Jeffrey I Gasser Vice President Southern Nuclear Operating Company, Inc.
40 Inverness Center Parkway Post Office Box 1295 Birmingham, Alabama 35201 Tel 205.992.7721 Fax 205.992.0403 SOUTHERN A COMPANY Energy to Serve Your World' NL-03-1501 July 10, 2003 Docket Nos.:
50424 50-425 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Vogtle Electric Generating Plant Monthly Operating Reports Ladies and Gentlemen:
Enclosed are the June 2003 Monthly Operating Reports as required by Section 5.6.4 of the Technical Specifications.
Sincerely, ey.
asser JTG/NJS
Enclosures:
E - VEGP Unit 1 Monthly Operating Report E2 - VEGP Unit 2 Monthly Operating Report cc:
Southern Nuclear Operating Company Mr. J. D. Woodard, Executive Vice President Mr. W. F. Kitchens, General Manager - Plant Vogtle Mr. M. Sheibani, Engineering Supervisor - Plant Vogtle Document Services RTYPE: CVC7000 U. S. Nuclear Regulatorv Commission Mr. L. A. Reyes, Regional Administrator Mr. F. Rinaldi, NRR Project Manager - Vogtle Mr. J. Zeiler, Senior Resident Inspector - Vogtle
,I 4
OPERATING DATA REPORT Docket No.:
Unit Name:
Date:
Completed By:
Telephone:
50424 VEGP UNIT 1 July 1,2003 Andrew R Cato (706) 826-3823 Operating Status
- 1. Reporting Period:
- 2. Design Electrical Rating (Net MWe):
- 3. Maximum Dependable Capacity (Net MWe):
June 2003 1169 1152 This Month Year-To-Date Cumulative
- 4. Number Of Hours Reactor Was Critical:
- 5. Hours Generator On Line:
- 6. Unit Reserve Shutdown Hours:
- 7. Net Electrical Energy Generated (MWHe):
720.0 720.0 0.0 840,578 4304.4 4292.3 0.0 5,025,975 126,477.0 124,915.5 0.0 140,110,799 CHALLENGES TO PRESSURIZER PORV AND PRESSURIZER SAFETY VALVES Date Tag No.
Event Description N/A N/A NA E1-1
UNIT SHUTDOWNS Docket No.:
Unit Name:
Date:
Completed By:
Telephone:
50424 VEGP UNIT I July 1, 2003 Andrew R. Cato (706) 826-3823 Reporting Period:
June 2003 Type Method of Cause/
F: Forced Duration Shutting Corrective Actions No.
Date (YYMMDD)
S: Scheduled (Hours)
Reason (1)
Down (2)
Comments N/A N/A N/A N/A N/A N/A N/A (1) REASON:
(2) METHOD:
A - Equipment Failure (Explain)
E - Operator Training/License Examination
- 1. Manual
- 4. Continuation B - Maintenance or Test F - Administrative
- 2. Manual Trip/Scram
- 5. Other C - Refueling G - Operational Error (Explain)
- 3. Automatic Trip/Scram D - Regulatory Restriction H - Other (Explain)
CAUSE/CORRECTIVE ACTION/COMMENTS:
EVENT CAUSE:
CORRECTIVE ACTION:
CRITICAL PATH WAS NARRATIVE REPORT June 01 00:00 Unit 1 at 100% power with no significant operating problems.
June 30 23:59 Unit 1 at 100% power with no significant operating problems.
E1-2
OPERATING DATA REPORT Docket No.:
Unit Name:
Date:
Completed By:
Telephone:
50-425 VEGP UNIT 2 July 1, 2003 Andrew R. Cato (706) 826-3823 Operating Status
- 1. Reporting Period:
- 2. Design Electrical Rating (Net MWe):
- 3. Maximum Dependable Capacity (Net MWe):
June 2003 1169 1149 This Month Year-To-Date Cumulative
- 4. Number Of Hours Reactor Was Critical:
- 5. Hours Generator On Line:
- 6. Unit Reserve Shutdown Hours:
- 7. Net Electrical Energy Generated (MWHe):
720.0 720.0 0.0 839,078 4305.7 4292.7 0.0 4,962,010 112,749.5 111,861.6 0.0 126,173,376 CHALLENGES TO PRESSURIZER PORV AND PRESSURIZER SAFETY VALVES Date Tag No.
Event Description N/A N/A N A E2-1
UNIT SHUTDOWNS Docket No.:
Unit Name:
Date:
Completed By:
Telephone:
50-425 VEGP UNIT 2 July 1, 2003 Andrew R. Cato (706) 826-3823 Reporting Period:
June 2003 Type Method of Cause/
F: Forced Duration Shutting Corrective Actions No.
Date (YYMMDD)
S: Scheduled (Hours)
Reason (1)
Down (2)
Comments N/A N/A N/A N/A NIA NIA N/A (1) REASON:
(2) METHOD:
A - Equipment Failure (Explain)
E - Operator Tralning/License Examination
- 1. Manual
- 4. Continuation B - Maintenance or Test F - Administrative
- 2. Manual Trip/Scram
- 5. Other C - Refueling G - Operational Error (Explain)
- 3. Automatic Trip/Scram D - Regulatory Restriction H - Other (Explain)
CAUSEICORRECTIVE ACTIONICOMMENTS:
EVENT CAUSE:
CORRECTIVE ACTION:
CRITICAL PATH WAS:
NARRATIVE REPORT June 01 00:00 Unit 2 at 100% power with no significant operating problems.
June 30 23:59 Unit 2 at 100% power with no significant operating problems.