ITAAC Closure Notification on Completion of ITAAC C.2.6.09.02 (Index Number 659)
ML20224A159
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 08/11/2020
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
ND-20-0913
Download: ML20224A159 (6)


Text

Michael J. Yox 7825 River Road Southern Nuclear Regulatory Affairs Director Waynesboro, GA 30830 Vogtle 3 & 4 706-848-6459 tel AUG 1 1 2020 Docket Nos.: 52-025 ND-20-0913 10 CFR 52.99(c)(1)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 ITAAC Closure Notification on Completion of ITAAC C.2.6.09.02 [Index Number 6591 Ladies and Gentlemen; In accordance with 10 CFR 52.99(c)(1), the purpose of this letter is to notify the Nuclear Regulatory Commission (NRC) of the completion of Vogtle Electric Generating Plant(VEGP) Unit 3 Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item C.2.6.09.02 [Index Number 659]. This ITAAC confirms that the physical barriers at the perimeter of the protected area are separated from any other barrier designated as a vital area barrier. The closure process for this ITAAC is based on the guidance described in Nuclear Energy Institute (NEI) 08-01,"Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52," which was endorsed by the NRC in Regulatory Guide 1.215.

This letter contains no new NRC regulatory commitments. Southern Nuclear Operating Company (SNC) requests NRC staff confirmation of this determination and publication of the required notice in the Federal Register per 10 CFR 52.99.

If there are any questions, please contact Tom Petrak at 706-848-1575.

Respectfully submitted, 4

Michael J. Yox Regulatory Affairs Direqfor Vogtle 3 & 4

Enclosure:

Vogtle Electric Generating Plant(VEGP) Unit 3 Completion of ITAAC C.2.6.09.02 [Index Number 659]

MJY/RLB/sfr

U.S. Nuclear Regulatory Commission ND-20-0913 Page 2 of 3 To:

Southern Nuclear Operating Company/ Georgia Power Company Mr. Peter P. Sena III (w/o enclosures)

Mr. D. L. McKinney (w/o enclosures)

Mr. M. D. Meier (w/o enclosures)

Mr. G. Chick Mr. S. Stimac Mr. P. Martino Mr. M. J. Yox Mr. A. S. Parton Ms. K. A. Roberts Mr. T. G. Petrak Mr. C. T. Defnall Mr. C. E. Morrow Mr. R. L. Beiike Mr. S. Leighty Ms. A. C. Chamberlain Mr. J. C. Haswell Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc:

Nuclear Requlatorv Commission M . C. P. Patel M . G. J. Khouri Ms. S. E. Temple M . N. D. Karlovich M . A. Lerch M . C. J. Even M . 8. J. Kemker Ms. N. C. Coovert M C. Welch M J. Gaslevic M V. Hall M G. Armstrong M M. Webb M T. Fredette M S. Smith M C. Santos M s. M. Bailey M . S. Rose M . B. Davis M . J. Vasquez M . J. Eargle Ms. K. Carrington M . P. Heher M . M. King M . E. Davidson

U.S. Nuclear Regulatory Commission ND-20-0913 Page 3 of 3 Qqlethorpe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. 8. M. Jackson Dalton Utilities Mr. T. Bundros Westinqhouse Electric Company. LLC Dr. L. OrlanI (w/o enclosures)

Mr. D. 0. Durham (w/o enclosures)

Mr. M. M. CorlettI Mr. Z. 8. Harper Mr. J. L. Coward Other Mr. J. E. Hesler, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, Inc.

Mr. 8. Roetger, Georgia Public Service Commission Ms. 8. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Batch BIngham

U.S. Nuclear Regulatory Commission ND-20-0913 Enclosure Page 1 of 3 Southern Nuclear Operating Company ND-20-0913 Enclosure Vogtle Electric Generating Plant(VEGP) Unit 3 Completion of ITAAC C.2.6.09.02[Index Number 659]

U.S. Nuclear Regulatory Commission ND-20-0913 Enclosure Page 2 of 3 ITAAC Statement Design Commitment

2. Physical barriers for the protected area perimeter are not part of vital area barriers.

Inspections/Tests/Analvses An inspection of the protected area perimeter barrier will be performed.

Acceptance Criteria Physical barriers at the perimeter of the protected area are separated from any other barrier designated as a vital area barrier.

ITAAC Determination Basis An inspection of the VEGP Unit 3 protected area perimeter barrier was performed to verify that physical barriers at the perimeter of the Unit 3 protected area are separated from any other Unit 3 barrier designated as a vital area barrier and satisfy the applicable protected area perimeter physical barrier physical separation requirements of the VEGP Unit 3 and Unit 4 Physical Security Plan associated with 10 CFR 73.55(e)(8)(i)(C). The VEGP Unit 3 Plant Security System ITAACs only cover the Unit 3 plant security system design commitment scope.

The inspection was performed per Principal Closure Document SV3-SES-ITR-800659 (Reference 1) and involved a review of approved construction drawings and performance of a walkdown to verify that the Unit 3 protected area perimeter physical barriers are physically separated from Unit 3 vital area barriers.

The results of the inspection are documented in Reference 1 and verify that the Unit 3 physical barriers at the perimeter of the protected area are separated from any other Unit 3 barrier designated as a vital area barrier.

Reference 1 is available for NRC inspection as part of the Unit 3 ITAAC C.2.6.09.02 Completion Package (Reference 2).

ITAAC Finding Review In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company(SNC) performed a review of all findings pertaining to the subject ITAAC and associated corrective actions. This review found there are no relevant ITAAC findings associated with this ITAAC. The ITAAC completion review is documented in the ITAAC Completion Package for ITAAC C.2.6.09.02(Reference 2) and is available for NRC review.

ITAAC Completion Statement Based on the above information, SNC hereby notifies the NRC that ITAAC C.2.6.09.02 was performed for VEGP Unit 3 and that the prescribed acceptance criteria were met.

Systems, structures, and components verified as part of this ITAAC are being maintained in their as-designed, ITAAC compliant condition in accordance with approved plant programs and procedures.

U.S. Nuclear Regulatory Commission ND-20-0913 Enclosure Page 3 of 3 References ^available for NRG inspection)

1. SV3-SES-ITR-800659, Rev. 0,"Unit 3 ITAAC 659 Walkdown Inspection: ITAAC C.2.6.09.02"
2. C.2.6.09.02-U3-CP-Rev0, ITAAC Completion Package