Letter Sequence Other |
---|
|
|
MONTHYEARML1017206072010-06-21021 June 2010 Acceptance Review Email, License Amendment Request, Revise Technical Specification 6.8.3.1, Containment Post Tensioning System Surveillance Program, Consistent with Updated Edition of ASME Code, Section XI Project stage: Acceptance Review ML1102403852011-01-24024 January 2011 Request for Additional Information, License Amendment Request, Revise TS 6.8.3.I, Containment Post Tensioning System Surveillance Program, Consistent with Updated Edition of ASME Code Section XI Project stage: RAI NOC-AE-11002632, Revised Proposed Amendment to Technical Specification 6.8.3.I for Containment Post-Tensioning System Surveillance Program2011-03-0101 March 2011 Revised Proposed Amendment to Technical Specification 6.8.3.I for Containment Post-Tensioning System Surveillance Program Project stage: Other ML1107405092011-03-15015 March 2011 Individual Notice of Consideration of Issuance of Amendment, Revise Technical Specification 6.8.3.I, Containment Post Tensioning System Surveillance Program, Consistent with Updated Edition of ASME Code, Section XI Project stage: Other ML1107405012011-03-15015 March 2011 Letter, Individual Notice of Consideration of Issuance of Amendment, Revise Technical Specification 6.8.3.I, Containment Post Tensioning System Surveillance Program, Consistent with Updated Edition of ASME Code, Section XI Project stage: Other NRC-2011-0063, Individual Notice of Consideration of Issuance of Amendment, Revise Technical Specification 6.8.3.I, Containment Post Tensioning System Surveillance Program, Consistent with Updated Edition of ASME Code, Section Xi2011-03-15015 March 2011 Individual Notice of Consideration of Issuance of Amendment, Revise Technical Specification 6.8.3.I, Containment Post Tensioning System Surveillance Program, Consistent with Updated Edition of ASME Code, Section Xi Project stage: Approval NOC-AE-11002665, Proposed Amendment to Technical Specifications for Containment Post-Tensioning System Surveillance Program (Revision 2) (TAC ME3969/ME3970)2011-05-0202 May 2011 Proposed Amendment to Technical Specifications for Containment Post-Tensioning System Surveillance Program (Revision 2) (TAC ME3969/ME3970) Project stage: Other ML1113702772011-05-27027 May 2011 Issuance of Amendment Nos. 196 and 184, Revise Technical Specification 6.8.3.I, Containment Post Tensioning System Surveillance Program and Surveillance Requirement 4.6.1.6, Containment Prestressing System. Project stage: Approval 2011-03-01
[Table View] |
|
---|
Category:Letter type:NOC
MONTHYEARNOC-AE-240040, Change to South Texas Project Electric Generating Station (STPEGS) Emergency Plan2024-10-16016 October 2024 Change to South Texas Project Electric Generating Station (STPEGS) Emergency Plan NOC-AE-230039, Docket Nos. Stn 50-498, Stn 50-499 - Reply to a Notice of Violation, NRC Inspection Report 05000498/2023003 and 05000499/20230032023-12-12012 December 2023 Docket Nos. Stn 50-498, Stn 50-499 - Reply to a Notice of Violation, NRC Inspection Report 05000498/2023003 and 05000499/2023003 NOC-AE-230040, Update Foreign Ownership, Control, or Influence (FOCI)2023-12-0505 December 2023 Update Foreign Ownership, Control, or Influence (FOCI) NOC-AE-230039, Submittal of Update Foreign Ownership, Control or Influence (FOCI)2023-07-11011 July 2023 Submittal of Update Foreign Ownership, Control or Influence (FOCI) NOC-AE-220039, Physical Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program Revision 252023-02-0606 February 2023 Physical Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program Revision 25 NOC-AE-220038, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask2022-06-23023 June 2022 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask NOC-AE-210038, Submittal of Operations Quality Assurance Plan Changes QA-089, QA-091, and Revision 252022-01-0404 January 2022 Submittal of Operations Quality Assurance Plan Changes QA-089, QA-091, and Revision 25 NOC-AE-21003858, 10 CFR 50.46 Thirty-Day Report of Significant ECCS Model Changes2021-12-0606 December 2021 10 CFR 50.46 Thirty-Day Report of Significant ECCS Model Changes NOC-AE-21003853, Revised Response to End of Enforcement Discretion and Request for Approval of Alternate Disposal Procedures for Very Low-Level Radioactive Material2021-12-0303 December 2021 Revised Response to End of Enforcement Discretion and Request for Approval of Alternate Disposal Procedures for Very Low-Level Radioactive Material NOC-AE-21003848, Unit 1 Cycle 24 Core Operating Limits Report2021-11-18018 November 2021 Unit 1 Cycle 24 Core Operating Limits Report NOC-AE-21003846, Response to End of Enforcement Discretion and Request for Approval of Alternate Disposal Procedures for Very Low-Level Radioactive Material2021-11-0404 November 2021 Response to End of Enforcement Discretion and Request for Approval of Alternate Disposal Procedures for Very Low-Level Radioactive Material NOC-AE-21003842, 10 CFR 50.59 Summary Report2021-09-23023 September 2021 10 CFR 50.59 Summary Report NOC-AE-21003841, Request for Relief from ASME Section Xl Code Requirements for Weld Examinations (Relief Request RR-ENG-3-25)2021-09-23023 September 2021 Request for Relief from ASME Section Xl Code Requirements for Weld Examinations (Relief Request RR-ENG-3-25) NOC-AE-21003832, Supplement to License Amendment Request to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections2021-09-0909 September 2021 Supplement to License Amendment Request to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections NOC-AE-21003812, Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections2021-08-10010 August 2021 Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections NOC-AE-21003825, Update of Foreign Ownership, Control, or Influence Information (FOCI)2021-08-0505 August 2021 Update of Foreign Ownership, Control, or Influence Information (FOCI) NOC-AE-21003824, Update Foreign Ownership, Control, or Influence (FOCI)2021-07-29029 July 2021 Update Foreign Ownership, Control, or Influence (FOCI) NOC-AE-21003823, Update Foreign Ownership Control or Influence (FOCI)2021-07-28028 July 2021 Update Foreign Ownership Control or Influence (FOCI) NOC-AE-21003820, Nuclear Insurance Protection2021-07-20020 July 2021 Nuclear Insurance Protection NOC-AE-21003819, Inservice Inspection Summary Report - 2RE212021-07-15015 July 2021 Inservice Inspection Summary Report - 2RE21 NOC-AE-21003816, Commitment Change Summary Report2021-06-30030 June 2021 Commitment Change Summary Report NOC-AE-21003814, Technical Specification Bases Control Program2021-06-24024 June 2021 Technical Specification Bases Control Program NOC-AE-21003810, Update Foreign Ownership, Control, or Influence (FOCI)- CPS Energy2021-06-17017 June 2021 Update Foreign Ownership, Control, or Influence (FOCI)- CPS Energy NOC-AE-21003811, Update Foreign Ownership, Control, or Influence (FOCI)- Nrg Energy2021-06-17017 June 2021 Update Foreign Ownership, Control, or Influence (FOCI)- Nrg Energy NOC-AE-21003806, Inservice Inspection Program Plan and Inservice Testing Program Snubber Inservice Test Plan for the Fourth Ten-Year Interval2021-05-20020 May 2021 Inservice Inspection Program Plan and Inservice Testing Program Snubber Inservice Test Plan for the Fourth Ten-Year Interval NOC-AE-21003801, Annual Dose Report for 20202021-04-26026 April 2021 Annual Dose Report for 2020 NOC-AE-21003802, 2020 South Texas Project Electric Generating Station Annual Environmental Operating Report2021-04-26026 April 2021 2020 South Texas Project Electric Generating Station Annual Environmental Operating Report NOC-AE-21003804, Operator Licensing Examination Schedule2021-04-21021 April 2021 Operator Licensing Examination Schedule NOC-AE-21003800, Radioactive Effluent Release Report2021-04-19019 April 2021 Radioactive Effluent Release Report NOC-AE-21003799, Changes to South Texas Project Electric Generating Station (STPEGS) Emergency Plan2021-04-15015 April 2021 Changes to South Texas Project Electric Generating Station (STPEGS) Emergency Plan NOC-AE-21003795, Cycle 22 Core Operating Limits Report2021-04-15015 April 2021 Cycle 22 Core Operating Limits Report NOC-AE-21003796, Update Foreign Ownership, Control, or Influence (FOCI)2021-04-15015 April 2021 Update Foreign Ownership, Control, or Influence (FOCI) NOC-AE-21003790, Response to Apparent Violations in NRC Inspection Report 05000498/2020401 and 05000499/2020401: (EA-20-122) (Letter)2021-03-31031 March 2021 Response to Apparent Violations in NRC Inspection Report 05000498/2020401 and 05000499/2020401: (EA-20-122) (Letter) NOC-AE-21003791, Financial Assurance for Decommissioning - 2021 Update2021-03-31031 March 2021 Financial Assurance for Decommissioning - 2021 Update NOC-AE-210037, STP Fire Hazards Analysis Report, Amendment 26 (Redacted)2021-03-30030 March 2021 STP Fire Hazards Analysis Report, Amendment 26 (Redacted) NOC-AE-21003792, STP Fire Hazards Analysis Report, Amendment 26 (Redacted)2021-03-30030 March 2021 STP Fire Hazards Analysis Report, Amendment 26 (Redacted) NOC-AE-200037, License Amendment Request to Revise Technical Specification 3.6.3 to Append a Note and Remove the Index from Technical Specifications2021-03-11011 March 2021 License Amendment Request to Revise Technical Specification 3.6.3 to Append a Note and Remove the Index from Technical Specifications NOC-AE-21003784, Response to Request for Additional Information Regarding 1RE22 Inspection Summary Report for Steam Generator Tubing2021-03-0808 March 2021 Response to Request for Additional Information Regarding 1RE22 Inspection Summary Report for Steam Generator Tubing NOC-AE-21003786, Annual Fitness for Duty Performance Report for 20202021-03-0101 March 2021 Annual Fitness for Duty Performance Report for 2020 NOC-AE-21003785, Evidence of Financial Protection2021-02-23023 February 2021 Evidence of Financial Protection NOC-AE-21003781, Notice Regarding Withdrawal of Funds from Nuclear Decommissioning Trust Subaccounts2021-01-27027 January 2021 Notice Regarding Withdrawal of Funds from Nuclear Decommissioning Trust Subaccounts NOC-AE-21003780, Submittal of Update Foreign Ownership, Control, or Influence (FOCI)2021-01-0707 January 2021 Submittal of Update Foreign Ownership, Control, or Influence (FOCI) NOC-AE-20003778, Changes to South Texas Project Electric Generating Station Emergency Plan2020-12-17017 December 2020 Changes to South Texas Project Electric Generating Station Emergency Plan NOC-AE-20003777, STPNOC Concerns Regarding the Proposed Change to the Evaluated Force-on-Force Inspection Guidance During the COVID-19 Public Health Emergency2020-12-10010 December 2020 STPNOC Concerns Regarding the Proposed Change to the Evaluated Force-on-Force Inspection Guidance During the COVID-19 Public Health Emergency NOC-AE-20003766, Supplement to Change Implementation Date for License Amendment Request to Revise the STPEGS Emergency Plan2020-12-0202 December 2020 Supplement to Change Implementation Date for License Amendment Request to Revise the STPEGS Emergency Plan NOC-AE-20003767, Request for a One-Time Exemption from 10 CFR 73, Appendix 8, Section VI, Subsection C.3.(1)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic2020-11-16016 November 2020 Request for a One-Time Exemption from 10 CFR 73, Appendix 8, Section VI, Subsection C.3.(1)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic NOC-AE-20003765, Inservice Testing Program Description for the Fourth Ten-Year Interval2020-10-28028 October 2020 Inservice Testing Program Description for the Fourth Ten-Year Interval NOC-AE-20003764, 1 RE22 Inspection Summary Report for Steam Generator Tubing2020-10-0707 October 2020 1 RE22 Inspection Summary Report for Steam Generator Tubing NOC-AE-20003762, Supplement to License Amendment Request to Revise Technical Specifications to Adopt TSTF-374, Revision 0, Revision to TS 5.5.13 and Associated TS Bases for Diesel Fuel Oil Using the Consolidated Line Item Improvemen2020-09-22022 September 2020 Supplement to License Amendment Request to Revise Technical Specifications to Adopt TSTF-374, Revision 0, Revision to TS 5.5.13 and Associated TS Bases for Diesel Fuel Oil Using the Consolidated Line Item Improvemen NOC-AE-20003761, Supplement to Exemption Request from 10 CFR 50 Appendix E Due to COVID-19 Pandemic2020-09-10010 September 2020 Supplement to Exemption Request from 10 CFR 50 Appendix E Due to COVID-19 Pandemic 2024-10-16
[Table view] Category:License-Application for Facility Operating License (Amend/Renewal) DKT 50
MONTHYEARML24269A1762024-09-25025 September 2024 Tpdes Permit Renewal Application WQ0001 908000 ML23089A2042023-03-30030 March 2023 License Amendment Request to Revise Alternative Source Term Dose Calculation ML22221A2122022-08-0909 August 2022 Application to Revise Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements NOC-AE-21003832, Supplement to License Amendment Request to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections2021-09-0909 September 2021 Supplement to License Amendment Request to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections ML21252A7582021-09-0909 September 2021 Supplement to License Amendment Request to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections ML21222A2272021-08-10010 August 2021 Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections NOC-AE-21003812, Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections2021-08-10010 August 2021 Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections NOC-AE-200037, License Amendment Request to Revise Technical Specification 3.6.3 to Append a Note and Remove the Index from Technical Specifications2021-03-11011 March 2021 License Amendment Request to Revise Technical Specification 3.6.3 to Append a Note and Remove the Index from Technical Specifications ML20253A0462020-09-29029 September 2020 Issuance of Amendment Nos. 220 and 205 to Revise Technical Specifications to Adopt TSTF-490, Deletion of E-Bar Definition and Revision to RCS Specific Activity Tech Spec ML20266H8192020-09-22022 September 2020 Supplement to License Amendment Request to Revise Technical Specifications to Adopt TSTF-374, Revision 0, Revision to TS 5.5.13 and Associated TS Bases for Diesel Fuel Oil Using the Consolidated Line Item Improvemen NOC-AE-20003762, Supplement to License Amendment Request to Revise Technical Specifications to Adopt TSTF-374, Revision 0, Revision to TS 5.5.13 and Associated TS Bases for Diesel Fuel Oil Using the Consolidated Line Item Improvemen2020-09-22022 September 2020 Supplement to License Amendment Request to Revise Technical Specifications to Adopt TSTF-374, Revision 0, Revision to TS 5.5.13 and Associated TS Bases for Diesel Fuel Oil Using the Consolidated Line Item Improvemen ML20134K7582020-05-13013 May 2020 License Amendment Request Under Exigent Circumstances for One-Time Revision to Technical Specification 3.5.1 to Reduce Minimum Allowed Accumulator Pressures NOC-AE-20003734, License Amendment Request Under Exigent Circumstances for One-Time Revision to Technical Specification 3.5.1 to Reduce Minimum Allowed Accumulator Pressures2020-05-13013 May 2020 License Amendment Request Under Exigent Circumstances for One-Time Revision to Technical Specification 3.5.1 to Reduce Minimum Allowed Accumulator Pressures ML20090B7452020-03-30030 March 2020 License Amendment Request for Revise South Texas Project Electric Generating Station (STPEGS) Emergency Plan NOC-AE-20003712, License Amendment Request for Revise South Texas Project Electric Generating Station (STPEGS) Emergency Plan2020-03-30030 March 2020 License Amendment Request for Revise South Texas Project Electric Generating Station (STPEGS) Emergency Plan NOC-AE-19003677, License Amendment Request to Revise Technical Specifications to Adopt TSTF-490, Revision 0, Deletion of E Bar Definition and Revision to RCS Specific Activity Tech Spec.2019-09-26026 September 2019 License Amendment Request to Revise Technical Specifications to Adopt TSTF-490, Revision 0, Deletion of E Bar Definition and Revision to RCS Specific Activity Tech Spec. NOC-AE-18003604, License Amendment Request to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Using the Consolidated Line Item Improvement Process2019-05-0101 May 2019 License Amendment Request to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Using the Consolidated Line Item Improvement Process NOC-AE-18003583, License Amendment Request to Revise Technical Specifications to Adopt TSTF-522, Revise Ventilation System Surveillance Requirements to Operate for 10 Hours Per Month, Using the Consolidated Line Item ...2018-09-27027 September 2018 License Amendment Request to Revise Technical Specifications to Adopt TSTF-522, Revise Ventilation System Surveillance Requirements to Operate for 10 Hours Per Month, Using the Consolidated Line Item ... NOC-AE-17003529, License Amendment Request to Revise Technical Specification 3.8.1.1 (A.C. Sources, Operating)2018-03-27027 March 2018 License Amendment Request to Revise Technical Specification 3.8.1.1 (A.C. Sources, Operating) NOC-AE-17003510, License Amendment Request to Revise Technical Specifications for Administrative Changes and to Relocate Fxy Exclusion Zones to the Core Operating Limits Reports (Colrs)2017-09-18018 September 2017 License Amendment Request to Revise Technical Specifications for Administrative Changes and to Relocate Fxy Exclusion Zones to the Core Operating Limits Reports (Colrs) NOC-AE-16003406, License Amendment Request for Revision to Staffing and Staff Augmentation Times in the South Texas Project Electric Generating Station Emergency Plan2017-07-31031 July 2017 License Amendment Request for Revision to Staffing and Staff Augmentation Times in the South Texas Project Electric Generating Station Emergency Plan NOC-AE-17003459, Supplement to the License Renewal Application Re Aging Management Programs2017-04-19019 April 2017 Supplement to the License Renewal Application Re Aging Management Programs NOC-AE-16003403, Supplemental Information for the Review of the South Texas Project, Units 1 and 2, License Renewal - (TAC Nos. ME4936 and ME4937)2016-09-28028 September 2016 Supplemental Information for the Review of the South Texas Project, Units 1 and 2, License Renewal - (TAC Nos. ME4936 and ME4937) NOC-AE-16003385, 2016 Annual Update to the License Renewal Application2016-06-28028 June 2016 2016 Annual Update to the License Renewal Application NOC-AE-16003378, Additional Information for the Review of the License Renewal Application - Aluminum Bronze AMP (TAC Nos. ME4936 and ME4937)2016-05-31031 May 2016 Additional Information for the Review of the License Renewal Application - Aluminum Bronze AMP (TAC Nos. ME4936 and ME4937) NOC-AE-16003351, License Amendment Request to Revise Technical Specification 5.3.2 to Allow Operation with 56 Full-Length Control Rod Assemblies2016-04-0707 April 2016 License Amendment Request to Revise Technical Specification 5.3.2 to Allow Operation with 56 Full-Length Control Rod Assemblies NOC-AE-16003330, Transmittal of Information of Foreign Ownership, Control, or Influence (FOCI)2016-01-27027 January 2016 Transmittal of Information of Foreign Ownership, Control, or Influence (FOCI) NOC-AE-15003318, Response to Request for Additional Information and Supplement to Emergency License Amendment Request to Revise Technical Specification 5.3.2 to Allow Operation with 56 Full-Length Control Rod Assemblies for Cycle 202015-12-0909 December 2015 Response to Request for Additional Information and Supplement to Emergency License Amendment Request to Revise Technical Specification 5.3.2 to Allow Operation with 56 Full-Length Control Rod Assemblies for Cycle 20 NOC-AE-15003315, Emergency License Amendment Request to Revise Technical Specification 5.3.2 to Allow Operation with 56 Full-Length Control Rod Assemblies for Cycle 202015-12-0303 December 2015 Emergency License Amendment Request to Revise Technical Specification 5.3.2 to Allow Operation with 56 Full-Length Control Rod Assemblies for Cycle 20 NOC-AE-15003307, Supplement - Error Correction - License Amendment Request for Extension of Containment Leakage Rate Testing Program2015-11-11011 November 2015 Supplement - Error Correction - License Amendment Request for Extension of Containment Leakage Rate Testing Program NOC-AE-15003227, License Amendment Request for Extending the 10 Year ILRT to 15 Years2015-04-29029 April 2015 License Amendment Request for Extending the 10 Year ILRT to 15 Years NOC-AE-15003223, License Amendment Request: Proposed Revision to Updated Final Safety Analysis Report Table 15.6-172015-04-29029 April 2015 License Amendment Request: Proposed Revision to Updated Final Safety Analysis Report Table 15.6-17 NOC-AE-14003116, Application to Revise Technical Specifications to Adopt TSTF-510-A, Revision 2, Revision to Steam Generator Program Inspection Frequencies & Tube Sample Selection, Using the Consolidated Line Item Improvement Process2015-04-23023 April 2015 Application to Revise Technical Specifications to Adopt TSTF-510-A, Revision 2, Revision to Steam Generator Program Inspection Frequencies & Tube Sample Selection, Using the Consolidated Line Item Improvement Process NOC-AE-15003214, Response to Request for Additional Information Regarding License Amendment Request for Emergency Action Level Scheme Change2015-02-11011 February 2015 Response to Request for Additional Information Regarding License Amendment Request for Emergency Action Level Scheme Change ML14260A4372014-08-14014 August 2014 Project Units 1 & 2, License Amendment Request - Proposed Administrative Controls Technical Specification 6.9.1.6, Core Operating Limits Report ML14164A3002014-05-15015 May 2014 Project, Revision to Unit 1 and Unit 2 Emergency Action Levels, Evaluation of the Proposed Changes License Amendment Request (LAR) for Revision of EAL Scheme to NEI 99-01 Revision 6. Part 1 of 7 NOC-AE-14003087, Revision to Unit 1 and Unit 2 Emergency Action Levels, Evaluation of the Proposed Changes License Amendment Request (LAR) for Revision of EAL Scheme to NEI 99-01 Revision 6. Part 7 of 72014-05-15015 May 2014 Revision to Unit 1 and Unit 2 Emergency Action Levels, Evaluation of the Proposed Changes License Amendment Request (LAR) for Revision of EAL Scheme to NEI 99-01 Revision 6. Part 7 of 7 ML14164A3182014-05-15015 May 2014 Project, Revision to Unit 1 and Unit 2 Emergency Action Levels, Evaluation of the Proposed Changes License Amendment Request (LAR) for Revision of EAL Scheme to NEI 99-01 Revision 6. Part 6 of 7 ML14164A3032014-05-15015 May 2014 Project, Revision to Unit 1 and Unit 2 Emergency Action Levels, Evaluation of the Proposed Changes License Amendment Request (LAR) for Revision of EAL Scheme to NEI 99-01 Revision 6. Part 2 of 7 ML14164A3082014-05-15015 May 2014 Project, Revision to Unit 1 and Unit 2 Emergency Action Levels, Evaluation of the Proposed Changes License Amendment Request (LAR) for Revision of EAL Scheme to NEI 99-01 Revision 6. Part 5 of 7 ML14164A3112014-05-15015 May 2014 Project, Revision to Unit 1 and Unit 2 Emergency Action Levels, Evaluation of the Proposed Changes License Amendment Request (LAR) for Revision of EAL Scheme to NEI 99-01 Revision 6. Part 3 of 7 ML14164A3142014-05-15015 May 2014 Project, Revision to Unit 1 and Unit 2 Emergency Action Levels, Evaluation of the Proposed Changes License Amendment Request (LAR) for Revision of EAL Scheme to NEI 99-01 Revision 6. Part 4 of 7 NOC-AE-13003031, License Amendment Request, Proposed Revision to Technical Specification 3.3. 1, Functional Unit 20, Reactor Trip Breakers.2014-01-0606 January 2014 License Amendment Request, Proposed Revision to Technical Specification 3.3. 1, Functional Unit 20, Reactor Trip Breakers. ML13323A1852013-11-13013 November 2013 Enclosure 3 - License Amendment Request for STP Piloted Risk-Informed Approach to Closure for GSI-191 NOC-AE-13002962, License Amendment Request for Approval of a Revision to the South Texas Project Fire Protection Program Related to the Alternative Shutdown Capability2013-07-23023 July 2013 License Amendment Request for Approval of a Revision to the South Texas Project Fire Protection Program Related to the Alternative Shutdown Capability ML13175A2112013-06-19019 June 2013 Project, Units 1 and 2, Revised STP Pilot Submittal and Requests for Exemptions and License Amendment for a Risk-Informed Approach to Resolving Generic Safety Issue (GSI)-191 NOC-AE-12002915, Annual Update to the South Texas Project License Renewal Application2012-10-29029 October 2012 Annual Update to the South Texas Project License Renewal Application NOC-AE-12002877, Proposed Revision to Technical Specification 3.3.3.6, Accident Monitoring Instrumentation.2012-08-0101 August 2012 Proposed Revision to Technical Specification 3.3.3.6, Accident Monitoring Instrumentation. ML11335A1402011-11-30030 November 2011 Annual Update to the South Texas Project License Renewal Application (TAC Nos. ME4936 and ME4937) NOC-AE-11002643, License Amendment Request for Approval of a Revision to the South Texas Project Fire Protection Program Related to the Alternative Shutdown Capability2011-06-0202 June 2011 License Amendment Request for Approval of a Revision to the South Texas Project Fire Protection Program Related to the Alternative Shutdown Capability 2024-09-25
[Table view] |
Text
Nuclear Operating Company South Texas ProjectElectric Generatin$ Station PO Box 289 Wadsworth, Texas 77483 -
May 2, 2011 NOC-AE-1 1002665 File No.: G25 10 CFR 50.90 U. S. Nuclear Regulatory Commission Attention: Document Control Desk One White Flint North 11555 Rockville Pike Rockville, MD 20852 South Texas Project Units 1 and 2 Docket Nos. STN 50-498, STN 50-499 Proposed Amendment to Technical Specifications for Containment Post-Tensioning System Surveillance Program (Revision 2) (TAC ME3969/ME3970)
References:
- 1) G. T. Powell to NRC Document Control Desk, "Proposed Amendment to Technical Specification 6.8.3.1 for Containment Post-Tensioning System Surveillance Program," dated May 18, 2010 (NOC-AE-10002541)
(ML101450414)
- 2) G. T. Powell to NRC Document Control Desk, "Revised Proposed Amendment to Technical Specification 6.8.3.1 for Containment Post-Tensioning System Surveillance Program," dated March 1, 2011 (NOC-AE-1 1002632) (ML110690223)
Pursuant to 10 CFR 50.90, STP Nuclear Operating Company (STPNOC) requests Nuclear Regulatory Commission (NRC) approval of an amendment to Unit 1 Operating License NPF-76 and Unit 2 Operating License NPF-80. The proposed change revises Technical Specification 6.8.3.1, "Containment Post-Tensioning System Surveillance Program." This amendment request was previously submitted in the referenced correspondence. This revised request addresses NRC reviewer comments. Text changes are indicated by change bars in the margin. A supporting change to Surveillance Requirement 4.6.1.6 (page 3/4 6-9) is included.
This proposed amendment provides changes that are consistent with the Revision 3.1 of NUREG-1431, "Standard Technical Specifications for Westinghouse Plants." A safety evaluation of the proposed change and the proposed revised pages of the Technical Specifications are attached.
STPNOC has reviewed the attached proposed amendment pursuant to 10CFR50.92 and determined that it does not involve a significant hazards consideration. In addition, STPNOC has determined that the proposed amendment satisfies the criteria of 10CFR51.22(c)(9) for categorical exclusion from the requirement for an environmental assessment.
NýV~
STI: 32854496
NOC-AE-1 1002665 Page 2 of 3 The NRC is requested to approve the proposed amendment by June 30, 2011. This date is flexible. STPNOC will implement the amendment within 30 days after NRC approval. The STPNOC Plant Operations Review Committee has reviewed and concurred with the proposed change to the Technical Specifications.
In accordance with 10 CFR 50.91(b), STPNOC is notifying the State of Texas of this request for license amendment by providing a copy of this letter and its attachment.
There are no commitments in this letter.
If there are any questions, please contact either Philip L. Walker at 361-972-8392 or me at 361-972-7566.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on 2, 2ol Date G. T. Powell Vice President, Technical Support & Oversight PLW
Attachment:
Proposed Amendment to Technical Specification 6.8.3.1 for Containment Post-Tensioning System Surveillance Program (Revision 2) - Evaluation of the Proposed Change
NOC-AE-1 1002665 Page 3 of 3 cc: (paper copy) (electronic copy)
Regional Administrator, Region IV John Ragan U.S. Nuclear Regulatory Commission Catherine Callaway 612 East Lamar Blvd., Suite 400 Jim von Suskil Arlington, TX 76011-8064 NRG South Texas LP Balwant K. Singal A. H. Gutterman, Esquire Senior Project Manager Morgan, Lewis & Bockius LLP U.S. Nuclear Regulatory Commission One White Flint North (MS 8B1) 11555 Rockville Pike Balwant K. Singal Rockville, MD 20852 U. S. Nuclear Regulatory Commission Senior Resident Inspector Richard Pena U.S. Nuclear Regulatory Commission E. Alarcon P.O. Box 289, Mail Code: MN1 16 Kevin Polio Wadsworth, TX 77483 City Public Service C. M. Canady C. Mele City of Austin City of Austin Electric Utility Department 721 Barton Springs Road Peter Nemeth Austin, TX 787804 Crain Caton & James, P.C.
Richard A. Ratliff Texas Department of State Health Services Alice Rogers Texas Department of State Health Services
ATTACHMENT SOUTH TEXAS PROJECT UNITS I AND 2 Evaluation of the Proposed Change
Subject:
Proposed Amendment to Technical Specification 6.8.3.1 for Containment Post-Tensioning System Surveillance Program (Revision 2) 1.0
SUMMARY
DESCRIPTION
2.0 PROPOSED CHANGE
3.0 BACKGROUND
4.0 TECHNICAL EVALUATION
5.0 REGULATORY EVALUATION
5.1 No Significant Hazards Consideration 5.2 Applicable Regulatory Requirements 5.3 Analysis
6.0 ENVIRONMENTAL CONSIDERATION
7.0 IMPLEMENTATION Enclosure 1 - Updated Technical Specification Pages Enclosure 2 - Proposed Technical Specification Pages
Attachment NOC-AE-1 1002665 Page 1 of 4 SOUTH TEXAS PROJECT UNITS I AND 2 PROPOSED AMENDMENT TO TECHNICAL SPECIFICATION 6.8.3.L FOR CONTAINMENT POST-TENSIONING SYSTEM SURVEILLANCE PROGRAM (REVISION 2) 1.0
SUMMARY
DESCRIPTION South Texas Project (STP) Technical Specification Section 6.8.3.1 states that the Containment Post-Tensioning System Surveillance Program shall be in accordance with ASME Code Section X1, Subsection IWL, 1992 Edition with 1992 Addenda, as supplemented by 10 CFR 50.55a(b)(2)(viii). This change removes the specific year of the applicable Code edition consistent with Revision 3.1 of NUREG-1431, "Standard Technical Specifications for Westinghouse Plants." This will allow for future updates to the surveillance program when the applicable code edition changes without requiring additional Technical Specification changes. Additional changes have been made for consistency with the current version of NUREG-1431, and to assure that the surveillance intervals are consistent with Code requirements. These changes have no impact on implementation of the Containment Post-Tensioning System Surveillance Program.
2.0 PROPOSED CHANGE
STP Technical Specification 6.8.3.1 currently states the following:
Containment Post-Tensioning System Surveillance Program This program provides controls for monitoring any tendon degradation in pre-stressed concrete containments, including effectiveness of its corrosion protection medium, to ensure containment structural integrity. The program shall include baseline measures prior to initial operations. The Containment Post-Tensioning System Surveillance Program shall be in accordance with ASME Code Section X1, Subsection IWL, 1992 Edition with 1992 Addenda, as supplemented by 10CFR50.55a(b)(2)(viii).
Changes proposed by this amendment will result in the following (change bar shows additional change to be made under this revision):
Containment Post-Tensioning System Surveillance Program This program provides controls for monitoring any tendon degradation in pre-stressed concrete containments, including effectiveness of its corrosion protection medium, to ensure containment structural integrity. The program shall include baseline measurements prior to initial operations. The Containment Post-Tensioning System Surveillance Program, inspection frequencies, and acceptance criteria shall be in accordance with ASME Code Section X1, Subsection IWL, of the ASME Boiler and Pressure Vessel Code and applicable addenda as required by 1992 Edition with 1992 Addenda, mentd
. .upp . ,by Fr-,,"50.55a(b)(2)("imi+, 10 CFR 50.55a, except where an alternative, exemption, or relief has been authorized by the NRC.
The provisions of SR 4.0.3 are applicable to the Containment Post-Tensioning System Surveillance Program inspection frequencies with the exception of the surveillance interval extension allowed per Surveillance Requirement 4.0.2.
Attachment NOC-AE-1 1002665 Page 2 of 4 In addition, the following addition is proposed for surveillance requirement 4.6.1.6:
The provisions of SR 4.0.2 do not apply to extending the interval for this surveillance.
3.0 TECHNICAL EVALUATION
There will be no change in the design basis of the South Texas Project as a result of this amendment. There will be no change in the level of compliance with the General Design Criteria. There will be no change in compliance with the requirements of the applicable ASME code edition because that is established by the requirements of 10 CFR 50.55a.
Consequently, revising the description of the Containment Post-Tensioning System Surveillance Program for consistency with the Standard Technical Specifications does not affect safe operation of the South Texas Project.
4.0 REGULATORY EVALUATION
4.1 Applicable Regulatory Requirements/Criteria 10 CFR 50.55a requires that STP containment structural integrity be determined in accordance with the requirements of ASME Code Section Xl, Subsection IWL, "Requirements for Class CC Concrete Components of Light Water Cooled Power Plants," 2004 Edition as modified and supplemented by specified requirements and limitations. There is no change in applicable code requirements as a consequence of this amendment.
Inspection requirements for containment structural integrity applied by 10 CFR 50.55a do not have provisions for extending the inspection interval consistent with the provisions of Surveillance Requirement 4.0.2. Specifically removing Surveillance Requirement 4.0.2 as a provision for extending the inspection interval is for consistency between the Technical Specifications and code requirements.
4.1.1 General Design Criteria General Design Criterion 16, "Containment Design" Reactor containment and associated systems shall be provided to establish an essentially leak-tight barrier against the uncontrolled release of radioactivity to the environment and to assure that the containment design conditions important to safety are not exceeded for as long as postulated accident conditions require.
This change does not affect the function of reactor containment and associated functions.
4.1.2 Regulatory Compliance Future changes to the Containment Post-Tensioning System Surveillance Program that depart from code requirements will continue to require prior NRC approval, pursuant to the provisions of 10CFR50.55a. Therefore, adequate regulatory oversight will be maintained following implementation of this change.
Attachment NOC-AE-1 1002665 Page 3 of 4 4.2 Significant Hazards Consideration Excluding the extension allowed for a specified surveillance interval per Surveillance Requirement 4.0.2 from implementation of the Containment Post-Tensioning System Surveillance Program has no impact on the Significant Hazards Consideration.
STPNOC has evaluated whether a significant hazards consideration is involved with the proposed amendment by focusing on the three standards set forth in 10CFR50.92, "Issuance of amendment," as discussed below.
- 1) Does the proposed change involve a significant increase in the probability or consequences of an accident previously evaluated?
Response
No. Inspection practices and acceptance standards will continue to be consistent with the approved ASME code edition as specified by 10 CFR 50.55a.
Therefore, the proposed changes will not increase the probability or consequences of an accident previously evaluated.
- 2) Does the proposed change create the possibility of a new or different kind of accident from any accident previously evaluated?
Response
No. The proposed changes will not alter the plant configuration (no new or different type of equipment will be installed) or require any unusual operator actions. The proposed changes will not alter the way any structure, system, or component functions, and will not significantly alter the manner in which the plant is operated. The response of the plant and the operators following an accident will not be different. In addition, the proposed change does not introduce any new failure modes. Therefore, the proposed changes will not create the possibility of a new or different kind of accident from any accident previously analyzed.
- 3) Does the proposed change involve a significant reduction in a margin of safety?
Response
No. Containment tendon inspection practices and acceptance standards will continue to be consistent with the applicable ASME code edition. There is no change in surveillance acceptance criteria. Therefore, the proposed changes will not result in a reduction in a margin of safety.
Based on the above, STPNOC concludes that the proposed change presents no significant hazards consideration under the standards set forth in 10 CFR 50.92(c), and accordingly, a finding of "no significant hazards consideration" is justified.
Attachment NOC-AE-1 1002665 Page 4 of 4 4.3 Conclusion Based on the considerations discussed above: (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner; (2) such activities will be conducted in compliance with the Commission's regulations; and (3) implementation of the amendment will not be detrimental to the common defense and security or to the health and safety of the public.
5.0 ENVIRONMENTAL CONSIDERATION
The proposed amendment will not change a requirement with respect to installation or use of a facility component located within the restricted area, as defined in 10 CFR 20, nor would change an inspection or surveillance requirement. The proposed amendment does not involve (i) a significant hazards consideration, (ii) a significant change in the types or significant increase in the amounts of any effluents that may be released offsite, or (iii) a significant increase in individual or cumulative occupational radiation exposure.
Accordingly, the proposed amendment meets the eligibility criterion for categorical exclusion set forth in 10 CFR 51.22(c)(9). Therefore, pursuant to 10 CFR 51.22(b), no environmental impact statement, or environmental assessment need be prepared in connection with the proposed amendment.
6.0 IMPLEMENTATION The NRC is requested to approve the proposed amendment by June 30, 2011. This date is flexible. STPNOC will implement the amendment within 30 days after NRC approval.
ENCLOSURE I UPDATED TECHNICAL SPECIFICATION PAGES
CONTAINMENT SYSTEMS CONTAINMENT STRUCTURAL INTEGRITY LIMITING CONDITION FOR OPERATION 3.6.1.6 The structural integrity of the containment(s) shall be maintained as required by the Containment Post-Tensioning System Surveillance Program.
APPLICABILITY: MODES 1, 2, 3, and 4.
ACTION:
If the containment is not OPERABLE, restore containment to OPERABLE status in 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />, or be in at least HOT STANDBY in the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and be in COLD SHUTDOWN in the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
SURVEILLANCE REQUIREMENTS 4.6.1.6 CONTAINMENT PRESTRESSING SYSTEM Verify containment structural integrity in accordance with the Containment Post-Tensioning System Surveillance Program. The provisions of SR 4.0.2 do not applyto extending the interval for this surveillance.
SOUTH TEXAS - UNITS 1 & 2 3/4 6-9 Unit 1 - Amendment No. !1, !37 Unit 2 - Amendment No. 8, 426
6.0 ADMINISTRATIVE CONTROLS 6.8 Procedures, Programs, and Manuals 6.8.3 (continued)
Containment Post-Tensioning System Surveillance Program This program provides controls for monitoring any tendon degradation in pre-stressed concrete containments, including effectiveness of its corrosion protection medium, to ensure containment structural integrity. The program shall include baseline measures prior to initial operations. The Containment Post-Tensioning System Surveillance Program, inspection frequencies, and acceptance criteria shall be in accordance with ASAME.-Gede Section XI, Subsection IWL, of the ASME BoieradrssueVessel Code and applicable addenda :as required by 1992 Edition with 199A_ 2 Add onda, as-1 suplem~t by!CFR50.55a(b)(2)(Yiii),. 10 GFR 50.55a, exetweeanatraie exemption, or relief has been authorized by the NRC.
The provisions of SR 4.0.3 are applicable to the Containment PotTensioning System Surveillance Program inspection frequencies with the exception of the urveillance interval extension allowed per Surveillance Requirement 4.0.2.
- m. Technical Specifications (TS) Bases Control Program This program provides a means for processing changes to the Bases of these Technical Specifications.
- a. Changes to the Bases of the TS shall be made under appropriate administrative controls and reviews.
- b. Licensees may make changes to Bases without prior NRC approval provided the changes do not require either of the following:
- 1. A change in the TS incorporated in the license or
- 2. A change to the updated FSAR or Bases that requires NRC approval pursuant to 10 CFR 50.59.
- c. The Bases Control Program shall contain provisions to ensure that the Bases are maintained consistent with the FSAR.
- d. Proposed changes that meet the criteria of Specification 6.8.3.m.b above shall be reviewed and approved by the NRC prior to implementation. Changes to the Bases implemented without prior NRC approval shall be provided to the NRC on a frequency consistent with 10 CFR 50.71(e).
- n. Offsite Dose Calculation Manual (ODCM)
- 1) The ODCM shall contain the methodology and parameters used in the calculation of offsite doses resulting from radioactive gaseous and liquid effluents, in the calculation of gaseous and liquid effluent monitoring alarm and trip setpoints, and in the conduct of the radiological environmental monitoring program; and (continued)
SOUTH TEXAS - UNITS 1 & 2 6-11 Unit 1 - Amendment No. 137,14 , 151-Unit 2 - Amendment No. 426,129,139
ENCLOSURE 2 PROPOSED TECHNICAL SPECIFICATION PAGES
CONTAINMENT SYSTEMS CONTAINMENT STRUCTURAL INTEGRITY LIMITING CONDITION FOR OPERATION 3.6.1.6 The structural integrity of the containment(s) shall be maintained as required by the Containment Post-Tensioning System Surveillance Program.
APPLICABILITY: MODES 1, 2, 3, and 4.
ACTION:
If the containment is not OPERABLE, restore containment to OPERABLE status in 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />, or be in at least HOT STANDBY in the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and be in COLD SHUTDOWN in the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
SURVEILLANCE REQUIREMENTS 4.6.1.6 CONTAINMENT PRESTRESSING SYSTEM Verify containment structural integrity in accordance with the Containment Post-Tensioning System Surveillance Program. The provisions of SR 4.0.2 do not apply to extending the interval for this surveillance.
SOUTH TEXAS - UNITS 1 & 2 3/4 6-9 Unit 1 -Amendment No. 41-8, -37 Unit 2 - Amendment No. 8, --26
6.0 ADMINISTRATIVE CONTROLS 6.8 Procedures, Programs, and Manuals 6.8.3 (continued)
Containment Post-Tensioninq System Surveillance Program This program provides controls for monitoring any tendon degradation in pre-stressed concrete containments, including effectiveness of its corrosion protection medium, to ensure containment structural integrity. The program shall include baseline measures prior to initial operations. The Containment Post-Tensioning System Surveillance Program, inspection frequencies, and acceptance criteria shall be in accordance with Section Xl, Subsection IWL, of the ASME Boiler and Pressure Vessel Code and applicable addenda as required by 10 CFR 50.55a, except where an alternative, exemption, or relief has been authorized by the NRC.
The provisions of SR 4.0.3 are applicable to the Containment Post-Tensioning System Surveillance Program inspection frequencies with the exception of the surveillance interval extension allowed per Surveillance Requirement 4.0.2.
- m. Technical Specifications (TS) Bases Control Program This program provides a means for processing changes to the Bases of these Technical Specifications.
- a. Changes to the Bases of the TS shall be made under appropriate administrative controls and reviews.
- b. Licensees may make changes to Bases without prior NRC approval provided the changes do not require either of the following:
- 1. A change in the TS incorporated in the license or
- 2. A change to the updated FSAR or Bases that requires NRC approval pursuant to 10 CFR 50.59.
- c. The Bases Control Program shall contain provisions to ensure that the Bases are maintained consistent with the FSAR.
- d. Proposed changes that meet the criteria of Specification 6.8.3.m.b above shall be reviewed and approved by the NRC prior to implementation. Changes to the Bases implemented without prior NRC approval shall be provided to the NRC on a frequency consistent with 10 CFR 50.71(e).
- n. Offsite Dose Calculation Manual (ODCM)
- 1) The ODCM shall contain the methodology and parameters used in the calculation of offsite doses resulting from radioactive gaseous and liquid effluents, in the calculation of gaseous and liquid effluent monitoring alarm and trip setpoints, and in the conduct of the radiological environmental monitoring program; and (continued)
SOUTH TEXAS - UNITS 1 & 2 6-11 Unit 1 - Amendment No. 137,141, !51 Unit 2 - Amendment No. 126,29, 139