NRC-11-0014, Decommissioning Funding Status Report

From kanterella
(Redirected from NRC-11-0014)
Jump to navigation Jump to search
Decommissioning Funding Status Report
ML110900577
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 03/30/2011
From: Plona J
DTE Energy
To:
Document Control Desk, NRC/FSME
References
NRC-11-0014
Download: ML110900577 (9)


Text

Joseph H. Plona Site Vice President 6400 N.Dixie Highway, Newport, MI 48166 Tel: 734.586.5910 Fax: 734.586.4172 10 CFR 50.75(f)(1)

March 30, 2011 NRC-11-0014 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington DC 20555-0001

Reference:

Enrico Fermi Atomic Power Plant, Unit No. 1 NRC Docket No. 50-16 NRC License No. DPR-9

Subject:

Decommissioning Funding Status Report for Fermi 1 This letter provides the report required by 10 CFR 50.75(f)(1) on the status of Detroit Edison's decommissioning fund for Fermi 1.

Fermi 1 is a permanently shutdown experimental sodium cooled breeder reactor, which last operated in 1972. It is in the SAFSTOR status and its possession-only license expires in 2025. Decommissioning activities are being performed with the goal of removing the radioactive material and terminating the Fermi 1 license. The cost of decommissioning continues to be evaluated as decommissioning proceeds. The decommissioning estimate provided is based on an end of year review, as required. A more detailed financial review of the project is currently in progress.

The requested annual decommissioning fund information for Fermi 1, reported in 2010 dollars, is provided in Enclosure 1 of this letter. The prepayment trust method and Detroit Edison funding combined with a DTE Energy guarantee is providing funding assurance. Documentation of the financial test for this guarantee is provided in of this letter.

USNRC NRC-11-0014 Page 2 Should you have any questions or require additional information, please contact Ms. Lynne Goodman of my staff at (734) 586-1205.

Sincerely, Enclosures cc: NRC Project Manager (T. Smith)

NRC Resident Office NRC Region III (P. Lee)

Regional Administrator, Region III Supervisor, Electric Operations, Michigan Public Service Commission

USNRC NRC-11-0014 Page 3 bcc: P. B. Cavazos G. H. Cerullo W. A. Colonnello J. M. Davis L. S. Goodman T. Grimaldi M. K. Homan R. W. Johnson J. J. Musial K. L. O'Neill R. K. Pelzer J. H. Plona D. T. Richards L. D. Schenk S. Stasek K. H. Stump Fermi 1 Staff Information Management (140 NOC)

[Fermi 1 Decommissioning Funding Records]

NRR Chron File NRC Notebook (Fermi 1)

ENCLOSURE 1 to NRC-11-0014 FERMI 1 DECOMMISSIONING FUNDING STATUS REPORT Enrico Fermi Atomic Power Plant, Unit 1 NRC Docket No. 50-16 NRC License No. DPR-9 to NRC-11-0014 Page 1 Decommissioning Funding Status Report Fermi 1 (Millions of Dollars)

1. The decommissioning cost estimate for Fermi 1 is based on a site- -$22.5 specific estimate adjusted by ongoing engineering reviews. The estimated remaining decommissioning cost in 2010 dollars, including a contingency of 25% or $4.5 million'.
2. The market value of the Fermi 1 trust fund was approximately $2.6 million -$2.6 as of December 31, 2010. This amount is greater than the amount needed to return the facility to a passive safe storage condition if the project were to cease.
3. Amount fund is above (or below) estimated remaining costs. -$(20)

A DTE Energy guarantee has been chosen as the assurance method for Fermi 1's shortfall.

4. The assumptions used regarding escalation in decommissioning cost, rates of earnings on decommissioning fund, and rates of other factors used in funding projections.

Decommissioning costs are assumed to increase at a rate equal to 0% due to the majority of the money to be spent within the next 12 months, with earnings on decommissioning fund to be equal to 0%.

5. Any modifications to the current method of providing financial None assurance occurring since the last submitted report.
6. Any material changes to the trust agreement. None IThe project cost estimate cited in the DTE Energy guarantee funding assurance document included an identified contingency of $3.0 million.

ENCLOSURE 2 to NRC-11-0014 FERMI 1 DECOMMISSIONING FUNDING STATUS REPORT DTE Energy Guarantee Financial Test Enrico Fermi Atomic Power Plant, Unit 1 NRC Docket No. 50-16 NRC License No. DPR-9

pwc Report of Independent Accountants To The Detroit Edison Company We have performed the procedures enumerated below, which were agreed to by The Detroit Edison Company (the "Company") and the U.S. Nuclear Regulatory Commission ("NRC"), solely to assist you in the Company's compliance with the NRC financial assurance regulations, to CFR Part 50, as of December 31, 2010, as detailed in the "Letter from David E. Meador, Chief Financial Officer of DTE Energy Company, Corporate Parent of The Detroit Edison Company, Including Costs Estimates and Data from Audited Financial Statements" (the "Letter") to be provided to the NRC. The Company is responsible for the Letter. This agreed-upon procedures engagement was conducted in accordance with attestation standards established by the American Institute of Certified Public Accountants. The sufficiency of these procedures is solely the responsibility of those parties specified in this report.

Consequently, we make no representation regarding the sufficiency of the procedures described below either for the purpose for which this report has been requested or for any other purpose.

1. We compared the amount of "Tangible net worth" per line 5 of the Letter to "Total Equity" less the sum of "Goodwill" and "Intangible assets," as reflected in the audited consolidated financial statements of DTE Energy Company as of December 31, 2010, and found the amounts to be in agreement.
2. We compared the amount of "Total assets in the United States" per line 6 of the Letter to a schedule prepared by the Company from its accounting records. We compared the amounts listed on the schedule to the corresponding amounts included in the Company's accounting records and found the amounts to be in agreement, after giving effect to rounding.

We were not engaged to and did not conduct an examination, the objective of which would be the expression of an opinion on the Letter. Accordingly, we do not express such an opinion. Had we performed additional procedures, other matters might have come to our attention that would have been reported to you.

This report is intended solely for the information and use of The Detroit Edison Company and the U.S.

Nuclear Regulatory Commission, and is not intended to be and should not be used by anyone other than these specified parties.

March 25, 2011 PricewaterhouseCoopersLLP, 19oo St. Antoine Street, Detroit,MI 48226-2263 T: (313) 394 6ooo, F: (313) 394 6555, www.pwc.com/us

LETTER FROM David E. Meador, CHIEF FINANCIAL OFFICER OF DTE Energy Company, CORPORATE PARENT of The Detroit Edison Company, INCLUDING COST ESTIMATES AND DATA FROM AUDITED FINANCIAL STATEMENTS U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C. 20555-0001 I am the Chief Financial Officer of DTE Energy Company (DTE or firm), One Energy Plaza, Detroit, MI 48226-1279, a Michigan corporation. This letter is in support of this firm's use of the financial test to demonstrate financial assurance, as specified in 10 CFR Part 50.

DTE guarantees, through the parent company guarantee submitted to demonstrate compliance under 10 CFR Part 50, the decommissioning of the following facility owned by The Detroit Edison Company, a Michigan corporation and wholly-owned subsidiary of this firm. The current cost estimates for decommissioning, and the amounts being guaranteed, are shown for each facility:

Name of Location of Current Amount Being Facility Facility Cost Estimates Guaranteed Enrico Fermi 6400 N. Dixie Hwy $21,000,000 $20,000,000 Atomic Power Newport, MI 48166 Plant Unit 1 This firm is required to file a Form 10-K with the U.S. Securities and Exchange Commission for the latest fiscal year 2010.

This fiscal year of this firm ended on December 31. The figures for the following items marked with an asterisk are derived from this firm's independently audited, year-end financial statements and footnotes for the latest completed fiscal year, ended December 31, 2010.

FINANCIAL TEST: ALTERNATIVE II

1. Decommissioning cost estimates or guaranteed amount for facility

[license number DPR 9] $20,000,000

2. Current notes rating of most recent unsecured issuance of this firm Rating BBB+/Baa2 Name of rating service Standard & Poor's / Moody's Investors Service
3. Date of issuance of notes May 2009
4. Date of maturity of notes May 15, 2014

5*. Tangible net worth** $4,680,000,000 6*. Total assets in the United States $24,868,000,000 Yes No

7. Is line 5 at least $10 million? X
8. Is line 5 at least 6 times line 1? X
9. Are at least 90 percent of firm's assets located in the United States? If not, complete line 10. X
10. Is line 6 at least 6 times line 1? X
11. Is the rating specified on line 2 "BBB" or better (if issued by Standard & Poor's) or "Baa" or better (if issued by Moody's)*** X
  • denotes figures derived from financial statements
  • Tangible net worth is defined as net worth minus goodwill, patents, trademarks, and copyrights
      • "BBB" and "Baa" are rating categories, not specific ratings, so DTE has interpreted the criteria to be that the ratings are within the BBB category or Baa category or better. DTE meets this standard.

I certify that the information is true and correct to the best of my knowledge DTE Energy Company By___

David E. Meador Executive Vice President and Chief Financial Officer, DTE Energy Company March 25, 2011