NLS2017047, Preparation and Scheduling of Operator Licensing Examinations

From kanterella
Jump to navigation Jump to search
Preparation and Scheduling of Operator Licensing Examinations
ML17125A262
Person / Time
Site: Cooper Entergy icon.png
Issue date: 04/25/2017
From: Shaw J
Nebraska Public Power District (NPPD)
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NLS2017047
Download: ML17125A262 (2)


Text

H Nebraska Public Power District Always there when you need us NLS2017047 April25,2017 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

Subject:

Preparation and Scheduling of Operator Licensing Examinations Cooper Nuclear Station, Docket No. 50-298, DPR-46

Reference:

Nuclear Regulatory Commission Regulatory Issue Summary 2017-03, "Preparation and Scheduling of Operator Licensing Examinations"

Dear Sir or Madam:

The purpose ofthis letter is to transmit to the U.S. Nuclear Regulatory Commission (NRC) a completed NRC Form 536 for Cooper Nuclear Station as requested in the reference above.

This letter contains no new commitments.

Should you have any questions or require additional information, please contact me at (402) 825-2788 or Joshua Adams, Nuclear Instructor, at (402) 825-5756.

Sincerely, Licensing Manager

/jo

Attachment:

NRC Form 536, "Operator Licensing Examination Data" cc: Regional Administrator w/attachment Training Manager w/o attachment USNRC - Region IV Cooper Nuclear Station Operations Initial Training Superintendent CNS Records w/attachment w/attachment Cooper Nuclear Station COOPER NUCLEAR STATION P.O. Box 98 /Brownville, NE 68321-0098 Telephone: (402) 825-3811 /Fax: (402) 825-5211 www.nppd.com

NRC FORM 536 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3150*0131 EXPIRES: 10/31/2017 (05-2016)

,:.,,v'-"*"'R AE'Ou~.,>.

Estimated burden per response lo comply wi!h this voluntary information collection request: 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. This information collection is used to plan budgets and resources for opera!or examinations. Send

"'~ ., o.,,"

I!!

0 0

OPERATOR LICENSING comments regarding burden estimate to the FOIA, Privacy, and Information Collections Branch (T-5

~ £ F53), U.S. Nuclear Regula!ory Commission, Washington, DC20555-0001, or by e-mail lo

~ J EXAMINATION DATA lnfocollects.Resource@nrc.gov, and to the Desk Officer, Office of Information and Regula!ory Affairs,

.-~.., +O~

...... .,..., NEOB-10202, (3150-0131), Office of Management and Budge!, Washing!on, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, !he NRC may no! conduc! or sponsor, and a person is not required to respond lo, !he information collection.

FACILITY NRCREGION Cooper Nuclear Station IV 72676 648 A Ave, PO Box 98 Brownville, NE 68321 A. PROPOSED EXAMINATION PREPARATION SCHEDULE CY2019 CY2020 CY2021 CY2022 PROPOSED NUMBER ESTIMATED NUMBER OF LICENSEE-PREPARED 0 1 0 1 EXAMINATIONS ESTIMATED NUMBER OF NRG-PREPARED 0 0 0 0 EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS CY2019 CY2020 CY2021 CY2022 PROPOSED NUMBER NUMBER OF REACTOR OPERATORS 0 6 0 6 NUMBER OF SENIOR REACTOR OPERATORS- INSTANT 0 3 0 9 NUMBER OF SENIOR REACTOR OPERATORS-UPGRADE 0 3 0 3 NUMBER OF SENIOR REACTOR OPERATORS- LIMITED 0 0 0 0 PROPOSED DATES PRIMARY DATE NIA 811712020 NIA 8108/2022 ALTERNATE DATE NIA 812412020 NIA 8/1512022

c. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE PROPOSED NUMBER MARCH CY

-2019 SEPTEMBER MARCH CY

-2020 SEPTEMBER ESTIMATED NUMBER OF 9 0 0 15 CANDIDATES NRG FORM 536 (05-2016)