B. Keith Taber Vice President Vogtle -Units 1 & 2 September 19, 2016 Southern Nuclear Operating Company, Inc.
7821 River Road Waynesboro, GA 30830 Tel 706.826.3151 Southern Nuclear Docket Nos.: 50-424 50-425 72-1039 NL-16-1662 ATTN: Document Control Desk Director, Division of Spent Fuel Storage and Transportation Office of Nuclear Material Safety and Safeguards U. S. Nuclear Regulatory Commission Washington, D. C. 20555-0001 Vogtle Electric Generating Plant - Units 1 and 2 Registration of Scent Fuel Casks Ladies and Gentlemen:
Southern Nuclear Operating Company (SNC) operates the Vogtle Electric Generating Plant (Vogtle) Independent Spent Fuel Storage Installation (ISFSI) in accordance with the general license provisions of 10 CFR 72.210. The requirements of 10 CFR 72.212(b)(2) include the registration of a spent fuel cask within 30 days of using a cask for the storage of spent nuclear fuel. Accordingly, SNC provides the following registration information for HI-STORM 100 spent fuel cask systems placed into storage in the Vogtle ISFSI during the past 30 days.
Cask Certificate:
Cask Model:
MPC Serial Number:
Overpack Serial Number:
Number of Fuel Bundles:
Placed in Service:
Cask Certificate:
Cask Model:
MPC Serial Number:
Overpack Serial Number:
Number of Fuel Bundles:
Placed in Service:
72-1014, Amendment 9R1 HI-STORM 100S, Version B 0364 218-861 32 August 27, 2016 72-1014, Amendment 9R1 HI-STORM 1 OOS, Version B 0365 218-862 32 September 8, 2016 This letter contains no NRC commitments. If you have any questions, please contact Ken McElroy at (205) 992-7369.
U.S. Nuclear Regulatory Commission NL-16-1662 Page2 Respectfully submitted, t~{}l B. Keith Taber Vice President Vogtle 1& 2 BKT/KCW cc:
Southern Nuclear Operating Company Mr. S. E. Kuczynski, Chairman, President & CEO Mr. D. G. Bost, Executive Vice President & Chief Nuclear Officer Mr. D. R. Madison, Vice President-Fleet Operations Mr. M.D. Meier, Vice President-Regulatory Affairs Mr. B. K. Taber, Vice President-Vogtle 1 & 2 Mr. B. J. Adams, Vice President-Engineering Mr. D. D. Sutton, Regulatory Affairs Manager-Vogtle 1 & 2 RType: CVC7000 U. S. Nuclear Regulatory Commission Ms. C. Haney, Regional Administrator Mr. R. E. Martin, NRR Senior Project Manager-Vogtle 1 & 2 Ms. N. R. Childs, Senior Resident Inspector - Vogtle 1 & 2 Mr. R. P. Carrion, Senior Reactor Inspector, Region II