NG-05-0011, December 2004 Monthly Operating Report for Duane Arnold Energy Center
| ML050250134 | |
| Person / Time | |
|---|---|
| Site: | Duane Arnold |
| Issue date: | 01/14/2005 |
| From: | Peifer M Nuclear Management Co |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| GL-97-002, NG-05-0011 | |
| Download: ML050250134 (3) | |
Text
Committed to Nuclear Excellene Duane Arnold Energy Center Operated by Nuclear Management Company, LLC January 14, 2005 NG-05-0011 TS 5.6.4 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Duane Arnold Energy Center Docket 50-331 License No. DPR-49 Monthly Operating Report Please find enclosed the Duane Arnold Energy Center (DAEC) Monthly Operating Report. The report has been prepared in accordance with the guidelines of NRC Generic Letter 97-02: "Revised Contents Of The Monthly Operating Report," and distribution has been made in accordance with DAEC Technical Specifications, Section 5.6.4.
This letter makes no new commitments or changes to any existing commitments.
ark A. e Site Vice President, Duane Arnold Energy Center
~Nuclear-Management Company, LLC
Enclosure:
(1)
CC Administrator, Region Ill, USNRC Project Manager, DAEC, USNRC Resident Inspector, DAEC, USNRC 1.
. .-. .. I . . . 1. "o 3277 DAEC Road
- Palo, Iowa 52324-9i85 I-Telephone: 319.851.7611
ENCLOSURE 1 MONTHLY OPERATING REPORT DOCKET NO. 50-331 UNIT NAME Duane Arnold DATE January 7, 2005 COMPLETED BY Mike Fairchild TELEPHONE (319) 851-7642 REPORTING December 2004 PERIOD:
- 1. Design Electrical Raing(Mw-e) .40- -581
- 2. Maximum Dependable Capacity 565.50 (MWe-Net)
This Month Yr-to-Date Cumulative
- 3. Number of Hours the Reactor was 744.00 8,633.90 210,312.17 Critical
- 4. Number of Hours Generator On-line 744.00 8,597.01 205,882.53
- 5. Reserve Shutdown Hours 0.00 0.00 192.80
- 6. Net Electrical Energy Generated 433,737.20 4,929,909.80 96,885,185.48 (MWHrs)
UNIT SHUTDOWNS Type Method F: Forced of Cause & Corrective S: Duration Shuttinq Action No. Date Scheduled (Hours) Reason 1 Down Comments
'Reason: 2 Metl hod:
A Equipment Failure (Explain) I rMlanual B Maintenance or Test 2 fManual Trip/Scram C Refueling 3 JAutomatic Trip/Scram D Regulatory Restriction 4 (Continuation E Operator Training & License Examination 5 C)ther (Explain)
F Administration G Operational Error (Explain)
H Other (Explain)
Page 1 of 2
NARRATIVE
SUMMARY
The only power reductions during the month were for load line adjustments on December 4, 13 and 21, and a control rod sequence exchange on December 11.
Page 2 of 2
Text
Committed to Nuclear Excellene Duane Arnold Energy Center Operated by Nuclear Management Company, LLC January 14, 2005 NG-05-0011 TS 5.6.4 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Duane Arnold Energy Center Docket 50-331 License No. DPR-49 Monthly Operating Report Please find enclosed the Duane Arnold Energy Center (DAEC) Monthly Operating Report. The report has been prepared in accordance with the guidelines of NRC Generic Letter 97-02: "Revised Contents Of The Monthly Operating Report," and distribution has been made in accordance with DAEC Technical Specifications, Section 5.6.4.
This letter makes no new commitments or changes to any existing commitments.
ark A. e Site Vice President, Duane Arnold Energy Center
~Nuclear-Management Company, LLC
Enclosure:
(1)
CC Administrator, Region Ill, USNRC Project Manager, DAEC, USNRC Resident Inspector, DAEC, USNRC 1.
. .-. .. I . . . 1. "o 3277 DAEC Road
- Palo, Iowa 52324-9i85 I-Telephone: 319.851.7611
ENCLOSURE 1 MONTHLY OPERATING REPORT DOCKET NO. 50-331 UNIT NAME Duane Arnold DATE January 7, 2005 COMPLETED BY Mike Fairchild TELEPHONE (319) 851-7642 REPORTING December 2004 PERIOD:
- 1. Design Electrical Raing(Mw-e) .40- -581
- 2. Maximum Dependable Capacity 565.50 (MWe-Net)
This Month Yr-to-Date Cumulative
- 3. Number of Hours the Reactor was 744.00 8,633.90 210,312.17 Critical
- 4. Number of Hours Generator On-line 744.00 8,597.01 205,882.53
- 5. Reserve Shutdown Hours 0.00 0.00 192.80
- 6. Net Electrical Energy Generated 433,737.20 4,929,909.80 96,885,185.48 (MWHrs)
UNIT SHUTDOWNS Type Method F: Forced of Cause & Corrective S: Duration Shuttinq Action No. Date Scheduled (Hours) Reason 1 Down Comments
'Reason: 2 Metl hod:
A Equipment Failure (Explain) I rMlanual B Maintenance or Test 2 fManual Trip/Scram C Refueling 3 JAutomatic Trip/Scram D Regulatory Restriction 4 (Continuation E Operator Training & License Examination 5 C)ther (Explain)
F Administration G Operational Error (Explain)
H Other (Explain)
Page 1 of 2
NARRATIVE
SUMMARY
The only power reductions during the month were for load line adjustments on December 4, 13 and 21, and a control rod sequence exchange on December 11.
Page 2 of 2