ND-20-0283, ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.ix (Index Number 61)
| ML20090C266 | |
| Person / Time | |
|---|---|
| Site: | Vogtle |
| Issue date: | 03/27/2020 |
| From: | Yox M Southern Nuclear Operating Co |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| ND-20-0283 | |
| Download: ML20090C266 (6) | |
Text
,
Michael J. Vox 7825 River Road
^
Southern Nuclear Regulatory Affairs Director Waynesboro, GA 30830 Vogtle 3 & 4 706-848-6459 tel MAR 2 7 2020 Docket Nos.: 52-026 U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 ND-20-0283 10CFR 52.99(c)(1)
Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 4 ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.ix flndex Number 611 Ladies and Gentlemen:
In accordance with 10 CFR 52.99(c)(1), the purpose of this letter is to notify the Nuclear Regulatory Commission (NRC) of the completion of Vogtle Electric Generating Plant (VEGP) Unit 4 Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 2.1.02.12a.ix [Index Number 61] for the verification that the referenced Item OSd.iv of Table 2.1.2-4 determines the effective flow area through each stage 1 Automatic Depressurization System (ADS) valve is >4.6 in^ and each stage 2 and 3 ADS valve is >16 in^. The closure process for this ITAAC is based on the guidance described in NEI 08-01, "Industry Guideline for the ITAAC Closure Process under 10 CFR Part 52,"
which was endorsed by the NRC in Regulatory Guide 1.215.
This letter contains no new NRC regulatory commitments. Southern Nuclear Operating Company (SNC) requests NRC staff confirmation of this determination and publication of the required notice in the Federal Register per 10 CFR 52.99.
If there are any questions, please contact Tom Petrak at 706-848-1575.
Respectfully submitted, I
Michael J. Vox Regulatory Affairs Director Vogtle 3 & 4
Enclosure:
Vogtle Electric Generating Plant (VEGP) Unit 4 Completion of ITAAC 2.1.02.12a.ix [Index Number 61]
MJY/WLP/sfr
U.S. Nuclear Regulatory Commission ND-20-0283 Page 2 of 3 To:
Southern Nuclear Operating Company/Georgia Power Company Mr. Peter P. Sena III (w/o enclosures)
Mr. D. L. McKinney (w/o enclosures)
Mr. M. D. Meier (w/o enclosures)
Mr. D. H. Jones (w/o enclosures)
Mr. G. Chick Mr. M. Page Mr. P. Martino Mr. M. J. Yox Mr. A. S. Parton Ms. K. A. Roberts Mr. T. G. Petrak Mr. C. T. Defnall Mr. C. E. Morrow Mr. J. L. Hughes Mr. S. Leighty Ms. A. C. Chamberlain Mr. J. C. Haswell Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc; Nuclear Reaulatorv Commission M
M M
Ms. S. E. Temple M
M M
M Ms. N. C. Coovert M
M M
M W. Jones (w/o enclosures)
C. P. Patel G. J. Khouri N. D. Karlovich A. Lerch C. J. Even B. J. Kemker C. Welch J. Gaslevic V. Hall G. Armstrong Ms. T. Lamb Mr. M. Webb Mr. T. Fredette Mr. C. Weber Mr. S. Smith Mr. C. Santos Mrs. M. Bailey Mr. S. Rose Mr. B. Davis Mr. J. Vasquez Mr. J. Eargle Ms. K. Carrington Mr. P. Heher Mr. M. King Mr. E. Davidson
U.S. Nuclear Regulatory Commission ND-20-0283 Page 3 of 3 Qqlethorpe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. 8. M. Jackson Dalton Utilities Mr. T. Bundros Westinahouse Electric Company. LLC Dr. L. OrlanI (w/o enclosures)
Mr. D. C. Durham (w/o enclosures)
Mr. M. M. CorlettI Mr. Z. 8. Harper Mr. J. L. Coward Other Mr. J. E. Hesler, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.
Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, inc.
Mr. 8. Roetger, Georgia Public Sen/ice Commission Ms. 8. W. Kernlzan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Baich Bingham
U.S. Nuclear Regulatory Commission ND-20-0283 Enclosure Page 1 of 3 Southern Nuclear Operating Company ND-20-0283 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 4 Completion of ITAAC 2.1.02.12a.ix [Index Number 61]
U.S. Nuclear Regulatory Commission ND-20-0283 Enclosure Page 2 of 3 ITAAC Statement Design Commitment 12a) The automatic depressurization valves identified in Table 2.1.2-1 perform an active safety-related function to change position as indicated in the table.
Inspections. Tests. Analvses:
ix) See item S.d.iv in this table.
Acceptance Criteria:
ix) See item S.d.iv in this table.
ITAAC Determination Basis This Inspection, Test, Analyses and Acceptance Criteria (ITAAC) Design Commitment is shown to be met by reference to ITAAC 2.1.02.08d.iv in Vogtle Unit 4 Combined License (COL)
Appendix C, Table 2.1.2-4. The referenced Item Sd.iv of Table 2.1.2-4 determines the effective flow area through each stage 1 Automatic Depressurization System (ADS) valve is >4.6 in^ and each stage 2 and 3 ADS valve is >16 in^.
The ITAAC closure notification (ICN) letter (Reference 1) summarizes the methodology for conducting the Inspections, Tests, Analyses (ITA), and the results that demonstrate that the acceptance criteria were met. This ICN has been submitted to the NRC and the supporting ITAAC closure activities are complete.
The records (Tests, Reports, Completed Procedures, Completed Analyses, etc.) that form the ITAAC determination basis are referenced in the ICN for Item 8d.iv of Table 2.1.2-4.
ITAAC Finding Review In accordance with plant procedures for ITAAC completion. Southern Nuclear Operating Company (SNC) performed a review of all ITAAC findings pertaining to the subject ITAAC and associated corrective actions. This review found that there are no relevant ITAAC findings associated with this ITAAC. The ITAAC completion review document number is included in the Vogtle Unit 4 ITAAC Completion Package for ITAAC 2.1.02.12a.ix (Reference 2) and is available for NRC inspection.
U.S. Nuclear Regulatory Commission ND-20-0283 Enclosure Page 3 of 3 ITAAC Completion Statement Based on the above information, SNC hereby notifies the NRG that ITAAC 2.1.02.12a.ix was performed for VEGP Unit 4 and that the prescribed acceptance criteria are met.
Systems, structures, and components verified as part of this ITAAC are being maintained in their as-designed, ITAAC compliant condition in accordance with approved plant programs and procedures.
References (available for NRG inspection)
- 1. ND-20-0281, "Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 4 ITAAC Closure Notification on Completion of ITAAC 2.1.02.08d.iv [Index Number 35]"
- 2. 2.1.02.12a.ix-U4-CP-Rev0, ITAAC Completion Package