ITAAC Closure Notification on Completion of ITAAC 2.2.03.01 (Index Number 158)
ML21295A721
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 10/22/2021
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
ND-20-1198
Download: ML21295A721 (6)


Text

3k. Southern Nuclear Michael J. Yox 7825 River Road Regulatory Affairs Director Waynesboro, GA 30830 Vogtle 3 & 4 706-848-6459 tel OCT 2 2 2021 Docket No.: 52-025 ND-20-1198 10CFR 52.99(c)(1)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 ITAAC Closure Notification on Completion of ITAAC 2.2.03.01 rindex Number 1581 Ladies and Gentlemen:

In accordance with 10 CFR 52.99(c)(1), the purpose of this letter is to notify the Nuclear Regulatory Commission (NRC) of the completion of Vogtle Electric Generating Plant(VEGP)

Unit 3 Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 2.2.03.01 [Index Number 158]. This ITAAC verified that the functional arrangement(FA) of the passive core cooling system (PXS) is as described in the Design Description of Combined License (COL)

Appendix C, Section 2.2.03.01. The closure process for this ITAAC is based on the guidance described in NEI-08-01, "Industry Guideline for the ITAAC Closure Process under 10 CFR Part 52", which is endorsed by the NRC in Regulatory Guide 1.215.

This letter contains no new NRC regulatory commitments. Southern Nuclear Operating Company(SNC) requests NRC staff confirmation of this determination and publication of the required notice in the Federal Register per 10 CFR 52.99.

If there are any questions, please contact Kelli A. Roberts at 706-848-6991.

Respectfully submitted.

Michael J. Yox Regulatory Affairs Dirdbtor Vogtle 3 & 4

Enclosure:

Vogtle Electric Generating Plant(VEGP) Unit 3 ITAAC Closure Notification on Completion of 2.2.03.01 [Index Number 158]

MJY/JRV/sfr

U.S. Nuclear Regulatory Commission ND-20-1198 Page 2 of 3 To:

Southern Nuclear Operating Company/ Georgia Power Company Mr. Peter P. Sena III Mr. D. L. McKinney Mr. H. Nieh Mr. G. Chick Mr. S. Stimac Mr. P. Martino Mr. M. J. Yox Mr. A. S. Parton Ms. K. A. Roberts Ms. J.M. Coleman Mr. C. T. Defnall Mr. C. E. Morrow Mr. K. J. Drudy Mr. J. M. Fisher Mr. R. L. Beiike Mr. S. Leighty Ms. A. C. Chamberlain Mr. J. C. Haswell Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc:

Nuclear Regulatory Commission Ms. M. Bailey Mr. M. King Mr. G. Bowman Ms. A. Veil M . C. P. Patel M . G. J. Khouri M . C. J. Even M B. J. Kemker Ms. N. C. Coovert M . C. Welch M J. Gaslevic M . O. Lopez-Santiago M G. Armstrong M M. Webb M T. Fredette M C. Santos M B. Davis M J. Vasquez M J. Eargle M E. Davidson M T. Fanelli Ms. K. McCurry M . J. Parent M B. Griman M V. Hall

U.S. Nuclear Regulatory Commission ND-20-1198 Page 3 of 3 Qqlethorpe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. 8. M. Jackson Dalton Utilities Mr. T. Bundros Westinahouse Electric Company. LLC Dr. L. Oriani Mr. D. 0. Durham Mr. M. M. Corletti Mr. Z. 8. Harper Mr. J. L. Coward Other Mr. 8. W. Kline, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., CDS Associates, Inc.

Mr. 8. Roetger, Georgia Public Service Commission Mr. R. L. Trokey, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Balch Bingham

U.S. Nuclear Regulatory Commission ND-20-1198 Enclosure Page 1 of 3 Southern Nuclear Operating Company ND-20-1ig8 Enclosure Vogtle Electric Generating Plant(VEGP) Unit 3 ITAAC Closure Notification on Completion of ITAAC 2.2.03.01 [Index Number 158]

U.S. Nuclear Regulatory Commission ND-20-1198 Enclosure Page 2 of 3 ITAAC Statement Design Commitment:

1. The functional arrangement of the PXS is as described in the Design Description of this Section 2.2.3.

Inspections. Tests. Analyses:

Inspection of the as-built system will be performed.

Acceptance Criteria:

The as-built PXS conforms with the functional arrangement as described in the Design Description of this Section 2.2.3.

ITAAC Determination Basis An inspection of the as-built passive core cooling system (PXS) was conducted after completion of construction to confirm that the functional arrangement of the PXS is as described in the Design Description of Combined License (COL) Appendix C, Section 2.2.3. This inspection encompassed the structures, systems, and components(SSCs) identified in the COL Appendix C, Section 2.2.3, Design Description, including those in Table 2.2.3-5 and Figure 2.2.3-1.

The inspection (walkdown) was completed in accordance with ND-RA-001-012, Functional and Physical Arrangement Scoping Process(Reference 1), which required the preparation of a detailed inspection plan. This inspection plan Included the use of detailed drawings such as Piping and Instrumentation Drawings (P&IDs) or Single Line Elementary Drawings to perform visual observations and compare the as-built system to the Design Description.

The inspection results are documented in the Unit 3 Principal Closure Document(Reference 2) supporting the Unit 3 ITAAC 2.2.03.01 Completion Package (Reference 3) and verified that the SSCs are physically arranged and located to perform the functions described in the Design Description and referenced table and figure. The inspection results confirm that the as-built PXS conforms with the functional arrangement as described in the COL Appendix C, Section 2.2.3 Design Description.

The Unit 3 Principal Closure Document(Reference 2) is available for NRC inspection as well as the Unit 3 ITAAC 2.2.03.01 Completion Package.

ITAAC Finding Review In accordance with plant procedures for ITAAC completion. Southern Nuclear Operating Company (SNC) performed a review of all ITAAC findings pertaining to the subject ITAAC and associated corrective actions. This review found that there are no relevant ITAAC findings associated with this ITAAC. The ITAAC completion review is documented in the ITAAC Completion Package for ITAAC 2.2.03.01 (Reference 3)and is available for NRC review.

U.S. Nuclear Regulatory Commission ND-20-1198 Enclosure Page 3 of 3 ITAAC Completion Statement Based on the above Information, SNO hereby notifies the NRG that ITAAC 2.2.03.01 was performed for VEGP Unit 3 and that the prescribed acceptance criteria are met.

Systems, structures, and components verified as part of this ITAAC are being maintained In their as-designed, ITAAC compliant condition In accordance with approved plant programs and procedures.

References(available for NRG inspection)

1. ND-RA-001-012, Version 6.0, Functional and Physical Arrangement Scoping Process
2. SV3-PXS-ITR-800158, Rev. 4, Unit 3 PXS Functional Arrangement Inspection: ITAAC 2.2.03.01 NRC Index Number 158
3. 2.2.03.01-U3-CP-RevO, ITAAC Completion Package