MONTHYEARNL-23-0310, Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 20222023-04-25025 April 2023 Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 2022 NL-21-0606, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 20202021-07-0101 July 2021 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2020 ML21090A0352021-03-24024 March 2021 Westinghouse Electric Company LLC, 10 CFR 50.46 Annual Report for the AP1000 Plant Design ND-20-1325, Report of CFR 50.59 Changes, Tests and Experiments and 10 CFR 52 Appendix D Departure Report2020-12-11011 December 2020 Report of CFR 50.59 Changes, Tests and Experiments and 10 CFR 52 Appendix D Departure Report NL-20-0630, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 20192020-06-19019 June 2020 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2019 NL-20-0548, Submittal of Annual Radiological Environmental Operating Reports for 20192020-05-13013 May 2020 Submittal of Annual Radiological Environmental Operating Reports for 2019 NL-19-0650, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 20182019-06-0505 June 2019 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2018 NL-18-0539, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 20172018-05-14014 May 2018 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2017 ND-18-0393, Submittal of 10 CFR 50.46 Annual Report2018-04-0606 April 2018 Submittal of 10 CFR 50.46 Annual Report NL-18-0181, ISFSI 10 CFR 72.48 (d)(2) Biennial Report2018-02-22022 February 2018 ISFSI 10 CFR 72.48 (d)(2) Biennial Report ND-17-2038, Report of 10 CFR 50.59 Changes, Tests and Experiments and 10 CFR 52 Appendix D Departure Report2017-12-11011 December 2017 Report of 10 CFR 50.59 Changes, Tests and Experiments and 10 CFR 52 Appendix D Departure Report NL-17-1560, CFR 72.48(d)(2)Biennial Report2017-09-19019 September 2017 CFR 72.48(d)(2)Biennial Report NL-17-1354, ISFSI - Submittal of 10 CFR 72.48(d)(2) Biennial Report2017-07-31031 July 2017 ISFSI - Submittal of 10 CFR 72.48(d)(2) Biennial Report NL-17-0463, Transmittal of 10 CFR 50.46 ECCS Evaluation Model Annual Report for 20162017-04-20020 April 2017 Transmittal of 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2016 NL-16-2660, Submittal of 10 CFR 50.46 ECCS Evaluation Model Annual Report for 20152016-12-21021 December 2016 Submittal of 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2015 NL-15-0802, J.M. Farley, E.I. Hatch, Vogtle - Annual Non-Radioactive Environmental Operating Reports for 20142015-04-30030 April 2015 J.M. Farley, E.I. Hatch, Vogtle - Annual Non-Radioactive Environmental Operating Reports for 2014 NL-14-0900, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2013 and Significant Change/Error Report2014-06-20020 June 2014 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2013 and Significant Change/Error Report NL-13-2576, CFR50.46 ECCS Evaluation Model Annual Report for 20122013-12-23023 December 2013 CFR50.46 ECCS Evaluation Model Annual Report for 2012 NL-13-2277, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2012 and Significant Change/Error Report2013-10-30030 October 2013 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2012 and Significant Change/Error Report NL-13-1006, Annual Radiological Environmental Operating Reports for 20122013-05-15015 May 2013 Annual Radiological Environmental Operating Reports for 2012 NL-13-0889, Annual Radioactive Effluent Release Report for 20122013-04-30030 April 2013 Annual Radioactive Effluent Release Report for 2012 NL-13-0450, ISFSI and Edwin I. Hatch, Units 1, 2 and ISFSI, Annual Radioactive Effluent Release Report2013-03-0101 March 2013 ISFSI and Edwin I. Hatch, Units 1, 2 and ISFSI, Annual Radioactive Effluent Release Report NL-12-2567, CFR 50.46 ECCS Evaluation Model Annual Report for 20112012-12-18018 December 2012 CFR 50.46 ECCS Evaluation Model Annual Report for 2011 NL-12-1983, 10 CFR 50.46 ECCS Evaluation Model, Annual Report for 2011 and Significant Change/Error Report2012-10-18018 October 2012 10 CFR 50.46 ECCS Evaluation Model, Annual Report for 2011 and Significant Change/Error Report NL-11-2402, CFR 50.46 ECCS Evaluation Model Annual Reports for 20102011-12-21021 December 2011 CFR 50.46 ECCS Evaluation Model Annual Reports for 2010 NL-11-0888, Annual Radiological Environmental Operating Reports for 20102011-05-12012 May 2011 Annual Radiological Environmental Operating Reports for 2010 NL-11-0865, Annual Non-Radiological Environmental Operating Reports for 20102011-04-30030 April 2011 Annual Non-Radiological Environmental Operating Reports for 2010 NL-10-0905, Enclosure 2 - Joseph M. Farley, Units 1 and 2, Annual Radiological Environmental Operating Report for 20092010-05-14014 May 2010 Enclosure 2 - Joseph M. Farley, Units 1 and 2, Annual Radiological Environmental Operating Report for 2009 ML1013905352010-05-14014 May 2010 Enclosure 1 - Edwin I. Hatch, Units 1 and 2, Annual Radiological Environmental Operating Report for 2009 ML1013905332010-05-14014 May 2010 Enclosure 2 - Joseph M. Farley, Units 1 and 2, Annual Radiological Environmental Operating Report for 2009 NL-10-0905, Enclosure 3 - Vogtle, Units 1 and 2, Annual Radiological Environmental Operating Report for 20092010-05-14014 May 2010 Enclosure 3 - Vogtle, Units 1 and 2, Annual Radiological Environmental Operating Report for 2009 NL-10-0905, Enclosure 1 - Edwin I. Hatch, Units 1 and 2, Annual Radiological Environmental Operating Report for 20092010-05-14014 May 2010 Enclosure 1 - Edwin I. Hatch, Units 1 and 2, Annual Radiological Environmental Operating Report for 2009 NL-10-0839, Submittal of Annual Non-Radiological Environmental Operating Report for 20092010-04-28028 April 2010 Submittal of Annual Non-Radiological Environmental Operating Report for 2009 NL-09-1838, CFR 50.46 ECCS Evaluation Model Annual Reports for 20082009-12-17017 December 2009 CFR 50.46 ECCS Evaluation Model Annual Reports for 2008 NL-09-0775, Annual Radiological Environmental Operating Reports for 20082009-05-14014 May 2009 Annual Radiological Environmental Operating Reports for 2008 NL-08-1735, Plants - 10 CFR 50.46 ECCS Evaluation Model Annual Reports for 20072008-12-19019 December 2008 Plants - 10 CFR 50.46 ECCS Evaluation Model Annual Reports for 2007 NL-08-0623, Joseph M. Farley, Units 1 and 2, Annual Submission Report2008-04-23023 April 2008 Joseph M. Farley, Units 1 and 2, Annual Submission Report ML0812203982008-04-23023 April 2008 Annual Submission Report ML0713600572007-05-14014 May 2007 Annual Radiological Environmental Operating Report for 2006 ML0713600592007-05-14014 May 2007 Annual Radiological Environmental Operating Report for 2006 NL-07-1039, Annual Radiological Environmental Operating Report for 20062007-05-14014 May 2007 Annual Radiological Environmental Operating Report for 2006 ML0712204712007-04-30030 April 2007 Enclosure 3, Vogtle, Units 1 & 2 - Annual Radioactive Effluent Release Report for 2006 NL-07-0778, Submittal of Annual Radioactive Effluent Release Reports for 20062007-04-30030 April 2007 Submittal of Annual Radioactive Effluent Release Reports for 2006 ML0712204702007-04-30030 April 2007 Enclosure 2, Joseph M. Farley, Units 1 & 2 - Annual Radioactive Effluent Release Reports for 2006 NL-06-2513, E. I. Hatch, J. M. Farley, Vogtle, 10 CFR 50.46 ECCS Evaluation Model Annual Reports for 20052006-12-14014 December 2006 E. I. Hatch, J. M. Farley, Vogtle, 10 CFR 50.46 ECCS Evaluation Model Annual Reports for 2005 ML0612901482006-04-26026 April 2006 Annual Submission Reports NL-05-1551, 10 CFR 50.46 Annual ECCS Evaluation Model Report for 2004 and Significant Error Report2005-09-0707 September 2005 10 CFR 50.46 Annual ECCS Evaluation Model Report for 2004 and Significant Error Report NL-05-1050, and Vogtle Electric Generating Plant 10 CFR 50.46 ECCS Evaluation Model Annual Reports for 20042005-06-25025 June 2005 and Vogtle Electric Generating Plant 10 CFR 50.46 ECCS Evaluation Model Annual Reports for 2004 NL-05-0761, Annual Non-Radiological Environmental Operating Reports for 20042005-04-25025 April 2005 Annual Non-Radiological Environmental Operating Reports for 2004 ML0414001392004-05-14014 May 2004 Annual Radiological Environmental Operating Report for 2003 2023-04-25
[Table view] Category:Letter type:NL
MONTHYEARNL-24-0014, Revised Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical.2024-01-30030 January 2024 Revised Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical. NL-24-0031, Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 2R232024-01-29029 January 2024 Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 2R23 NL-24-0020, Plan, Unit 1 Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report2024-01-22022 January 2024 Plan, Unit 1 Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report NL-23-0926, Correction of Technical Specification Typographical Error2024-01-12012 January 2024 Correction of Technical Specification Typographical Error NL-24-0011, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2024-01-11011 January 2024 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis NL-23-0901, 30-Day 10 CFR 21 Notification - Framatome Supplied Siemens Medium Voltage (Mv) Circuit Breakers2023-12-15015 December 2023 30-Day 10 CFR 21 Notification - Framatome Supplied Siemens Medium Voltage (Mv) Circuit Breakers NL-23-0908, Cycle 30 Core Operating Limits Report2023-12-13013 December 2023 Cycle 30 Core Operating Limits Report NL-23-0889, Units 1 and 2 - License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water (RHRSW) and Plant Service Water (Psw) Systems2023-12-0606 December 2023 Units 1 and 2 - License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water (RHRSW) and Plant Service Water (Psw) Systems NL-23-0879, Request for Exemption from Security Event Notification Implementation2023-11-29029 November 2023 Request for Exemption from Security Event Notification Implementation NL-23-0877, Request for Exemption from Security Event Notification Implementation2023-11-29029 November 2023 Request for Exemption from Security Event Notification Implementation NL-23-0878, Request for Exemption from Security Event Notification Implementation2023-11-29029 November 2023 Request for Exemption from Security Event Notification Implementation NL-23-0841, Update to Notice of Intent to Pursue Subsequent License Renewal2023-11-20020 November 2023 Update to Notice of Intent to Pursue Subsequent License Renewal NL-23-0827, Response to Requests for Additional Information for a License Amendment Request and a Proposed Alternative Related to TS 3.4.142023-11-17017 November 2023 Response to Requests for Additional Information for a License Amendment Request and a Proposed Alternative Related to TS 3.4.14 NL-23-0825, Reply to Notice of Violation EA-23-080 and Readiness for 95001 Inspection2023-11-14014 November 2023 Reply to Notice of Violation EA-23-080 and Readiness for 95001 Inspection NL-23-0750, Response to Second Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the Colr2023-10-0404 October 2023 Response to Second Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the Colr NL-23-0745, Refueling Outage 1R24 Steam Generator Tube Inspection Report2023-09-22022 September 2023 Refueling Outage 1R24 Steam Generator Tube Inspection Report NL-23-0739, Response to NRC Inspection Report and Preliminary White Finding2023-09-0808 September 2023 Response to NRC Inspection Report and Preliminary White Finding NL-23-0695, Response to Round 2 Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters Operating, Completion Time Extension (LAR-22-002S2)2023-08-31031 August 2023 Response to Round 2 Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters Operating, Completion Time Extension (LAR-22-002S2) NL-23-0666, License Amendment Request: Remove Combined License Appendix C (LAR 23-008)2023-08-28028 August 2023 License Amendment Request: Remove Combined License Appendix C (LAR 23-008) NL-23-0713, Response to Request for Additional Information Regarding Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit2023-08-23023 August 2023 Response to Request for Additional Information Regarding Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit NL-23-0716, Response to Request for Additional Information Regarding Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit2023-08-23023 August 2023 Response to Request for Additional Information Regarding Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit NL-23-0704, Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit2023-08-22022 August 2023 Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit NL-23-0658, Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal2023-08-11011 August 2023 Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal NL-23-0670, Response to Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the COLR Consistent with WCAP-144832023-08-11011 August 2023 Response to Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the COLR Consistent with WCAP-14483 NL-23-0672, Licensee Guarantees of Payment of Deferred Premiums2023-08-10010 August 2023 Licensee Guarantees of Payment of Deferred Premiums NL-23-0542, CFR 50.46 ECCS Evaluation Model Annual Report for 20222023-08-0909 August 2023 CFR 50.46 ECCS Evaluation Model Annual Report for 2022 NL-23-0624, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2023-08-0404 August 2023 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis NL-23-0628, Readiness for Supplemental Inspection EA-22-1012023-07-26026 July 2023 Readiness for Supplemental Inspection EA-22-101 NL-23-0611, Core Operating Limits Report, Cycle 11 Version 12023-07-19019 July 2023 Core Operating Limits Report, Cycle 11 Version 1 NL-23-0566, ISFSI and Edwin I. Hatch Nuclear Plant ISFSI - Registration of Spent Fuel Cask Use2023-07-13013 July 2023 ISFSI and Edwin I. Hatch Nuclear Plant ISFSI - Registration of Spent Fuel Cask Use NL-23-0584, Preservice Inspection Program Owner'S Activity Report2023-07-10010 July 2023 Preservice Inspection Program Owner'S Activity Report NL-23-0555, Request for Exemption from Physical Barrier Requirement2023-07-0707 July 2023 Request for Exemption from Physical Barrier Requirement NL-23-0506, to Non-Voluntary License Amendment Request: Technical Specification Revision to Adopt WCAP-17661-P-A, Improved RAOC and CAOC Fq Surveillance Technical Specifications2023-07-0505 July 2023 to Non-Voluntary License Amendment Request: Technical Specification Revision to Adopt WCAP-17661-P-A, Improved RAOC and CAOC Fq Surveillance Technical Specifications NL-23-0541, Inservice Inspection Program Owners Activity Report for Outage 1R242023-06-28028 June 2023 Inservice Inspection Program Owners Activity Report for Outage 1R24 NL-23-0444, Quality Assurance Topical Report Submittal2023-06-15015 June 2023 Quality Assurance Topical Report Submittal NL-23-0339, Response to Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters - Operating, Completion Time Extension (LAR-22-002S1)2023-06-13013 June 2023 Response to Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters - Operating, Completion Time Extension (LAR-22-002S1) NL-23-0455, Report of 10 CFR 50.59 Changes, Tests, and Experiments and 10 CFR 52 Appendix D Departure Report2023-06-12012 June 2023 Report of 10 CFR 50.59 Changes, Tests, and Experiments and 10 CFR 52 Appendix D Departure Report NL-23-0457, ISFSI, and Edwin I. Hatch Nuclear Plant, ISFSI - Registration of Spent Fuel Cask Use2023-06-12012 June 2023 ISFSI, and Edwin I. Hatch Nuclear Plant, ISFSI - Registration of Spent Fuel Cask Use NL-23-0467, Response to Request for Additional Information Regarding License Amendment Request: Timing of Unit 4 Technical Specifications Effectiveness Prior to Initial Criticality (LAR-23-005S1)2023-06-0909 June 2023 Response to Request for Additional Information Regarding License Amendment Request: Timing of Unit 4 Technical Specifications Effectiveness Prior to Initial Criticality (LAR-23-005S1) NL-23-0449, National Pollutant Discharge Elimination System (NPDES) Permit Renewal Application2023-06-0202 June 2023 National Pollutant Discharge Elimination System (NPDES) Permit Renewal Application NL-23-0422, Inservice Inspection Program Owner'S Activity Report for Refueling Outage 2R272023-05-30030 May 2023 Inservice Inspection Program Owner'S Activity Report for Refueling Outage 2R27 NL-23-0346, License Amendment Request for Exception to Regulatory Guide 1.163 (LAR 23-007)2023-05-25025 May 2023 License Amendment Request for Exception to Regulatory Guide 1.163 (LAR 23-007) NL-23-0383, SNC Response to Regulatory Issue Summary 2023-01:Preparation And.2023-05-19019 May 2023 SNC Response to Regulatory Issue Summary 2023-01:Preparation And. NL-23-0385, License Amendment Request: More Restrictive Action for Technical Specification 3.1.9 (LAR-23-006R1)2023-05-17017 May 2023 License Amendment Request: More Restrictive Action for Technical Specification 3.1.9 (LAR-23-006R1) NL-23-0398, Withdrawal of Request of License Amendment Request Regarding More Restrictive Action for Technical Specification 3.1.9 (LAR-23-006)2023-05-16016 May 2023 Withdrawal of Request of License Amendment Request Regarding More Restrictive Action for Technical Specification 3.1.9 (LAR-23-006) NL-23-0372, Units 1 & 2, Joseph M. Farley Nuclear Plant - Units 1 & 2, Vogtle Electric Generating Plant - Units 1 & 2, Annual Radiological Environmental Operating Reports for 20222023-05-10010 May 2023 Units 1 & 2, Joseph M. Farley Nuclear Plant - Units 1 & 2, Vogtle Electric Generating Plant - Units 1 & 2, Annual Radiological Environmental Operating Reports for 2022 NL-23-0337, Response to Request for Additional Information Related to License Amendment Request to Revise the Frequency of Surveillance Requirement 3.6.3.52023-05-0505 May 2023 Response to Request for Additional Information Related to License Amendment Request to Revise the Frequency of Surveillance Requirement 3.6.3.5 NL-23-0360, Supplement to License Amendment Request and Exemptions to Allow Use of Lead Test Assemblies for Accident-Tolerant Fuel2023-05-0505 May 2023 Supplement to License Amendment Request and Exemptions to Allow Use of Lead Test Assemblies for Accident-Tolerant Fuel NL-23-0326, Response to Apparent Violation in NRC Inspection Report 05000424, 425/2023090; EA-22-1082023-05-0101 May 2023 Response to Apparent Violation in NRC Inspection Report 05000424, 425/2023090; EA-22-108 NL-23-0217, License Amendment Request to Revise Technical Specification Surveillance Requirement 3.4.14.1 and Proposed Inservice Testing Alternative ALT-VR-022023-05-0101 May 2023 License Amendment Request to Revise Technical Specification Surveillance Requirement 3.4.14.1 and Proposed Inservice Testing Alternative ALT-VR-02 2024-01-30
[Table view] |
Text
.4. Southern Nuclear Cheryl A. Gayheart Regulatory Affatrs Dtrector 3535 Colonnade Parkway Btrmtngham AL 35243 205 992 5316 tel 205 992 7795 fax cagayhea@southernco com JUN 0 5 2019 Docket Nos. : 50-321 50-348 50-424 NL-19-0650 50-366 50-364 50-425 U. S. Nuclear Regulatory Commission ATIN : Document Control Desk Washington , D. C. 20555-0001 Edwin I. Hatch Nuclear Plant Units 1 and 2 Joseph M. Farley Nuclear Plant Units 1 and 2 Vogtle Electric Generating Plant Units 1 and 2 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2018 Ladies and Gentlemen:
Southern Nuclear Operating Company (SNC) is the licensed operator for the Edwin I. Hatch Nuclear Plant (Hatch) Units 1 & 2, the Joseph M. Farley Nuclear Plant (Farley) Units 1 and 2, and the Vogtle Electric Generating Plant (Vogtle), Units 1 and 2. The requirements of 10 CFR 50.46(a)(3)(ii) include an annual report by licensees of changes to, or errors in, acceptable emergency core cooling system (ECCS) models that affect the temperature calculation and the estimated effect of changes or errors on the limiting ECCS analysis. Accordingly, the reports required by 10 CFR 50.46(a)(3)(ii) for Hatch, Farley and Vogtle are provided in Enclosures 1, 2 ,
and 3. The resulting peak cladding temperature (PCT) for Hatch, Farley and Vogtle continue to meet the criterion of 10 CFR 50.46(b)(1) (i.e.,~ 2200°F).
This letter contains no NRC commitments. If you have any questions, please contact Jamie Coleman at 205.992.6611 .
Respectfully submitted, Regulatory Affairs Director CAGffLE/scm
U.S. Nuclear Regulatory Commission NL-19-0650 Page 2
Enclosures:
- 1. Edwin I. Hatch Nuclear Plant Units 1 and 2 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2018
- 2. Joseph M. Farley Nuclear Plant Units 1 and 2 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2018
- 3. Vogtle Electric Generating Plant Units 1 and 2 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2018 cc: Regional Administrator, Region II NRR Project Manager- Farley, Hatch, Vogtle 1 & 2 Senior Resident Inspector- Farley, Hatch, Vogtle 1 & 2 NRR Project Manager- Farley, Hatch, Vogtle 1 & 2 RType: Farley=CFA04.054, Hatch=CHA02.004, Vogtle=CVC7000
Edwin I. Hatch Nuclear Plant Units 1 and 2 Joseph M. Farley Nuclear Plant Units 1 and 2 Vogtle Electric Generating Plant Units 1 and 2 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2018 Enclosure 1 Edwin I. Hatch Nuclear Plant Units 1 and 2 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2018 to NL-19-0650 Edwin I. Hatch Nuclear Plant Units 1 and 2 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2018 Edwin I. Hatch Nuclear Plant Unit 1 Table 1-1a- SAFERIGESTR-LOCA Summary of Changes I Errors (2018) (GE14)
Estimated Description Effect (t.\ PCT, °F)
None affecting PCT. 0 Table 1-1b- SAFERIPRIME-LOCA Summary of Changes I Errors (2018) (GNF2)
Estimated Description Effect (t.\ PCT, °F)
None affecting PCT. 0 Table 1-1c- Cumulative Impact of Changes I Errors GE14 GNF2 Description t.\IPCTI t.\IPCTI (oF) (oF)
Changes/Errors Previously Reported (Reference 1) 0 0 Summary of Changes/Errors (2018) (Reference 2) 0 0 Cumulative 0 0 Total E1-1 to NL-19-0650 Edwin I. Hatch Nuclear Plant Units 1 and 2 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2018 Edwin I. Hatch Nuclear Plant Unit 2 Table 1-2a- SAFERIGESTR-LOCA Summary of Changes I Errors (2018) (GE14)
Estimated Description Effect (A PCT, °F)
None affecting PCT. 0 Table 1-2b- SAFERIPRIME-LOCA Summary of Changes I Errors (2018) (GNF2)
Estimated Description Effect (A PCT, °F)
None affecting PCT. 0 Table 1-2c- SAFERIPRIME-LOCA Summary of Changes I Errors (2018) (GNF3 LUAs)
Estimated Description Effect (A PCT, °F)
None affecting PCT. 0 E1-2 to NL-19-0650 Edwin I. Hatch Nuclear Plant Units 1 and 2 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2018 Table 1-2d- Cumulative Impact of Changes I Errors GNF3 GE14 GNF2 (LUAs)
Description iliPCTI iliPCTI (oF) (oF) iliPCTI (oF)1 Changes/Errors Previously Reported (Reference 1) 0 0 0 Summary of Changes/Errors (2018) (Reference 3) 0 0 0 Cumulative 0 0 0 Total 1 GNF3 lead-use assemblies (LUAs) have a PCT 50 degrees greater than GNF2 assemblies.
References:
- 1. Letter from Cheryl A. Gayheart to USNRC (NL-18-0539), ML18134A282, "Edwin I. Hatch Nuclear Plant Units 1 and 2, Joseph M. Farley Nuclear Plant Units 1 and 2, Vogtle Electric Generating Plant Units 1 and 2, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2017," dated May 14, 2018
- 2. Global Nuclear Fuel 004N0711 , "Supplemental Reload Licensing Report for Hatch 1 Reload 28 Cycle 29," Revision 0, dated November 2017
- 3. Global Nuclear Fuel 002N6847, "Supplemental Reload Licensing Report for Hatch 2 Reload 24 Cycle 25," Revision 1, dated November 2016 E1-3
Edwin I. Hatch Nuclear Plant Units 1 and 2 Joseph M. Farley Nuclear Plant Units 1 and 2 Vogtle Electric Generating Plant Units 1 and 2 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2018 Enclosure 2 Joseph M. Farley Nuclear Plant Units 1 and 2 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2018 to NL-19-0650 Joseph M. Farley Nuclear Plant Units 1 and 2 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2018 Joseph M. Farley Nuclear Plant- Unit 1 ASTRUM Best Estimate Large Break LOCA Evaluation Table 1-1a- Summary of Changes/Errors (2018)
Estimated Description Effect (d PCT °F)
None affecting PCT. 0 Table 1-1 b- Cumulative Impact of Changes/Errors d!PCTI Description (oF)
Changes/Errors Previously Reported (Reference 1) 0 Summary of Changes/Errors (2018) (Reference 2) 0 Cumulative Total 0 E2-1 to NL-19-0650 Joseph M. Farley Nuclear Plant Units 1 and 2 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2018 Joseph M. Farley Nuclear Plant- Unit 1 NOTRUMP Appendix K Small Break LOCA Evaluation Table 1-1c- Summary of Changes/Errors (2018)
Estimated Description Effect
(~ PCT °F)
None affecting PCT. 0 Table 1-1d- Cumulative Impact of Changes/Errors
~IPCTI Description (oF)
Changes/Errors Previously Reported (Reference 1) 0 Summary of Changes/Errors (2018) (Reference 2) 0 Cumulative Total 0 E2-2 to NL-19-0650 Joseph M. Farley Nuclear Plant Units 1 and 2 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2018 Joseph M. Farley Nuclear Plant- Unit 2 ASTRUM Best Estimate Large Break LOCA Evaluation Table 1-2a- Summary of Changes/Errors (2018)
Estimated Description Effect
(~ PCT °F)
None affecting PCT. 0 Table 1-2b- Cumulative Impact of Changes/Errors
~IPCTI Description (oF)
Changes/Errors Previously Reported (Reference 1) 0 Summary of Changes/Errors (2018) (Reference 2) 0 Cumulative Total 0 E2-3 to NL-19-0650 Joseph M. Farley Nuclear Plant Units 1 and 2 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2018 Joseph M. Farley Nuclear Plant- Unit 2 NOTRUMP Appendix K Small Break LOCA Evaluation Table 1-2c- Summary of Changes/Errors (2018)
Estimated Description Effect
(/1 PCT °F)
None affecting PCT. 0 Table 1-2d- Cumulative Impact of Changes/Errors 11IPCTI Description (oF)
Changes/Errors Previously Reported (Reference 1) 0 Summary of Changes/Errors (2018) (Reference 2) 0 Cumulative Total 0
References:
- 1. Letter from Cheryl A. Gayheart to USNRC (NL-18-0539), ML18134A282, "Edwin I. Hatch Nuclear Plant Units 1 and 2, Joseph M. Farley Nuclear Plant Units 1 and 2, Vogtle Electric Generating Plant Units 1 and 2, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2017," dated May 14, 2018
- 2. Westinghouse Letter LTR-LIS-19-13, "J. M. Farley Units 1 and 2, 10 CFR 50.46 Annual Notification and Reporting for 2018," dated February 14, 2019 E2-4
Edwin I. Hatch Nuclear Plant Units 1 and 2 Joseph M. Farley Nuclear Plant Units 1 and 2 Vogtle Electric Generating Plant Units 1 and 2 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2018 Enclosure 3 Vogtle Electric Generating Plant Units 1 and 2 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2018 to NL-19-0650 Vogtle Electric Generating Plant Units 1 and 2 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2018 Vogtle Electric Generating Plant- Unit 1 BASH Large Break LOCA Evaluation Table 1-1a- Summary of Changes/Errors (2018)
Estimated Description Effect
(!\ PCT) (°F)
None affecting PCT 0 Table 1-1 b
- Cumulative Impact of Changes/Errors l\jPCTI Description (oF)
Changes/Errors Previously Reported (Reference 1) 29 Summary of Changes/Errors (2018) (Reference 2) 0 Cumulative Total 29 E3-1 to NL-19-0650 Vogtle Electric Generating Plant Units 1 and 2 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2018 Vogtle Electric Generating Plant- Unit 1 Appendix K Small Break LOCA Evaluation Table 1-1c- Summary of Changes/Errors (2018)
Estimated Description Effect
(~ PCT)
None affecting PCT. 0 Table 1-1d- Cumulative Impact of Changes/Errors
~ IPCTI Description (oF)
Changes/Errors Previously Reported (Reference 1) 0 Changes/Errors 2018 Calendar Year (Reference 2) 0 Cumulative Total 0 E3-2 to NL-19-0650 Vogtle Electric Generating Plant Units 1 and 2 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2018 Vogtle Electric Generating Plant- Unit 2 BASH Large Break LOCA Evaluation Table 1-2a- Summary of Changes/Errors (2018}
Estimated Description Effect
(~ PCT}
None affecting PCT. 0 Table 1-2b *Cumulative Impact of Changes/Errors
~ IPCTI Description (oF)
Changes/Errors Previously Reported (Reference 1) 29 Summary of Changes/Errors (2018) (Reference 2) 0 Cumulative Total 29 E3-3 to NL-19-0650 Vogtle Electric Generating Plant Units 1 and 2 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2018 Vogtle Electric Generating Plant- Unit 2 Appendix K Small Break LOCA Evaluation Table 1-2c- Summary of Changes/Errors (2018)
Estimated Description Effect
(~ PCT)
None affecting PCT. 0 Table 1-2d- Cumulative Impact of Changes/Errors
~ IPCTI Description (oF)
Changes/Errors Previously Reported (Reference 1) 0 Changes/Errors 2018 Calendar Year (Reference 2) 0 Cumulative Total 0
References:
- 1. Letter from Cheryl A. Gayheart to USNRC (NL-18-0539), ML18134A282, "Edwin I. Hatch Nuclear Plant Units 1 and 2, Joseph M. Farley Nuclear Plant Units 1 and 2, Vogtle Electric Generating Plant Units 1 and 2, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2017," dated May 14, 2018
- 2. Westinghouse Letter LTR-LIS-19-31, "A. W. Vogtle Units 1 and 2, 10 CFR 50.46 Annual Notification and Reporting for 2018," dated February 13, 2019 E3-4