MONTHYEARNLS2024068, Core Operating Limits Report, Cycle 34, Revision 02024-10-25025 October 2024 Core Operating Limits Report, Cycle 34, Revision 0 NLS2024065, 10 CFR 50.59(d)(2) and 10 CFR 72.48(d)(2) Summary Report2024-10-0707 October 2024 10 CFR 50.59(d)(2) and 10 CFR 72.48(d)(2) Summary Report NLS2024053, Licensee Guarantees of Payment of Deferred Premiums2024-07-30030 July 2024 Licensee Guarantees of Payment of Deferred Premiums NLS2024055, Data from Metamic Coupon Sampling Program2024-07-29029 July 2024 Data from Metamic Coupon Sampling Program NLS2024052, Supplement to the Application to Modify the Allowable Value for Cooper Nuclear Station Technical Specifications High Pressure Coolant Injection Pump Discharge Low Flow2024-07-24024 July 2024 Supplement to the Application to Modify the Allowable Value for Cooper Nuclear Station Technical Specifications High Pressure Coolant Injection Pump Discharge Low Flow NLS2024051, Supplement to the Application to Revise Technical Specifications to Adopt TSTF-374, Revision to Diesel Fuel Oil Testing Program2024-07-0303 July 2024 Supplement to the Application to Revise Technical Specifications to Adopt TSTF-374, Revision to Diesel Fuel Oil Testing Program NLS2024025, License Amendment Request to Revise Technical Specifications Table 3.3.2.1-1, Control Rod Block Instrumentation2024-05-0909 May 2024 License Amendment Request to Revise Technical Specifications Table 3.3.2.1-1, Control Rod Block Instrumentation NLS2024037, 2023 Annual Radiological Environmental Report2024-05-0808 May 2024 2023 Annual Radiological Environmental Report NLS2024030, Annual Radioactive Effluent Release Report2024-04-25025 April 2024 Annual Radioactive Effluent Release Report NLS2024033, Preparation and Scheduling of Operator Licensing Examinations2024-04-25025 April 2024 Preparation and Scheduling of Operator Licensing Examinations NLS2024031, Notice of Intent to Apply for Subsequent Renewal of Operating License2024-04-22022 April 2024 Notice of Intent to Apply for Subsequent Renewal of Operating License NLS2024036, Nebraska Public Power District 2023 Financial Report2024-04-19019 April 2024 Nebraska Public Power District 2023 Financial Report NLS2024027, Response to NRC Request for Additional Information Regarding Application for the Emergency License Amendment Request to Revise Technical Specifications 3 .3 .1.1, Reactor Protection (RPS) Instrumentation2024-04-0303 April 2024 Response to NRC Request for Additional Information Regarding Application for the Emergency License Amendment Request to Revise Technical Specifications 3 .3 .1.1, Reactor Protection (RPS) Instrumentation NLS2024024, Emergency License Amendment Request to Revise Technical Specifications 3.3.1.1, Reactor Protection (RPS) Instrumentation2024-04-0101 April 2024 Emergency License Amendment Request to Revise Technical Specifications 3.3.1.1, Reactor Protection (RPS) Instrumentation NLS2024018, Property Insurance Coverage2024-03-20020 March 2024 Property Insurance Coverage NLS2024017, Response to an Apparent Violation in NRC Inspection Report 05000298/2023012; EA-24-0012024-03-0808 March 2024 Response to an Apparent Violation in NRC Inspection Report 05000298/2023012; EA-24-001 NLS2024009, Response to Nuclear Regulatory Commission Request for Additional Information Regarding Application to Revise Technical Specifications to Support Inspection of2024-03-0808 March 2024 Response to Nuclear Regulatory Commission Request for Additional Information Regarding Application to Revise Technical Specifications to Support Inspection of NLS2024001, Application to Modify the Allowable Value for Cooper Nuclear Station Technical Specifications High Pressure Coolant Injection Pump Discharge Low Flow2024-02-16016 February 2024 Application to Modify the Allowable Value for Cooper Nuclear Station Technical Specifications High Pressure Coolant Injection Pump Discharge Low Flow NLS2024006, Response to Nuclear Regulatory Commissions Request for Additional Information for Relief Request RC3-022024-01-25025 January 2024 Response to Nuclear Regulatory Commissions Request for Additional Information for Relief Request RC3-02 NLS2024007, Emergency Plan Implementing Procedure 5.7.1, Revision 732024-01-16016 January 2024 Emergency Plan Implementing Procedure 5.7.1, Revision 73 NLS2024003, 30 Day Report - Unauthorized Disassembly of Liquid Scintillation Detector2024-01-15015 January 2024 30 Day Report - Unauthorized Disassembly of Liquid Scintillation Detector NLS2024004, Annual Report of Changes and Errors in Emergency Core Cooling System Evaluation Models for 20232024-01-10010 January 2024 Annual Report of Changes and Errors in Emergency Core Cooling System Evaluation Models for 2023 NLS2023053, ISFSI, Supplement to Exemption Request from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-30030 November 2023 ISFSI, Supplement to Exemption Request from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation NLS2023050, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-22022 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation NLS2023045, Application to Revise Technical Specifications to Adopt TSTF-374, Revision to Diesel Fuel Oil Testing Program2023-11-15015 November 2023 Application to Revise Technical Specifications to Adopt TSTF-374, Revision to Diesel Fuel Oil Testing Program NLS2023051, Response to Nuclear Regulatory Commission Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-551, Revise Secondary Containment Surveillance Requirements2023-10-10010 October 2023 Response to Nuclear Regulatory Commission Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-551, Revise Secondary Containment Surveillance Requirements NLS2023049, 10 CFR Part 21 Report Regarding HGA Relays2023-09-0606 September 2023 10 CFR Part 21 Report Regarding HGA Relays NLS2023029, License Amendment Request to Revise Technical Specifications to Support Inspection of Diesel Fuel Oil Storage Tanks2023-09-0606 September 2023 License Amendment Request to Revise Technical Specifications to Support Inspection of Diesel Fuel Oil Storage Tanks NLS2023047, Licensee Guarantees of Payment of Deferred Premiums2023-07-26026 July 2023 Licensee Guarantees of Payment of Deferred Premiums NLS2023033, 10 CFR 50.55a Relief Request RC3-022023-06-27027 June 2023 10 CFR 50.55a Relief Request RC3-02 NLS2023039, Preparation and Scheduling of Operator Licensing Examinations2023-06-0101 June 2023 Preparation and Scheduling of Operator Licensing Examinations NLS2023038, Nebraska Public Power District 2022 Financial Report2023-05-22022 May 2023 Nebraska Public Power District 2022 Financial Report NLS2023031, Annual Radiological Environmental Report2023-05-11011 May 2023 Annual Radiological Environmental Report NLS2023018, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-0303 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling NLS2023017, Application to Revise Technical Specifications to Adopt TSTF-551, Revise Secondary Containment Surveillance Requirements2023-05-0303 May 2023 Application to Revise Technical Specifications to Adopt TSTF-551, Revise Secondary Containment Surveillance Requirements NLS2023030, Annual Radioactive Effluent Release Report2023-04-27027 April 2023 Annual Radioactive Effluent Release Report NLS2023007, Technical Specification Bases Changes2023-04-17017 April 2023 Technical Specification Bases Changes NLS2023027, Annual Report of Individual Exposure Monitoring2023-04-13013 April 2023 Annual Report of Individual Exposure Monitoring NLS2023021, Quality Assurance Program Changes2023-04-10010 April 2023 Quality Assurance Program Changes NLS2023020, Decommissioning Funding2023-03-29029 March 2023 Decommissioning Funding NLS2023019, Property Insurance Coverage2023-03-23023 March 2023 Property Insurance Coverage NLS2023010, Inservice Inspection OAR-1 Owners Activity Report for Cooper Nuclear Station2023-02-0909 February 2023 Inservice Inspection OAR-1 Owners Activity Report for Cooper Nuclear Station NLS2023005, Annual Report of Changes and Errors in Emergency Core Cooling System Evaluation Models for 20222023-01-19019 January 2023 Annual Report of Changes and Errors in Emergency Core Cooling System Evaluation Models for 2022 NLS2022054, Preparation and Scheduling of Operator Licensing Examinations2023-01-0505 January 2023 Preparation and Scheduling of Operator Licensing Examinations NLS2022055, Emergency Plan, Revision 812023-01-0404 January 2023 Emergency Plan, Revision 81 NLS2022053, CNS-2022-11 Post Exam Submittal2022-11-22022 November 2022 CNS-2022-11 Post Exam Submittal NLS2022050, Notification of Revision to Cooper Nuclear Station Emergency Response Data System Data Point Library2022-11-0909 November 2022 Notification of Revision to Cooper Nuclear Station Emergency Response Data System Data Point Library NLS2022048, Management Change and Correspondence Update2022-11-0101 November 2022 Management Change and Correspondence Update NLS2022047, Core Operating Limits Report, Cycle 33, Revision 02022-10-14014 October 2022 Core Operating Limits Report, Cycle 33, Revision 0 NLS2022042, 10 CFR 50.59(d)(2) and 10 CFR 72.48(d)(2) Summary Report2022-10-0707 October 2022 10 CFR 50.59(d)(2) and 10 CFR 72.48(d)(2) Summary Report 2024-07-30
[Table view] |
Text
Nebraska Public Power District Alwa:ys there when :you need us NLS2017100 December 20, 2017 Attention: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Subject:
Anchor Darling Double Disc Gate Valve Information and Status Cooper Nuclear Station, Docket No. 50-298, License No. DPR-46
References:
- 1) Letter from Greg Krueger (NEI) to John Lubinski (U.S. Nuclear Regulatory Commission), Anchor Darling Double Disc Gate Valve Industry Resolution Plan Update (Project Number 689), dated August 4, 2017
- 2) Letter from Joseph Pollock (NEI) to Brian Holian (U.S. Nuclear Regulatory Commission), NSIAC Concurrence on Anchor Darling Double Disc Gate Valve Industry Response Actions (Project Number 689), dated October 26, 2017
- 3) BWROG Topical Report TP16-1-112, Recommendations to Resolve Flowserve 10 CFR Part 21 Notification Affecting Anchor Darling Double Disc Gate Valve Wedge Pin Failures (Revision 4)
Dear Sir or Madam:
In Reference 1, the Nuclear Energy Institute (NEI) provided the Nuclear Regulatory Commission (NRC) a resolution plan for the U.S. Nuclear Industry to address the known Anchor Darling Double Disc Gate Valve (ADDDGV) issues. Reference 2 indicated each utility will provide a listing of their Anchor Darling valve population with active safety functions along with relevant valve information, including the results of susceptibility evaluations, repair status, and a repair schedule for each susceptible valve not yet repaired. This letter serves to provide this information for Cooper Nuclear Station. -
The attachment to this letter contains the following information for each ADDDGV:
- Plant Name, Unit, and Valve ID;
- Valve Functional Description;
- Active Safety Function (open, close, both);
- Are multiple design basis post-accident strokes required (yes/no);
COOPER NUCLEAR STATION P. 0. Box 98 / Brownville, NE 68321-0098 Telephone: (402) 825-3811 / Fax: (402) 825-5211 www.nppd.com
NLS2017100 Page 2 of2
- Expert Panel Risk Ranking (high, medium, low);
- Result of susceptibility evaluation (susceptible or not susceptible);
- Is the susceptibility evaluation in general conformance with TP16-1-112R4 (Reference 3)
(yes/no);
- Does the susceptibility evaluation rely on thread friction (yes/no)? If yes, was the coefficient of friction (COF) greater than 0.10? For cases where thread-friction was relied upon, information is provided whether the COF was above or below 0.1;
- Was an initial stem-rotation check performed (yes/no)? If yes, include rotation criteria (i.e. :SlO degrees or :S5 degrees);
- Was the diagnostic test data reviewed for failure precursors described in TP16-1-112R4 (Reference 3) (yes/no);
- The valve's repair status (i.e. repaired or not repaired); and
- A repair schedule for each susceptible valve.
This letter contains no regulatory commitments.
Should you have any questions or require additional information, please contact Jim Shaw, Licensing Manager, at (402) 825-2788.
Sincerely,
/;?;;:,~ f(V1)1& /wgo 'Jvv-. BuJJ-vice President - Nuclear and Chief Nuclear Officer
/dv Attachments: Cooper Nuclear Station (CNS) Anchor Darling Double Disc Gate Valve Listing cc: Regional Administrator w/ attachment USNRC - Region IV Cooper Project Manager w/ attachment USNRC - NRR Plant Licensing Branch IV Senior Resident Inspector w/ attachment USNRC-CNS NPG Distribution w/o attachment CNS Records w/ attachment
NLS2017100 Attachment Page 1 of 1 iI Cooper Nuclear Station (CNS) Anchor Darling Double Disc Gate Valve Listing
!' Is the Does the Was the Are multiple
' susceptibility susceptibility Was an initial stem- diagnostic test design Expert *, Result of Valve Valve Active evaluation in evaluation rely on rotation check data reviewed Plant basis post- Panel susceptibility Valve repair Unit Valve ID System Functional Size Safety general thread friction? performed? for failure Name accident Risk evaluation status
. Description (inches) Function conformance If yes, was the If yes, include precursors strokes Ranking with. TP16 COF greater than rotation criteria described in required?
112R4?<1> 0.10? i TP16-1-112R4?
(Open, (High, (susceptible (No), (No), (repaired Close,. Medium, or (Yes/No) (Yes, >0.10), (Yes, :::;10 deg.), (Yes/ No) or (Yes/No)
Both) Low) not susceptible) (Yes, <0.10) (Yes, <5 deg.) not repaired)
Reactor Recirc :
. :. Pump A Ye~, ongoing and RR-MOV- Reactor Discharge Yes, Yes periodic, once per CNS 1 M053A Recirculation Isolation 28 Close No Low Susceptible<2> Yes (>0.10, pendingi2) cycle, :S20 degrees< 3) Yes Not repaired<4 )
I Reactor Recirc PumpB yes, ongoing and RR-MOV-- Reactor -Discharge Yes, Yes periodic, once per I , (3)
CNS 1 M053B Recirculation , Isolation 28 Close No Low Susceptible<2
) Yes (>0.10, pendingf) cycle, :S20 degrees Yes Not repaired<4)
(1) Applied Wedge Pin Torque must bound anticipated design basis operating torque requirements and current maximum total torque. '
(2) Weak Link Analysis is currently in development to incorporate the wedge pin subcomponent and will move this to "non-susceptible" status; final acceptance projected January 26, 2018. Exact coefficient of friction (COF) is yet to be determined.
(3) Previous inspections used a :::20 degrees rotation criteria. The susceptible valves will be inspected in RE30 (Fall 2018) to the rotation criteria specified in the current inspection procedure which is :::5 degrees.
(4) CNS has no plans for disassembly/repair 1planned at this time. Completion of evaluation per Note (2) will move this from priority 3b to priority 5 with no inspection required:
The following table identifies commitments made in this document. (Any other actions discussed in the submittal represent intended or planned actions. They are described to the NRC for the NRC's information and are not regulatory commitments.)
.. COMMITMENT TYPE COMMITTED DATE OR COMMITMENT ONE-TIME ACTION Programmatic "OUTAGE" (Yes/No) (Yes/No)
None i'
'