revision 9, Supplement 1. The examination material shall be withheld from public disclosure until after the examinations are complete.
We look forward to working with you and your examination team during the examination development and administration process. If you have any questions or conments regarding the contents of the items listed above, please contact Mr. David G. Coseo, General Supervisor, Operations Training, at (734) 586-4055.
Sincerely, Zackary W. Rad Enclosures cc: [w/o Enclosures]
NRC Project Manager Reactor Projects Chief, Branch 5, Region III NRC Resident Office Document Control Desk Washington D C