ND-19-0986, Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.6.06.01.i (Index Number 637)

From kanterella
(Redirected from ND-19-0986)
Jump to navigation Jump to search
Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.6.06.01.i (Index Number 637)
ML19267A221
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 09/24/2019
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of New Reactors
References
ITAAC 2.6.06.01.i, ND-19-0986
Download: ML19267A221 (6)


Text

^Southern NucIear Michael J. Yox Regulatory Affairs Director 7825 River Road Waynesboro, GA 30830 Vogtle 3 & 4 706-848-6459 SEP 2 <1 2019 Docket Nos.;52-025 52-026 ND-19-0986 10 CFR 52.99(c)(3)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 and Unit 4 Notice of Uncompleted ITAAC 225-davs Prior to initial Fuel Load item 2.6.06.01.1 [index Number 6371 Ladies and Gentlemen:

Pursuant to 10 CFR 52.99(c)(3), Southern Nuclear Operating Company hereby notifies the NRC that as of Sept 20, 2019, Vogtle Electric Generating Plant(VEGP) Unit 3 and Unit 4 Uncompleted Inspections Tests Analyses and Acceptance Criteria (ITAAC) Item 2.6.06.01.1

[Index Number 637] has not been completed greater than 225-days prior to initial fuel load. The Enclosure describes the plan for completing ITAAC 2.6.06.01.1 [Index Number 637]. Southern Nuclear Operating Company will, at a later date, provide additional notifications for ITAAC that have not been completed 225-days prior to initial fuel load.

This notification is informed by the guidance described in NEI-08-01, Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52, which was endorsed by the NRC in Regulatory Guide 1.215. In accordance with NEI 08-01, this notification includes ITAAC for which required inspections, tests, or analyses have not been performed or have been only partially completed.

All ITAAC will be fully completed and all Section 52.99(c)(1) ITAAC Closure Notifications will be submitted to NRC to support the Commission finding that all acceptance criteria are met prior to plant operation, as required by 10 CFR 52.103(g).

This letter contains no new NRC regulatory commitments.

If there are any questions, please contact Tom Petrak at 706-848-1575.

Respectfully submitted Michael J. Yox Regulatory Affairs Director Vogtle 3 & 4

Enclosure:

Vogtle Electric Generating Plant(VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 2.6.06.01.1 [Index Number 637]

MJY/KM/sfr

U.S. Nuclear Regulatory Commission ND-19-0986 Page 2 of 3 To:

Southern Nuclear Operating Company/ Georgia Power Company Mr. Peter P. Sena III (w/o enclosures)

Mr. D. L. McKinney (w/o enclosures)

Mr. M. D. Meier (w/o enclosures)

Mr. D. H. Jones(w/o enclosures)

Mr. G. Chick Mr. M. Page Mr. M. J. Yox Mr. A. S. Parton Ms. K. A. Roberts Mr. T. G. Petrak Mr. C. T. Defnall Mr. C. E. Morrow Mr. J. L. Hughes Ms. K. M. Stacy Ms. A. C. Chamberlain Mr. J. C. Haswell Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc:

Nuclear Regulatory Commission Mr. W.Jones(w/o enclosures)

Mr. F. D. Brown Mr. C. P. Patel Mr. G. J. Khouri Ms. S. E. Temple Mr. N. D. Karlovich Mr. A. Lerch Mr. C. J. Even Mr. B. J. Kemker Ms. N. C. Coovert Mr. C. Welch Mr. J. Gaslevic Mr. V. Hall Mr. G. Armstrong Ms. T. Lamb Mr. M. Webb Mr. T. Fredette Mr. C. Weber Mr. S. Smith Oalethorpe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen

U.S. Nuclear Regulatory Commission ND-19-0986 Page 3 of 3 Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. 8. M. Jackson Dalton Utilities Mr. T. Bundros Westinqhouse Eiectric Company. LLC Dr. L. Oriani (w/o enclosures)

Mr. D. 0. Durham (w/o enclosures)

Mr. M. M. Corletti Ms. L. G. Iller Mr. Z. 8. Harper Mr. J. L. Coward Other Mr. J. E. Hesler, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, inc.

Mr. 8. Roetger, Georgia Public Service Commission Ms. 8. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Baich Bingham

U.S. Nuclear Regulatory Commission ND-19-0986 Enclosure Page 1 of 3 Southern Nuclear Operating Company ND-19-0986 Enclosure Vogtle Electric Generating Plant(VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 2.6.06.01.1 [Index Number 637]

U.S. Nuclear Regulatory Commission ND-19-0986 Enclosure Page 2 of 3 ITAAC Statement Design Commitment

1. The EGS provides an electrical grounding system for: (1) instrument/computer grounding; (2) electrical system grounding of the neutral points of the main generator, main step-up transformers, auxiliary transformers, load center transformers, auxiliary and onsite standby diesel generators; and (3) equipment grounding of equipment enclosures, metal structures, metallic tanks, ground bus of switchgear assemblies, load centers, motor control centers, and control cabinets. Lightning protection is provided for exposed structures and buildings housing safety-related and fire protection equipment. Each grounding system and lightning protection system is grounded to the station grounding grid.

Inspections/Tests/Analvses i) An inspection for the instrument/computer grounding system connection to the station grounding grid will be performed.

11) An inspection for the electrical system grounding connection to the station grounding grid will be performed.

ill) An inspection for the equipment grounding system connection to the station grounding grid will be performed.

iv) An inspection for the lightning protection system connection to the station grounding grid will be performed.

Acceptance Criteria i) A connection exists between the instrument/computer grounding system and the station grounding grid.

ii) A connection exists between the electrical system grounding and the station grounding grid.

iii) A connection exists between the equipment grounding system and the station grounding grid.

iv) A connection exists between the lightning protection system and the station grounding grid.

U.S. Nuclear Regulatory Commission ND-19-0986 Enclosure Page 3 of 3 ITAAC Completion Description The EGS provides an electrical grounding system for four grounding subsystems:(1)

Instrument/computer grounding;(2) electrical system grounding of the neutral points of the main generator, main step-up transformers, auxiliary transformers, load center transformers, and onslte standby diesel generators;(3) equipment grounding of equipment enclosures, metal structures, metallic tanks, ground bus of switchgear assemblies, load centers, motor control centers, and control cabinets and (4) Lightning protection Is provided for exposed structures and buildings housing safety-related and fire protection equipment. Each grounding system and lightning protection system Is grounded to the station grounding grid.

The connections to the station grounding grid for the four grounding subsections are Identified In Table 1 of drawing SV3-0000-EG-003 and SV4-0000-EG-003(References 1 and 2). Each connection Is uniquely Identified In the plan drawings. The connections to the station grounding grid are exothermic and Installed In accordance with the project specification. Each connection Is Inspected and documented In accordance with 26139-000-4MP-T81C-N3307(Reference 3).

The results of the Inspection performed at each connection to the station grounding grid for the four grounding subsections are Identified In SV3-EGS-ITR-800637 and SV4-EGS-ITR-800637 (References 4 and 5) and confirm;(1) a connection exists between the Instrument/computer grounding system and the station grounding grid;(2) a connection exists between the electrical system grounding and the station grounding grid;(3) a connection exists between the equipment grounding system and the station grounding grid, and (4) a connection exists between the lightning protection system and the station grounding grid.

List of ITAAC Findings In accordance with plant procedures for ITAAC completion. Southern Nuclear Operating Company(SNC) performed a review of all findings pertaining to the subject ITAAC and associated corrective actions. This review found there are no relevant ITAAC findings associated with this ITAAC.

References(available for NRG inspection)

1. SV3-0000-EG-003-Rev X,"Grounding Plan Nuclear Island Building"
2. SV4-0000-EG-003-Rev X,"Grounding Plan Nuclear Island Building"
3. 26139-000-4MP-T81C-N3307, Rev X,"Grounding Installation Inspection Record"
4. SV3-EGS-ITR-800637-Rev X,"EGS Inspection Technical Report"
5. SV4-EGS-ITR-800637-Rev X,"EGS Inspection Technical Report"
6. 2.6.06.01.l-U3-CP-Rev 0, ITAAC Completion Package
7. 2.6.06.01.l-U4-CP-Rev 0, ITAAC Completion Package
8. NEI 08-01,"Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52"