Qualification to Perform Dynamic Rod Worth Measurement Calculations
ML040710453
Person / Time
Site: Vogtle, Farley  
Issue date: 03/08/2004
From: Gasser J
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NL-04-0256 WCAP-13360P-A, Rev 1
Download: ML040710453 (2)


Text

JeffreyT. Gasser Southern Nuclear Vice President Operating Company, Inc.

40 Inverness Center Parkway Post Office Box 1295 Birmingham. Alabama 35201 Tel 205.992.7721 Fax 205.992.0403 S

SOUTHERN March 8, 2004 COMPANY Energy to Serve Your WorldM Docket Nos.:

50-348 50-424 NL-04-0256 50-364 50-425 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Joseph M. Farley Nuclear Plant, Units 1 and 2 Vogtle Electric Generating Plant, Units 1 and 2 Qualification to Perform Dynamic Rod Worth Measurement Calculations Ladies and Gentlemen:

Westinghouse topical report WCAP-13360-P-A, Revision 1, "Westinghouse Dynamic Rod Worth Measurement Technique," contains a description of the technique along with the documentation of the NRC's review and approval. On page 3 of the NRC's Safety Evaluation Report (SER), dated July 30, 1998, the NRC addressed transfer of the technology from Westinghouse to licensees. To address technology transfer, Westinghouse transmitted two letters to the NRC (References 6 and 7 in the SER) detailing five criteria that must be met by licensees in order to be qualified to perform the Dynamic Rod Worth Measurement (DRWM) calculations. These letters are included in Attachment F of WCAP-13360-P-A, Revision 1.

The five criteria are:

1. Eligibility of codes for DRWM calculations,
2. Application of procedures to DRWM computations,
3. Training and qualification of utility personnel,
4. Comparison calculations for the DRWM technique, and
5. Quality Assurance and change control.

In accordance with the requirements of Reference 6 of the SER, Southern Nuclear Operating Company (SNC) is submitting this letter to the NRC as notification of compliance with the above-listed criteria. By satisfying these criteria, SNC has demonstrated its qualification to perform DRWM calculations. SNC plans its first application of the DRWM calculations under the technology transfer for the startup of Farley Unit 2 Cycle 17 and Vogtle Unit 2 Cycle 11 with scheduled refueling outages in Spring 2004.

7k10

U. S. Nuclear Regulatory Commission NL-04-0256 Page 2 This letter contains no NRC commitments. If you have any questions, please advise.

Sincereser JTG/RJF/sdl cc:

Southern Nuclear Operating Company Mr. J. B. Beasley, Jr., Executive Vice President Mr. L. M. Stinson, Vice President, Plant Farley Mr. D. E. Grissette, General Manager - Plant Farley Mr. W. F. Kitchens, General Manager - Plant Vogtle Document Services RTYPE: CFA04.054; CVC7000; LC#13954 U. S. Nuclear Regulatory Commission Mr. L. A. Reyes, Regional Administrator Mr. S. E. Peters, NRR Project Manager - Farley Mr. C. Gratton, NRR Project Manager - Vogtle Mr. C. A. Patterson, Senior Resident Inspector - Farley Mr. J. Zeiler, Senior Resident Inspector - Vogtle