NOC-AE-08002346, 1RE14 Inspection Summary Report for Steam Generator Tubing

From kanterella
(Redirected from NOC-AE-08002346)
Jump to navigation Jump to search
1RE14 Inspection Summary Report for Steam Generator Tubing
ML082820569
Person / Time
Site: South Texas STP Nuclear Operating Company icon.png
Issue date: 09/23/2008
From: Jenewein B
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
G25, NOC-AE-08002346, STI: 32357583
Download: ML082820569 (7)


Text

Nuclear Operating Company South rexas Pro/ect ElectricGeneatin$Station P.. Box 289 Wadsworth, Texas 77483 ,

September 23, 2008 NOC-AE-08002346 File No.: G25 10CFR50.55a U. S. Nuclear Regulatory Commission Attention: Document Control Desk One White Flint North 11555 Rockville Pike Rockville, MD 20852-2738 South Texas Project Unit 1 Docket No. STN 50-498 1 RE14 Inspection Summary Report for Steam Generator Tubing Enclosed are four copies of the summary report describing the results of the steam generator tube inspection performed during refueling outage 1RE14. The summary report satisfies the reporting requirements of ASME Section XI, Article IWA-6230, and Section 6.9.1.7 of the South Texas Project Technical Specifications.

This inspection was not required by STP Technical Specification Section 6.8.3.o for maintaining steam generator tube integrity and therefore is not for surveillance credit. This report has been prepared to continue appropriate communication with the Nuclear Regulatory Commission regarding all examinations performed during 1 RE1 4 and their results.

There are no commitments in this letter.

If there are any questions regarding this report, please contact either Mr. P. L. Walker at (361) 972-8392 or me at (361) 972-7431.

t Br onJenewein

  • k*nger,r Testing/Programs PLW

Enclosure:

1 RE14 Inspection Summary Report for Steam Generator Tubing of the South Texas Project Electric Generating Station Unit 1 STI: 32357583 j,.yz(r

NOC-AE-08002346 Page 2 of 2 cc: (one copy of attachment)

(paper copy) (electronic copy)

Regional Administrator, Region IV Kevin Howell U. S. Nuclear Regulatory Commission Catherine Callaway 612 East Lamar Blvd., Suite 400 Jim von Suskil Arlington, Texas 76011-4125 NRG South Texas LP Mohan C. Thadani A. H. Gutterman, Esquire Senior Project Manager Morgan, Lewis & Bockius LLP U.S. Nuclear Regulatory Commission One White Flint North (MS 7 D1) Mohan C. Thadani 11555 Rockville Pike U. S. Nuclear Regulatory Commission Rockville, MD 20852 Richard A. Ratliff Ed Alarcon Bureau of Radiation Control J. J. Nesrsta Texas Department of State Health Services R. K. Temple 1100 West 49th Street Kevin Polio Austin, TX 78756-3189 City Public Service C. M. Canady Jon C. Wood City of Austin Cox Smith Matthews Electric Utility Department 721 Barton Springs Road C. Kirksey Austin, TX 78704 City of Austin Senior Resident Inspector U. S. Nuclear Regulatory Commission P. O. Box 289, Mail Code: MN116 Wadsworth, TX 77483

S Mr 1 1RE14 INSPECTION

SUMMARY

REPORT FOR STEAM GENERATOR TUBING of the SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNIT 1 P.O. BOX 289 WADSWORTH, TEXAS 77483 Commercial Operation: August 25, 1988 Issue Date: August 20, 2008

1RE14 INSPECTION

SUMMARY

REPORT FOR STEAM GENERATOR TUBING of the SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNIT 1 USNRC DOCKET NO.: STN 50-498 OPERATING LICENSE NO.: NPF-76 COMMERCIAL OPERATION DATE: August 25, 1988 Prepared By+__* *c,*c D. A. Stuhler Date Test Engineer Approved By: 6W14ý L Spiess Date SAoervisor, Test Engineering

Attachment NOC-AE-08002346 Page 1 of 3 SOUTH TEXAS PROJECT UNIT 1 1RE14 INSPECTION

SUMMARY

REPORT FOR STEAM GENERATOR TUBING Introduction This summary report describes the inspection of steam generator (SG) tubing at South Texas Project (STP) Unit 1 performed during refueling outage 1RE14 in April 2008. The 1RE14 inspection was required only for SG 1 D.

Steam generator eddy current inspection and Foreign Object Search and Retrieval (FOSAR) programs were conducted in steam generator 1D during refueling outage 1RE14. The inspection plan was developed to address tube wear and subsequent structural integrity concern associated with the inventory of feedwater stabilizer wire remaining in SG 1 D. The wire remnants originated from a feedwater heater cable stabilizer and migrated into the steam generator during cycle 11.

The 1 RE1 3 assessments projected that the structural and leakage integrity for SG's 1 A, 1 B, and 1C will continue until the steam generator inspection planned for 1RE16; therefore, no inspections of these steam generators were performed during 1 RE1 4.

The inservice inspection program, "2008 Outage Plan In-service Steam Generator Inspection for South Texas Project Electric Generating Station, Unit 1," identified the steam generator tube areas to be examined by eddy current (EC) testing and the procedures expected to be used during the inservice inspection. A degradation assessment was prepared prior to the outage to establish the scope of eddy current inspections and identify necessary examination, techniques and areas of applicability. These techniques were reviewed to ensure their qualification.

Scope of Examinations The primary side eddy current inspection for SG 1D was 100% +Pt inspection of all open tubes (7572) both hot and cold legs from below the top of the tubesheet (TTS) to the top of the 1 st tube support plate (TSP). The +Pt inspection region was the entire tube length from TTS (-3") to 1 st TSP (+6"). No bobbin coil inspections were performed during 1RE14 since +Pt is more sensitive for loose parts and loose parts wear.

Included in the +Pt inspection of the hot leg from below the TTS were fourteen locations containing overexpansions/bulges identified during pre-service inspection (PSI) of SG 1D.

The secondary side inspection of SG 1D included an extensive in-bundle inspection and FOSAR. The FOSAR was performed for every hot and cold leg column at the top of the tubesheet, the top and bottom of the flow distribution baffle (FDB), and the top of the 1 st and 2 nd tube support plate.

Examination Results Primary and secondary side inspections during 1RE14 were required for SG 1D only. The inspection plan was developed to address tube wear and, consequent structural integrity concern associated with the inventory of feedwater stabilizer wire remaining in SG 1 D.

Attachment NOC-AE-08002346 Page 2 of 3 The primary side eddy current inspection for SG 1 D was 100% +Pt inspection of both hot and cold legs from below the top of the tubesheet (TTS -3") to the top of the 1 st tube support plate (TSP +6"). This inspection included 100% of the flow distribution baffle. Site-specific EC detection and sizing techniques, qualified in accordance with EPRI non-destructive examination guidelines, were used to perform the analysis. One location (R70C140 HL) exhibited low level wear (9%) at the top of the tubesheet due to the presence of a metallic gasket remnant. Neither new wear due to stabilizer wire nor any corrosion-induced degradation was observed, and no tubes were removed from service.

During the +Pt inspection, signals indicative of external foreign objects (PLP) were detected.

These PLP calls were attributed to stabilizer wire remnants trapped in the nanofoil at the FDB or deposited at or near the nanofoil. No wear was detected by eddy current associated with the PLP calls. The locations of these PLP calls were compared with the detailed visual inspection records and, if necessary, additional visual inspections were performed within the capability of the secondary side equipment to evaluate the PLP calls.

For secondary-side visual inspections, a total of 220 foreign objects were identified. Nine were identified at the 2 nd TSP, fourteen at the 1 st TSP, three below the 1st TSP, 86 on the top of the FDB, 27 at or below the FDB (four were duplicates from the top of the FDB), and 81 at the TTS.

Of the 220 objects, 180 were stabilizer wire, 14 were metal gasket remnants, 11 were unspecified metallic remnants, five were graphite gasket filler, five were sludge rock/scale, two were called weld slag, and three other very small objects that did not warrant further investigation. 150 foreign objects were retrieved during the 1 RE1 4 efforts. The 70 objects that remain in SG 1 D are generally small and evaluation revealed no tube wear is expected over the next two cycles. Visual inspection of the TTS peripheral tubes was performed to identify and remove any foreign objects transposed to the periphery in the retrieval efforts that accompanied the in-bundle inspection and any objects resident in the annulus between the tube bundle and the vessel wall. All identified loose parts in the periphery annulus were removed from SG 1D.

Final comparison of the eddy current PLP calls and visual inspection results was performed to identify any location requiring additional visual inspections.

The following is a list of tubes with signals of interest:

Row-84 Column-22 has a single signal just above the top of tube sheet hot leg. Sizing was performed last inspection with +Pt which read 20% at this location. The signal characteristics remain the same as previous with no foreign objects present.

Row-84 Column-24 has a single signal just above the. top of tube sheet hot leg. Sizing was performed last inspection with +Pt which read 6% at this location. The signal characteristics remain the same as previous with no foreign objects present.

Row-99 Column-35 has a single signal just above the top of tube sheet cold leg. Sizing was performed last inspection with +Pt which read 11 % at this location. The signal characteristics remain the same as previous with no foreign objects present.

Row-1 16 Column-48 has a single signal just above the top of tube sheet cold leg. Sizing was performed last inspection with +Pt which read 11 % at this location. The signal characteristics remain the same as previous with no foreign objects present.

Attachment NOC-AE-08002346 Page 3 of 3 Row-2 Column-138 has two signals just above the top of tube sheet cold leg. Sizing was performed last inspection with +Pt, with values of 8% and 9% respectively. The signal characteristics remain the same as previous with no foreign objects present.

(

Row-70 Column-1 40 has a single signal just above the top of tube sheet hot leg. Sizing was performed this inspection with +Pt which read 9% at this location.' The ýignal characteristics are consistent with low level signals identified previously. Secondary side visual examinations confirmed a very small wear scar caused by gasket material. The foreign object was removed prior to performing eddy current.

Tube Plugging No tubes were removed from service during 1 RE1 4.

The total number of tubes plugged per steam generator to date in STP Unit 1 is as follows:

Steam Generator 1A 33 0.44%

Steam Generator 1B 40 0.53%

Steam Generator 1C 26 0.34%

Steam Generator 1D 13 0.17%

Condition Monitoring Results The maximum depth of the wear indication at location R70C140 was well below the condition monitoring limits defined in the degradation assessment. Based on the condition monitoring evaluation, inspections of tubes in service during Cycle 14 confirmed that they all met the Regulatory Guide 1.121 structural integrity requirements. The only confirmed degradation was low level wear (9%) due to a gasket remnant, and no primary-to-secondary leakage was observed prior to the end of Cycle 14. The condition monitoring assessment requirements for SG 1D operation were satisfied. The assessment of the secondary side inspection results demonstrated that any remaining foreign objects would not cause wear at a level that would violate the condition monitoring limit during the next two operating cycles for SG 1D. No challenges to the condition monitoring limits were identified; therefore, the condition monitoring requirements for the SG 1 D tube bundle at end of Cycle 14 were satisfied.