NRC-03-0033, Decommissioning Funding Status Report for Fermi 2
ML030980671 | |
Person / Time | |
---|---|
Site: | Fermi |
Issue date: | 03/28/2003 |
From: | Detroit Edison |
To: | Document Control Desk, Office of Nuclear Reactor Regulation |
References | |
NRC-03-0033 | |
Download: ML030980671 (3) | |
Similar Documents at Fermi | |
---|---|
Category:Decommissioning Funding Plan DKTs 30
MONTHYEARNRC-24-0015, Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report2024-03-31031 March 2024
[Table view]Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report NRC-23-0021, ISFSI, Decommissioning Funding Plan Update2023-03-30030 March 2023 ISFSI, Decommissioning Funding Plan Update NRC-23-0015, Decommissioning Funding Status Report for Fermi 12023-03-30030 March 2023 Decommissioning Funding Status Report for Fermi 1 NRC-23-0016, Decommissioning Funding Status Report2023-03-30030 March 2023 Decommissioning Funding Status Report NRC-22-0011, Enrico Fermi Atomic Power Plant, Unit No. 1 - Decommissioning Funding Status Report2022-03-31031 March 2022 Enrico Fermi Atomic Power Plant, Unit No. 1 - Decommissioning Funding Status Report NRC-21-0018, Enrico Fermi Atomic Power Plant, Unit No. 1 - Decommissioning Funding Status Report2021-03-31031 March 2021 Enrico Fermi Atomic Power Plant, Unit No. 1 - Decommissioning Funding Status Report NRC-21-0019, Decommissioning Funding Status Report for Fermi 22021-03-31031 March 2021 Decommissioning Funding Status Report for Fermi 2 NRC-20-0018, Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report2020-03-31031 March 2020 Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report NRC-20-0020, ISFSI Decommissioning Funding Plan Update2020-03-30030 March 2020 ISFSI Decommissioning Funding Plan Update NRC-19-0022, Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report2019-03-29029 March 2019 Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report NRC-19-0023, Decommissioning Funding Status Report2019-03-28028 March 2019 Decommissioning Funding Status Report NRC-17-0023, ISFSI Decommissioning Funding Plan Update2017-03-30030 March 2017 ISFSI Decommissioning Funding Plan Update NRC-17-0022, Decommissioning Funding Status Report for Fermi 22017-03-30030 March 2017 Decommissioning Funding Status Report for Fermi 2 NRC-16-0025, Decommissioning Funding Status Report2016-03-29029 March 2016 Decommissioning Funding Status Report NRC-14-0050, ISFSI Decommissioning Funding Plan2014-07-0202 July 2014 ISFSI Decommissioning Funding Plan NRC-14-0019, Decommissioning Funding Status Report2014-03-31031 March 2014 Decommissioning Funding Status Report NRC-13-0016, Decommissioning Funding Status Report2013-03-28028 March 2013 Decommissioning Funding Status Report NRC-13-0015, Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report2013-03-28028 March 2013 Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report NRC-12-0020, Decommissioning Funding Status Report2012-03-29029 March 2012 Decommissioning Funding Status Report NRC-11-0052, Response to Request for Additional Information Regarding Decommissioning Funding Status Report2011-11-18018 November 2011 Response to Request for Additional Information Regarding Decommissioning Funding Status Report ML1009700272010-03-31031 March 2010 Decommissioning Funding Status Report NRC-09-0019, Decommissioning Funding Status Report2009-03-31031 March 2009 Decommissioning Funding Status Report NRC-09-0020, Decommissioning Funding Status Report2009-03-25025 March 2009 Decommissioning Funding Status Report NRC-08-0026, Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report2008-03-31031 March 2008 Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report NRC-07-0016, Decommissioning Funding Status Report for Fermi 22007-03-29029 March 2007 Decommissioning Funding Status Report for Fermi 2 NRC-05-0022, Decommissioning Funding Status Report for Fermi 22005-03-28028 March 2005 Decommissioning Funding Status Report for Fermi 2 NRC-03-0033, Decommissioning Funding Status Report for Fermi 22003-03-28028 March 2003 Decommissioning Funding Status Report for Fermi 2 NRC-03-0031, Decommissioning Funding Status Report for Fermi 12003-03-26026 March 2003 Decommissioning Funding Status Report for Fermi 1 2024-03-31 Category:40 MONTHYEARNRC-24-0015, Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report2024-03-31031 March 2024
[Table view]Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report NRC-23-0021, ISFSI, Decommissioning Funding Plan Update2023-03-30030 March 2023 ISFSI, Decommissioning Funding Plan Update NRC-23-0015, Decommissioning Funding Status Report for Fermi 12023-03-30030 March 2023 Decommissioning Funding Status Report for Fermi 1 NRC-23-0016, Decommissioning Funding Status Report2023-03-30030 March 2023 Decommissioning Funding Status Report NRC-22-0011, Enrico Fermi Atomic Power Plant, Unit No. 1 - Decommissioning Funding Status Report2022-03-31031 March 2022 Enrico Fermi Atomic Power Plant, Unit No. 1 - Decommissioning Funding Status Report NRC-21-0018, Enrico Fermi Atomic Power Plant, Unit No. 1 - Decommissioning Funding Status Report2021-03-31031 March 2021 Enrico Fermi Atomic Power Plant, Unit No. 1 - Decommissioning Funding Status Report NRC-21-0019, Decommissioning Funding Status Report for Fermi 22021-03-31031 March 2021 Decommissioning Funding Status Report for Fermi 2 NRC-20-0018, Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report2020-03-31031 March 2020 Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report NRC-20-0020, ISFSI Decommissioning Funding Plan Update2020-03-30030 March 2020 ISFSI Decommissioning Funding Plan Update NRC-19-0022, Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report2019-03-29029 March 2019 Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report NRC-19-0023, Decommissioning Funding Status Report2019-03-28028 March 2019 Decommissioning Funding Status Report NRC-17-0023, ISFSI Decommissioning Funding Plan Update2017-03-30030 March 2017 ISFSI Decommissioning Funding Plan Update NRC-17-0022, Decommissioning Funding Status Report for Fermi 22017-03-30030 March 2017 Decommissioning Funding Status Report for Fermi 2 NRC-16-0025, Decommissioning Funding Status Report2016-03-29029 March 2016 Decommissioning Funding Status Report NRC-14-0050, ISFSI Decommissioning Funding Plan2014-07-0202 July 2014 ISFSI Decommissioning Funding Plan NRC-14-0019, Decommissioning Funding Status Report2014-03-31031 March 2014 Decommissioning Funding Status Report NRC-13-0015, Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report2013-03-28028 March 2013 Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report NRC-13-0016, Decommissioning Funding Status Report2013-03-28028 March 2013 Decommissioning Funding Status Report NRC-12-0020, Decommissioning Funding Status Report2012-03-29029 March 2012 Decommissioning Funding Status Report NRC-11-0052, Response to Request for Additional Information Regarding Decommissioning Funding Status Report2011-11-18018 November 2011 Response to Request for Additional Information Regarding Decommissioning Funding Status Report ML1020105052010-07-0808 July 2010 Independent Confirmatory Survey Project-Specific Plan for the Decommissioning of the Enrico Fermi Atomic Power Plant, Unit 1 ML1009700272010-03-31031 March 2010 Decommissioning Funding Status Report NRC-09-0043, Enrico Fermi, Unit 1 - License Termination Plan, Revision 12009-06-30030 June 2009 Enrico Fermi, Unit 1 - License Termination Plan, Revision 1 NRC-09-0019, Decommissioning Funding Status Report2009-03-31031 March 2009 Decommissioning Funding Status Report NRC-09-0020, Decommissioning Funding Status Report2009-03-25025 March 2009 Decommissioning Funding Status Report NRC-08-0061, Proposed License Amendment to Remove Statements Related to Nuclear Power Plant Staff Working Hours in Technical Specification2008-09-12012 September 2008 Proposed License Amendment to Remove Statements Related to Nuclear Power Plant Staff Working Hours in Technical Specification NRC-08-0026, Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report2008-03-31031 March 2008 Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report NRC-07-0016, Decommissioning Funding Status Report for Fermi 22007-03-29029 March 2007 Decommissioning Funding Status Report for Fermi 2 NRC-05-0022, Decommissioning Funding Status Report for Fermi 22005-03-28028 March 2005 Decommissioning Funding Status Report for Fermi 2 NRC-03-0033, Decommissioning Funding Status Report for Fermi 22003-03-28028 March 2003 Decommissioning Funding Status Report for Fermi 2 NRC-03-0031, Decommissioning Funding Status Report for Fermi 12003-03-26026 March 2003 Decommissioning Funding Status Report for Fermi 1 2024-03-31 Category:50 MONTHYEARNRC-24-0015, Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report2024-03-31031 March 2024
[Table view]Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report NRC-23-0021, ISFSI, Decommissioning Funding Plan Update2023-03-30030 March 2023 ISFSI, Decommissioning Funding Plan Update NRC-23-0015, Decommissioning Funding Status Report for Fermi 12023-03-30030 March 2023 Decommissioning Funding Status Report for Fermi 1 NRC-23-0016, Decommissioning Funding Status Report2023-03-30030 March 2023 Decommissioning Funding Status Report NRC-22-0011, Enrico Fermi Atomic Power Plant, Unit No. 1 - Decommissioning Funding Status Report2022-03-31031 March 2022 Enrico Fermi Atomic Power Plant, Unit No. 1 - Decommissioning Funding Status Report NRC-21-0018, Enrico Fermi Atomic Power Plant, Unit No. 1 - Decommissioning Funding Status Report2021-03-31031 March 2021 Enrico Fermi Atomic Power Plant, Unit No. 1 - Decommissioning Funding Status Report NRC-21-0019, Decommissioning Funding Status Report for Fermi 22021-03-31031 March 2021 Decommissioning Funding Status Report for Fermi 2 NRC-20-0018, Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report2020-03-31031 March 2020 Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report NRC-20-0020, ISFSI Decommissioning Funding Plan Update2020-03-30030 March 2020 ISFSI Decommissioning Funding Plan Update NRC-19-0022, Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report2019-03-29029 March 2019 Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report NRC-19-0023, Decommissioning Funding Status Report2019-03-28028 March 2019 Decommissioning Funding Status Report NRC-17-0023, ISFSI Decommissioning Funding Plan Update2017-03-30030 March 2017 ISFSI Decommissioning Funding Plan Update NRC-17-0022, Decommissioning Funding Status Report for Fermi 22017-03-30030 March 2017 Decommissioning Funding Status Report for Fermi 2 NRC-16-0025, Decommissioning Funding Status Report2016-03-29029 March 2016 Decommissioning Funding Status Report NRC-14-0050, ISFSI Decommissioning Funding Plan2014-07-0202 July 2014 ISFSI Decommissioning Funding Plan NRC-14-0019, Decommissioning Funding Status Report2014-03-31031 March 2014 Decommissioning Funding Status Report NRC-13-0015, Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report2013-03-28028 March 2013 Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report NRC-13-0016, Decommissioning Funding Status Report2013-03-28028 March 2013 Decommissioning Funding Status Report NRC-12-0020, Decommissioning Funding Status Report2012-03-29029 March 2012 Decommissioning Funding Status Report NRC-11-0052, Response to Request for Additional Information Regarding Decommissioning Funding Status Report2011-11-18018 November 2011 Response to Request for Additional Information Regarding Decommissioning Funding Status Report ML1020105052010-07-0808 July 2010 Independent Confirmatory Survey Project-Specific Plan for the Decommissioning of the Enrico Fermi Atomic Power Plant, Unit 1 ML1009700272010-03-31031 March 2010 Decommissioning Funding Status Report NRC-09-0043, Enrico Fermi, Unit 1 - License Termination Plan, Revision 12009-06-30030 June 2009 Enrico Fermi, Unit 1 - License Termination Plan, Revision 1 NRC-09-0019, Decommissioning Funding Status Report2009-03-31031 March 2009 Decommissioning Funding Status Report NRC-09-0020, Decommissioning Funding Status Report2009-03-25025 March 2009 Decommissioning Funding Status Report NRC-08-0026, Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report2008-03-31031 March 2008 Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report NRC-07-0016, Decommissioning Funding Status Report for Fermi 22007-03-29029 March 2007 Decommissioning Funding Status Report for Fermi 2 NRC-05-0022, Decommissioning Funding Status Report for Fermi 22005-03-28028 March 2005 Decommissioning Funding Status Report for Fermi 2 NRC-03-0033, Decommissioning Funding Status Report for Fermi 22003-03-28028 March 2003 Decommissioning Funding Status Report for Fermi 2 NRC-03-0031, Decommissioning Funding Status Report for Fermi 12003-03-26026 March 2003 Decommissioning Funding Status Report for Fermi 1 2024-03-31 Category:70 MONTHYEARNRC-24-0015, Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report2024-03-31031 March 2024
[Table view]Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report NRC-23-0021, ISFSI, Decommissioning Funding Plan Update2023-03-30030 March 2023 ISFSI, Decommissioning Funding Plan Update NRC-23-0015, Decommissioning Funding Status Report for Fermi 12023-03-30030 March 2023 Decommissioning Funding Status Report for Fermi 1 NRC-23-0016, Decommissioning Funding Status Report2023-03-30030 March 2023 Decommissioning Funding Status Report NRC-22-0011, Enrico Fermi Atomic Power Plant, Unit No. 1 - Decommissioning Funding Status Report2022-03-31031 March 2022 Enrico Fermi Atomic Power Plant, Unit No. 1 - Decommissioning Funding Status Report NRC-21-0018, Enrico Fermi Atomic Power Plant, Unit No. 1 - Decommissioning Funding Status Report2021-03-31031 March 2021 Enrico Fermi Atomic Power Plant, Unit No. 1 - Decommissioning Funding Status Report NRC-21-0019, Decommissioning Funding Status Report for Fermi 22021-03-31031 March 2021 Decommissioning Funding Status Report for Fermi 2 NRC-20-0018, Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report2020-03-31031 March 2020 Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report NRC-20-0020, ISFSI Decommissioning Funding Plan Update2020-03-30030 March 2020 ISFSI Decommissioning Funding Plan Update NRC-19-0022, Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report2019-03-29029 March 2019 Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report NRC-19-0023, Decommissioning Funding Status Report2019-03-28028 March 2019 Decommissioning Funding Status Report NRC-17-0023, ISFSI Decommissioning Funding Plan Update2017-03-30030 March 2017 ISFSI Decommissioning Funding Plan Update NRC-17-0022, Decommissioning Funding Status Report for Fermi 22017-03-30030 March 2017 Decommissioning Funding Status Report for Fermi 2 NRC-16-0025, Decommissioning Funding Status Report2016-03-29029 March 2016 Decommissioning Funding Status Report NRC-14-0050, ISFSI Decommissioning Funding Plan2014-07-0202 July 2014 ISFSI Decommissioning Funding Plan NRC-14-0019, Decommissioning Funding Status Report2014-03-31031 March 2014 Decommissioning Funding Status Report NRC-13-0015, Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report2013-03-28028 March 2013 Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report NRC-13-0016, Decommissioning Funding Status Report2013-03-28028 March 2013 Decommissioning Funding Status Report NRC-12-0020, Decommissioning Funding Status Report2012-03-29029 March 2012 Decommissioning Funding Status Report NRC-11-0052, Response to Request for Additional Information Regarding Decommissioning Funding Status Report2011-11-18018 November 2011 Response to Request for Additional Information Regarding Decommissioning Funding Status Report ML1020105052010-07-0808 July 2010 Independent Confirmatory Survey Project-Specific Plan for the Decommissioning of the Enrico Fermi Atomic Power Plant, Unit 1 ML1009700272010-03-31031 March 2010 Decommissioning Funding Status Report NRC-09-0043, Enrico Fermi, Unit 1 - License Termination Plan, Revision 12009-06-30030 June 2009 Enrico Fermi, Unit 1 - License Termination Plan, Revision 1 NRC-09-0019, Decommissioning Funding Status Report2009-03-31031 March 2009 Decommissioning Funding Status Report NRC-09-0020, Decommissioning Funding Status Report2009-03-25025 March 2009 Decommissioning Funding Status Report NRC-08-0061, Proposed License Amendment to Remove Statements Related to Nuclear Power Plant Staff Working Hours in Technical Specification2008-09-12012 September 2008 Proposed License Amendment to Remove Statements Related to Nuclear Power Plant Staff Working Hours in Technical Specification NRC-08-0026, Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report2008-03-31031 March 2008 Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report NRC-07-0016, Decommissioning Funding Status Report for Fermi 22007-03-29029 March 2007 Decommissioning Funding Status Report for Fermi 2 NRC-05-0022, Decommissioning Funding Status Report for Fermi 22005-03-28028 March 2005 Decommissioning Funding Status Report for Fermi 2 NRC-03-0033, Decommissioning Funding Status Report for Fermi 22003-03-28028 March 2003 Decommissioning Funding Status Report for Fermi 2 NRC-03-0031, Decommissioning Funding Status Report for Fermi 12003-03-26026 March 2003 Decommissioning Funding Status Report for Fermi 1 2024-03-31 Category:Letter type:NRC MONTHYEARNRC-24-0064, Supplement to License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance2024-10-31031 October 2024
[Table view]Supplement to License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance NRC-24-0058, Status of License Renewal Commitments2024-10-0303 October 2024 Status of License Renewal Commitments NRC-24-0057, Update to NRC 24-0041: Technical Specification (TS) 5.6.7 – Post Accident Monitoring Report2024-09-0303 September 2024 Update to NRC 24-0041: Technical Specification (TS) 5.6.7 – Post Accident Monitoring Report NRC-24-0053, Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30, 20242024-08-30030 August 2024 Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30, 2024 NRC-24-0050, Inservice Inspection-Nondestructive Examination (ISI-NDE) Program for the Fourth 10-Year Inspection Interval2024-08-12012 August 2024 Inservice Inspection-Nondestructive Examination (ISI-NDE) Program for the Fourth 10-Year Inspection Interval NRC-24-0048, Submittal of Inservice Inspection Summary Report2024-08-0606 August 2024 Submittal of Inservice Inspection Summary Report NRC-24-0046, Fenni 2 Power Plant - Approval of the National Pollutant Discharge Elimination System Permit Application for Reissuance2024-07-25025 July 2024 Fenni 2 Power Plant - Approval of the National Pollutant Discharge Elimination System Permit Application for Reissuance NRC-24-0020, Submittal of Revision 51 to the Fermi 2 Radiological Emergency Response Preparedness Plan2024-07-24024 July 2024 Submittal of Revision 51 to the Fermi 2 Radiological Emergency Response Preparedness Plan NRC-24-0044, Enrico Fermi 1 License Expiration - 10 CFR 50.51 (Continuation of License)2024-07-10010 July 2024 Enrico Fermi 1 License Expiration - 10 CFR 50.51 (Continuation of License) NRC-24-0041, Technical Specification (TS) 5.6.7 - Post Accident Monitoring Report2024-06-21021 June 2024 Technical Specification (TS) 5.6.7 - Post Accident Monitoring Report NRC-24-0042, Regulat01y Issues Summaty (RIS) 24-01 Preparation and Scheduling of Operator Licensing Examinations to Submit Fonn 536, Operator Licensing Examination Data2024-06-18018 June 2024 Regulat01y Issues Summaty (RIS) 24-01 Preparation and Scheduling of Operator Licensing Examinations to Submit Fonn 536, Operator Licensing Examination Data NRC-24-0040, Verification of No Significant Hazards Considerations for License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance Supplement Provided in NRC-24-00332024-06-0606 June 2024 Verification of No Significant Hazards Considerations for License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance Supplement Provided in NRC-24-0033 NRC-24-0033, DTE Electric Company - Final Response to Request for Additional Information for License Amendment Request Regarding Risk Informed Approach to Performance ECCS Strainer Performance2024-05-30030 May 2024 DTE Electric Company - Final Response to Request for Additional Information for License Amendment Request Regarding Risk Informed Approach to Performance ECCS Strainer Performance NRC-24-0017, 2023 Annual Radioactive Effluent Release Report and 2023 Radiological Environmental Operating Report2024-04-29029 April 2024 2023 Annual Radioactive Effluent Release Report and 2023 Radiological Environmental Operating Report NRC-24-0032, Transmittal of the Core Operating Limits Report for Cycle 232024-04-25025 April 2024 Transmittal of the Core Operating Limits Report for Cycle 23 NRC-24-0027, Partial Response to Request for Additional Information for License Amendment Request Regarding Risk Informed Approach to Performance ECCS Strainer Performance2024-04-24024 April 2024 Partial Response to Request for Additional Information for License Amendment Request Regarding Risk Informed Approach to Performance ECCS Strainer Performance NRC-24-0031, Retake Exam Outline Submittal Letter2024-04-22022 April 2024 Retake Exam Outline Submittal Letter NRC-24-0018, 2023 Annual Non-Radiological Environmental Operating Report2024-04-0909 April 2024 2023 Annual Non-Radiological Environmental Operating Report NRC-24-0015, Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report2024-03-31031 March 2024 Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report NRC-24-0001, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Rev. 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, TSTF-439, Rev. 2, Eliminate Second Completion2024-03-21021 March 2024 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Rev. 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, TSTF-439, Rev. 2, Eliminate Second Completion NRC-24-0019, Submittal of 2023 Safety Relief Valve Challenge Report, Main Steam Bypass Lines Report, and ECCS Cooling Performance Evaluation Model Changes or Errors Report2024-03-14014 March 2024 Submittal of 2023 Safety Relief Valve Challenge Report, Main Steam Bypass Lines Report, and ECCS Cooling Performance Evaluation Model Changes or Errors Report NRC-24-0023, NRC-24-0023, Post Exam Package Submittal Letter to NRC2024-03-0707 March 2024 NRC-24-0023, Post Exam Package Submittal Letter to NRC NRC-24-0008, Levels and Sources of Property Insurance Coverage2024-02-15015 February 2024 Levels and Sources of Property Insurance Coverage NRC-24-0009, Request for NRC to Suspend Regulatory Audit of License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance for Fermi Unit 22024-02-0606 February 2024 Request for NRC to Suspend Regulatory Audit of License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance for Fermi Unit 2 NRC-24-0002, Clarification for Request for Additional Information Responses for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.122024-01-12012 January 2024 Clarification for Request for Additional Information Responses for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 NRC-24-0007, Report of Changes to Quality Assurance Program for Radioactive Material Packages2024-01-12012 January 2024 Report of Changes to Quality Assurance Program for Radioactive Material Packages NRC-23-0079, Transmittal of Revision 1 of the Core Operating Limits Report for Cycle 222023-12-14014 December 2023 Transmittal of Revision 1 of the Core Operating Limits Report for Cycle 22 NRC-23-0077, Submittal of Revision 50 to the Fermi 2 Radiological Emergency Response Preparedness Plan2023-12-0404 December 2023 Submittal of Revision 50 to the Fermi 2 Radiological Emergency Response Preparedness Plan NRC-23-0075, Request for Exemption from Enhanced Weapons, Firearms Background Checks and Security Event Notification Implementation2023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks and Security Event Notification Implementation NRC-23-0073, Guarantee of Payment of Deferred Premiums2023-11-29029 November 2023 Guarantee of Payment of Deferred Premiums NRC-23-0071, Response to Request for Additional Information (RAI) for Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating2023-10-13013 October 2023 Response to Request for Additional Information (RAI) for Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating NRC-23-0062, Response to Request for Additional Information for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.122023-10-12012 October 2023 Response to Request for Additional Information for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 NRC-23-0068, Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating2023-09-28028 September 2023 Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating NRC-23-0064, Additional Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-09-11011 September 2023 Additional Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0057, Independent Spent Fuel Storage Installation Cask Registration2023-08-31031 August 2023 Independent Spent Fuel Storage Installation Cask Registration NRC-23-0054, Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30 20232023-08-31031 August 2023 Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30 2023 NRC-23-0056, Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval2023-08-31031 August 2023 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval NRC-23-0061, Clarification for NRC-23-0059, Response to Request for Additional Information for Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water..2023-08-30030 August 2023 Clarification for NRC-23-0059, Response to Request for Additional Information for Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water.. NRC-23-0059, Response to Request for Additional Information Exigent License Amendment Request for Technical Specification 3.7.2,Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-08-25025 August 2023 Response to Request for Additional Information Exigent License Amendment Request for Technical Specification 3.7.2,Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0060, Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-08-25025 August 2023 Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0053, Independent Spent Fuel Storage Installation Cask Registration2023-08-23023 August 2023 Independent Spent Fuel Storage Installation Cask Registration NRC-23-0050, Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-08-10010 August 2023 Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0048, Independent Spent Fuel Storage Installation Cask Registration2023-08-0101 August 2023 Independent Spent Fuel Storage Installation Cask Registration NRC-23-0049, Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-07-24024 July 2023 Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0043, Independent Spent Fuel Storage Installation, Cask Registration2023-06-27027 June 2023 Independent Spent Fuel Storage Installation, Cask Registration NRC-23-0020, License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance2023-06-13013 June 2023 License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance NRC-23-0039, Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-06-0606 June 2023 Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0030, Inservice Inspection-Nondestructive Examination (ISI-NDE) Program for the Fourth 10-Year Inspection Interval2023-06-0505 June 2023 Inservice Inspection-Nondestructive Examination (ISI-NDE) Program for the Fourth 10-Year Inspection Interval NRC-23-0029, Snubber Program for the Fourth 10-Year Testing Interval2023-06-0505 June 2023 Snubber Program for the Fourth 10-Year Testing Interval NRC-23-0037, 56542-EN 56542 - Fermi2023-05-26026 May 2023 56542-EN 56542 - Fermi 2024-09-03 |
Text
Fermi 2 6400 North Dixie Hwy, Newport, MI 48166 Detroit Edisoi 7F 10CFR50.75(f)(1)
March 28, 2003 NRC-03-0033 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington D C 20555-0001
Reference:
Fermi 2 NRC Docket No. 50-341 NRC License No. NPF-43
Subject:
Decommissioning Funding Status Report for Fermi 2 This letter provides the report required by 10 CFR 50.75(f)(1) on the status of Detroit Edison's decommissioning fund for Fermi 2.
Fermi 2 is an operating boiling water reactor with a licensed power of 3430MWt. Its operating license expires in 2025.
The requested annual decommissioning fund information for Fermi 2, reported in 2002 dollars, is provided as an enclosure to this letter. An external sinking fund is being used to accumulate monies for the decommissioning of Fermi 2.
Should you have any questions or require additional information, please contact Mr. Norman K. Peterson of my staff at (734) 586-4258.
Sincerely, Und
'7 Enclosure cc: J. F. Stang, Jr.
NRC Resident Office NRC Region HI A DTE Energy Company G~o I
Enclosure to NRC-03-0033 Page 1 ENCLOSURE TO NRC-03-0033 FERMI 2 NRC DECOMMISSIONING FUNDING STATUS REPORT Fermi 2 NRC Docket No. 50-341 NRC License No. NPF-43
Enclosure to NRC-03-0033 Page 2 NRC Decommissioning Funding Status Report Fermi 2 (Millions of Dollars)
- 1. The decommissioning cost estimate, pursuant $679,185,000 to IOCFR50.75 (b) and (c)':
- 2. The amount accumulated at the end of calendar year preceding $371,836,360 the date of the report for items included in 10CFR50.75 (b)and (c):
- 3. The schedule of the annual amounts remaining to be collected for items in 10 CFR 50.75 (b) and (c).
amount remaining (1-2): $307,348,640
- years to collect (2003-2025): 22
- 4. The assumptions used regarding rates of escalation in decommissioning cost, rates of earnings on decommissioning fund, and rates of other factors used in funding projections:
All decommissioning costs are assumed to increase at 6.0% annually; decommissioning funds are assumed to earn at 7.0% annually after-tax.
- 5. Any contracts upon which the licensee is relying pursuant to 10 CFR 50.75 (e) (1)(v): None
- 6. Any modifications to the current method of providing financial assurance occurring since the last submitted report: None
- 7. Any material changes to the trust agreement: None I The NRC formulas in section 10 CFR 50.75(c) include only those decommissioning costs incurred by licensees to remove a facility or site safely from service and reduce residual radioactivity to levels that permit: (1) release of the property for unrestricted use and termination of the license; or (2) release of the property under restricted conditions and termination of the license. The cost of dismantling or demolishing non-radiological systems and structures are not included in the NRC decommissioning cost estimates. The costs of managing and storing spent fuel on site until transfer to DOE are not included in the cost formulas.