NL-18-038, Browns Ferry, Units 1, 2, and 3, Request to Extend Enforcement Discretion Provided in Enforcement Guidance Memorandum 15-002 for Tornado-Generated Missile Protection Non-Conformances Identified in Response to Regulatory Issue Summary 2015-

From kanterella
Jump to navigation Jump to search
Browns Ferry, Units 1, 2, and 3, Request to Extend Enforcement Discretion Provided in Enforcement Guidance Memorandum 15-002 for Tornado-Generated Missile Protection Non-Conformances Identified in Response to Regulatory Issue Summary 2015-0
ML18068A731
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 03/09/2018
From: Shea J W
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
CNL-18-038, RIS-2015-06
Download: ML18068A731 (11)


Text

U.S. Nuclear Regulatory Commission CNL-18-038 Page 3 March 9, 2018 TVA requests NRC approval of this enforcement discretion date extension by June 9, 2018. There are no new regulatory commitments contained in this letter. If you have any question regarding this submittal , please contact Mike Oliver at (256) 729-7874. I declare under penalty of perjury that the foregoing is true and correct. Executed on the 9th day of March 2018. Respectfully ,

J. W. Shea Vice President , Nuclear Regulatory Affairs & Support Services

Enclosure:

cc (Enclosure)

Justification for Request to Extend the Expiration Date for Enforcement Discretion Regarding Tornado Missile Protection Requirements for the Browns Ferry Nuclear Plant NRC Regional Administrator

-Region II NRC Project Manager -Browns Ferry Nuclear Plant NRC Sen i or Resident Inspector

-Browns Ferry Nuclear Plant

--

---