N Nebraska Public Power District Always there when you need us NLS2005033 March 29, 2005 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555-0001
Subject:
Notice of Intent to Submit License Renewal Application Cooper Nuclear Station, NRC Docket 50-298, DPR-46
Reference:
Letter from D. Wilson (Nebraska Public Power District) to U.S. Nuclear Regulatory Commission dated January 24, 2002, "Application for Renewal of Operating License" (NLS2002016).
The purpose of this letter is to provide the Nuclear Regulatory Commission (NRC) notice of the intent of the Nebraska Public Power District (NPPD) to submit an application for license renewal for Cooper Nuclear Station.
In the referenced letter, NPPD informed the NRC of its previous decision to delay its application for license renewal beyond 2003, and that a revised date would be provided to the NRC once plans and a schedule were developed. NPPD intends to submit the license renewal application in September 2008. NPPD will inform the NRC of any adjustments to this anticipated submittal time frame as the project progresses.
Should you have any questions concerning this matter, please contact Mr. Paul Fleming at (402) 825-2774.
Sincerely, Randall K. Edington Vice President - Nuclear and Chief Nuclear Officer
/wrv COOPER NUCLEAR STATION P.O. Box 98 / Brownville, NE 68321-0098 Telephone: (402) 825-3811/ Fax: (402) 825-5211 www nppd.com 0Q0
NLS2005033 Page 2 of 2 cc:
Regional Administrator USNRC - Region IV Senior Project Manager USNRC - NRR Project Directorate IV-1 Senior Resident Inspector USNRC NPG Distribution Records
I ATTACHMENT 3 LIST OF REGULATORY COMMITMENTSl Correspondence Number: NLS2005033 The following table identifies those actions committed to by Nebraska Public Power District (NPPD) in this document. Any other actions discussed in the submittal represent intended or planned actions by NPPD. They are described for information only and are not regulatory commitments. Please notify the Licensing Manager at Cooper Nuclear Station of any questions regarding this document or any associated regulatory commitments.
COMMITTED DATE COMMITMENT OR OUTAGE None 4-4-
4-I PROCEDURE 0.42 l
REVISION 16 l