Mark J. Ailuni, P.E.

Southern Nuclear Nuclear Licensing Director Operating Company, Inc.

40 Inverness Center Parkway Post Office Box 1295 Birmingham, Alabama 35201 Tel 205.992.7673 Fax 205.992.7885 March 1, 2011 SOUTHERN'\\

COMPANY Docket No.:

50-321 NL-11-0317 Mr. Victor McCree U. S. Nuclear Regulatory Commission, Region II Marquis One Tower 245 Peachtree Center Avenue N.E., Suite 1200 Atlanta, GA 30303 Edwin I. Hatch Nuclear Plant - Unit 1 Request for Earlier Date for Unit 1 IP 71003 Phase 1 Inspection Ladies and Gentlemen:

NRC inspection procedure (IP) 71003, "Post-Approval Site Inspection for License Renewal" states in part that portions of the inspection program may be performed during the unit outage preceding the extended operation date (these activities are commonly referred to as the IP 73001 phase 1 inspection). For Edwin I. Hatch Nuclear Plant (HNP) Unit 1, the outage preceding the extended operation date is 1 R26 in the spring of 2014, and HNP Unit 1 enters the period of extended operation on August 7,2014. Southern Nuclear Operating Company (SNC) requests that the phase 1 IP 71003 inspection for HNP Unit 1 be scheduled for 1 R25 in February 2012. This revised inspection schedule will allow any follow-up inspections to be performed before HNP Unit 1 enters the extended period of operation. All outage one-time license renewal inspections for HNP Unit 1 are planned for the 'I R25 outage, so the staff's best opportunity to observe these inspections will be during that outage. In order to be ready for the phase 1 portion of the IP 71003 inspection, SNC intends to have implemented those license renewal commitments necessary to support the phase 1 portion of the inspection.

This letter contains no NRC commitments. If you have any questions, please advise.

Respectfully submitted,

~ ~ Of-:

M. J. Ajluni Nuclear Licensing Director MJAlJEH/ega

U. S. Nuclear Regulatory Commission NL-11-0317 Page 2 cc:

Southern Nuclear Operating Company Mr. J. T. Gasser, Executive Vice President Mr. D. R. Madison, Vice President - Hatch Ms. P. M. Marino, Vice President - Engineering RTYPE: CHA02.004 U. S. Nuclear Regulatory Commission Mr. Louis F. Lake, NRC Region II Mr. Joel E. Rivera-Ortiz, NRC Region II Mr. P. G. Boyle, NRR Project Manager - Hatch Mr. E. D. Morris, Senior Resident Inspector - Hatch Document Control Desk