NG-04-0627, September 2004 Monthly Operating Report for Duane Arnold

From kanterella
Jump to navigation Jump to search
September 2004 Monthly Operating Report for Duane Arnold
ML042950486
Person / Time
Site: Duane Arnold NextEra Energy icon.png
Issue date: 10/13/2004
From: Peifer M
Nuclear Management Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NG-04-0627, TS 5.6.4
Download: ML042950486 (3)


Text

CNu

]

Committed to Nuclear Excellene Duane Arnold Energy Center Operated by Nuclear Management Company, LLC October 13, 2004 NG-04-0627 TS 5.6.4 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Duane Arnold Energy Center Docket 50-331 License No. DPR-49 Monthly Operating Report Please find enclosed the Duane Arnold Energy Center (DAEC) Monthly Operating Report. The report has been prepared in accordance with the guidelines of NRC Generic Letter 97-02: "Revised Contents Of The Monthly Operating Report," and distribution has been made in accordance with DAEC Technical Specifications, Section 5.6.4.

This letter makes no new commitments or changes to any existing commitments.

arkA ifer Site Vice President, Duane Arnold Energy Center Nuclear Management Company, LLC

Enclosure:

(1)

CC Administrator, Region IIl, USNRC Project Manager, DAEC, USNRC Resident Inspector, DAEC, USNRC 3277 DAEC Road

  • Palo, Iowa 52324-9785 Telephone: 319.851.7611

,,' ,-7 Z,,(f L-,e

Z.

ENCLOSURE 1 MONTHLY OPERATING REPORT DOCKET NO.

UNIT NAME DATE COMPLETED BY TELEPHONE REPORTING PERIOD:

50-331 Duane Arnold October 4, 2004 Mike Fairchild (319) 851-7642 September 2004

1. Design Electrical Rating (MWe)
2. MaximuiimDependable Capacity (MWe-Net) 581.40 565.50
3. Number of Hours the Reactor was Critical
4. Number of Hours Generator On-line
5. Reserve Shutdown Hours
6. Net Electrical Energy Generated (MWHrs)

This Month 720.00 720.00 0.00 410.790.00 Yr-to-Date 6,503.57 6.481.23 0.00 3.731.652.00 Cumulative 208,181.84 203,766.75 192.80 95.686,927.68 UNIT SHUTDOWNS Type Method F: Forced of Cause & Corrective S:

Duration Shuttin

~

Action No.

Date Scheduled

{ours)

Reason 1 Dow Comments There were no shutdowns in

. September.

'Reason:

A Equipment Failure (Explain)

B Maintenance or Test C

Refueling D

Regulatory Restriction E

Operator Training & License Examination F

Administration G

Operational Error (Explain)

H Other (Explain) 2Method:

1 Manual 2

Manual Trip/Scram 3

Automatic Trip/Scram 4

Continuation 5

Other (Explain)

Page 1 of 2

NARRATIVE

SUMMARY

During the month of September, departures from full power operation occurred for the following:

1.)

September 11-13, a sequence exchange.

2.)

September 16, a load line adjustment.

3.)

September 25, a load line adjustment.