Fermi 2 6400 North Dixie Hwy., Newport, MI 48166 Detroit Edison Generic Letter 97-02 November 11, 2004 NRC-04-0087 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington D C 20555
Reference:
Fermi 2 NRC Docket No. 50-341 NRC Operating License No. NPF-43
Subject:
Monthly Operating Status Report for October 2004 Enclosed for your information and use is the Fermi 2 Monthly Operating Status Report for October 2004. This report includes the Operating Data Report and Summary of Unit Shutdowns identified in NRC Generic Letter 97-02 and Fermi 2 Technical Specification 5.6.4.
Should you have any questions or require additional information, please contact me at (734) 586-4258.
Sincerely, N J.manPeterson Manager - Nuclear Licensing Enclosure cc: R. J. Aben, Jr.
D. P. Beaulieu E. R. Duncan M. V. Yudasz, Jr.
NRC Resident Office Regional Administrator, Region m Region m ADTE Energy Company
OPERATING DATA REPORT DOCKET NO. 50-341 UNIT NAME Fermi 2 DATE November 11. 2004 COMPLETED BY Kevin Burke TELEPHONE (734) 586-5148 REPORTING PERIOD: October 2004
- 1. Design Electrical Rating (MWe-Net) 1,150.00
- 2. Maximum Dependable Capacity (Mwe-Net) 1.089.00 This Month Year-to-Date Cumulative
- 3. Number of Hours the Reactor Was Critical 745.0 7,091 114,987
- 4. Number of Hours Generator On-line 745.0 7,032 111,041
- 5. Reserve Shutdown Hours 0.00 0.00 0.00
- 6. Net Electrical Energy Generated (MWH) 823,176 7.688,741 112,312,309 UNIT SHUTDOWNS No. Date Type Duration Reason Method of Cause and Corrective Action F: Forced (Hours) (1) Shutting Comments 5: Scheduled Down (2)
N/A
SUMMARY
- The plant operated at full power during the month (excluding small power reductions for required surveillance testing) with the following exceptions: On October 10, 2004 at 0114 hours0.00132 days <br />0.0317 hours <br />1.884921e-4 weeks <br />4.3377e-5 months <br />, reduced power from 100% to 73% for Control Rod Pattern Adjustment and plant was returned to full power at 0622 hours0.0072 days <br />0.173 hours <br />0.00103 weeks <br />2.36671e-4 months <br />. On October 24, 2004 at 0100 hours0.00116 days <br />0.0278 hours <br />1.653439e-4 weeks <br />3.805e-5 months <br /> reduced power from 100% to 71% for Control Rod Pattern Adjustment and plant was returned to full power at 0605 hours0.007 days <br />0.168 hours <br />0.001 weeks <br />2.302025e-4 months <br />. On October 31, 2004 at 2046 hours0.0237 days <br />0.568 hours <br />0.00338 weeks <br />7.78503e-4 months <br />, a Reactor Recirculation Pump runback occurred and reactor power decreased to 62 %.
Restoration from this condition occurred in November 2004.
(1) Reason: (2) Method:
A Equipment Failure (Explain) 1 Manual B Maintenance or Test 2 Manual Trip/Scram C Refueling 3 Automatic Trip/Scram D Regulatory Restriction 4 Continuation E Operator Training and License Examination 5 Other (Explain)
F Administration G Operational Error (Explain)
H Other (Explain)
Text
Fermi 2 6400 North Dixie Hwy., Newport, MI 48166 Detroit Edison Generic Letter 97-02 November 11, 2004 NRC-04-0087 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington D C 20555
Reference:
Fermi 2 NRC Docket No. 50-341 NRC Operating License No. NPF-43
Subject:
Monthly Operating Status Report for October 2004 Enclosed for your information and use is the Fermi 2 Monthly Operating Status Report for October 2004. This report includes the Operating Data Report and Summary of Unit Shutdowns identified in NRC Generic Letter 97-02 and Fermi 2 Technical Specification 5.6.4.
Should you have any questions or require additional information, please contact me at (734) 586-4258.
Sincerely, N J.manPeterson Manager - Nuclear Licensing Enclosure cc: R. J. Aben, Jr.
D. P. Beaulieu E. R. Duncan M. V. Yudasz, Jr.
NRC Resident Office Regional Administrator, Region m Region m ADTE Energy Company
OPERATING DATA REPORT DOCKET NO. 50-341 UNIT NAME Fermi 2 DATE November 11. 2004 COMPLETED BY Kevin Burke TELEPHONE (734) 586-5148 REPORTING PERIOD: October 2004
- 1. Design Electrical Rating (MWe-Net) 1,150.00
- 2. Maximum Dependable Capacity (Mwe-Net) 1.089.00 This Month Year-to-Date Cumulative
- 3. Number of Hours the Reactor Was Critical 745.0 7,091 114,987
- 4. Number of Hours Generator On-line 745.0 7,032 111,041
- 5. Reserve Shutdown Hours 0.00 0.00 0.00
- 6. Net Electrical Energy Generated (MWH) 823,176 7.688,741 112,312,309 UNIT SHUTDOWNS No. Date Type Duration Reason Method of Cause and Corrective Action F: Forced (Hours) (1) Shutting Comments 5: Scheduled Down (2)
N/A
SUMMARY
- The plant operated at full power during the month (excluding small power reductions for required surveillance testing) with the following exceptions: On October 10, 2004 at 0114 hours0.00132 days <br />0.0317 hours <br />1.884921e-4 weeks <br />4.3377e-5 months <br />, reduced power from 100% to 73% for Control Rod Pattern Adjustment and plant was returned to full power at 0622 hours0.0072 days <br />0.173 hours <br />0.00103 weeks <br />2.36671e-4 months <br />. On October 24, 2004 at 0100 hours0.00116 days <br />0.0278 hours <br />1.653439e-4 weeks <br />3.805e-5 months <br /> reduced power from 100% to 71% for Control Rod Pattern Adjustment and plant was returned to full power at 0605 hours0.007 days <br />0.168 hours <br />0.001 weeks <br />2.302025e-4 months <br />. On October 31, 2004 at 2046 hours0.0237 days <br />0.568 hours <br />0.00338 weeks <br />7.78503e-4 months <br />, a Reactor Recirculation Pump runback occurred and reactor power decreased to 62 %.
Restoration from this condition occurred in November 2004.
(1) Reason: (2) Method:
A Equipment Failure (Explain) 1 Manual B Maintenance or Test 2 Manual Trip/Scram C Refueling 3 Automatic Trip/Scram D Regulatory Restriction 4 Continuation E Operator Training and License Examination 5 Other (Explain)
F Administration G Operational Error (Explain)
H Other (Explain)