David H. Jones Southern Nuclear Vice President Operating Company, Inc.

Engineering 40 Inverness Center Parkway Birmingham. Alabama 35242 Tel 205.992.5984 Fax 205.992.0341 May 13, 2008 SOUTHE~

COMPANY Energy to Serve }'ourWorU SN Docket Nos.: 50-348 NL-08-0513 50-364 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Joseph M. Farley Nuclear Plant - Units 1 and 2 Notification of Intent to Utilize Later Code Version Ladies and Gentlemen:

Recently. Southern Nuclear Operating Company (SNC) compared the existing Technical Requirements Manual (TRM) snubber programs for Farley Nuclear Plant (FNP) to the option included in 10 CFR 50.55a(b)(3)(v) dated January 1.

2007. This comparison resulted in a decision to adopt the ASME OM Code, Subsection ISTD, for snubber examinations and testing. SNC recognizes that inservice examinations must be performed using the VT-3 visual examination method described in the American Society of Mechanical Engineers (ASME)

Section XI Code, paragraph IWA-2213.

The current version of 10 CFR 50.55a endorses the ASME OM Code. 2001 Edition with Addenda through 2003. Therefore. SNC will amend FNP TRMs to reference this Code version for snubber examinations and testing prior to the Unit 2 R19 (Fall 2008) and Unit 1 R22 (Spring 2009) Refueling Outages. Additionally, SNC will also utilize ASME OM Code Case OMN-13, Revision 0, which was approved by the NRC in Regulatory Guide 1.192. dated June, 2003.

This letter serves only as notification of SNC's intent to utilize the ASME OM Code, 2001 Edition with Addenda through 2003, Subsection ISTD and Code Case OMN-13, Revision 0, which have both been previously endorsed by the NRC. Therefore. additional NRC approval is not required. This letter also notifies the NRC that there will no longer be a need for existing Inservice Inspection Program Request for Relief RR-12 for either FNP Unit; therefore, it is being withdrawn.

U. S. Nuclear Regulatory Commission NL-08-0513 Page 2 This letter contains no NRC commitments. If you have any questions, please advise.

D. H. Jon s Vice Presi ent - Engineering DHJ/BDM/daj cc:

Southern Nuclear Operating Company Mr. J. T. Gasser, Executive Vice President Mr. J. R. Johnson, Vice President - Farley RTYPE: CFA04.054; LC#14742 U. S. Nuclear Regulatory Commission Mr. V. M. McCree, Acting Regional Administrator Mr. R. A. Jervey, NRR Project Manager - Farley Mr. E. L. Crowe, Senior Resident Inspector - Farley