ND-19-0525, Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.7.05.02.i (Index Number 719)

From kanterella
(Redirected from ND-19-0525)
Jump to navigation Jump to search
Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.7.05.02.i (Index Number 719)
ML19122A098
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 05/01/2019
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of New Reactors
References
ND-19-0525
Download: ML19122A098 (9)


Text

^ ^ .I I Michael J. Vox 7825 River Road

^OULn0rn NUClSdr Regulatory Affairs Director Waynesboro, GA 30830 Vogtle 3 & 4 706-848-6459 tel MAY 0 1 2019 Docket Nos.: 52-025 52-026 ND-19-0525 10CFR 52.99(c)(3)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 and Unit 4 Notice of Uncompleted ITAAC 225-davs Prior to Initial Fuel Load Item 2.7.05.02.1 [Index Number 7191 Ladies and Gentlemen:

Pursuant to 10 CFR 52.99(c)(3), Southern Nuclear Operating Company hereby notifies the NRC that as of April 25, 2019, Vogtle Electric Generating Plant(VEGP) Unit 3 and Unit 4 Uncompleted Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 2.7.05.02.1 [Index Number 719]

has not been completed greater than 225-days prior to initial fuel load. The Enclosure describes the plan for completing this ITAAC. Southern Nuclear Operating Company will, at a later date, provide additional notifications for ITAAC that have not been completed 225-days prior to initial fuel load.

This notification is informed by the guidance described in NEI 08-01, Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52, which was endorsed by the NRC in Regulatory Guide 1.215. In accordance with NEI 08-01, this notification includes ITAAC for which required inspections, tests, or analyses have not been performed or have been only partially completed. All ITAAC will be fully completed and all Section 52.99(c)(1) ITAAC Closure Notifications will be submitted to NRC to support the Commission finding that all acceptance criteria are met prior to plant operation, as required by 10 CFR 52.103(g).

This letter contains no new NRC regulatory commitments.

If there are any questions, please contact Tom Petrak at 706-848-1575.

Respectfully submitted.

m Michael J. Vox" Regulatory Affairs Director Vogtle 3 & 4

Enclosure:

Vogtle Electric Generating Plant(VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 2.7.05.02.1 [Index Number 719]

MJY/DLW/sfr

U.S. Nuclear Regulatory Commission ND-19-0525 Enclosure Page 2 of 6 To:

Southern Nuclear Operating Company/ Georgia Power Company Mr. D. A. Bost(w/o enclosures)

Mr. D. L. McKinney(w/o enclosures)

Mr. M. D. Meier (w/o enclosures)

Mr. D. H. Jones(w/o enclosures)

Mr. J. B. Klecha Mr. G. Chick Mr. M. J. Vox Mr. A. 8. Parton Ms. K. A. Roberts Mr. T. G. Petrak Mr. W. A. Sparkman Mr. C. T. Defnall Mr. C. E. Morrow Mr. J. L. Hughes Ms. K. M. Stacy Ms. A. C. Chamberlain Mr. J. C. Haswell Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc:

Nuclear Reaulatorv Commission Mr. W.Jones(w/o enclosures)

Mr. F. D. Brown Ms. J. M. Heisserer Mr. C. P. Patel Mr. G. J. Khouri Ms. S. E. Temple Mr. N. D. Karlovich Mr. A. Lerch Mr. C. J. Even Mr. B. J. Kemker Ms. N. C. Coovert Mr. C. Welch Mr. I. Cozens Mr. J. Gaslevic Mr. V. Hall Oalethorpe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen Municipal Electric Authorltv of Georgia Mr. J. E. Fuller Mr. S. M. Jackson Dalton Utilities Mr. T. Bundros

U.S. Nuclear Regulatory Commission ND-19-0525 Enclosure Page 3of 6 Westinqhouse Electric Company. LLC Dr. L. Orlani (w/o enclosures)

Mr. D. 0. Durham (w/o enclosures)

Mr. M. M. Corletti Ms. L. G. Iller Ms. J. Monahan Mr. J. L. Coward Other Mr. J. E. Hesler, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, Inc.

Mr. 8. Roetger, Georgia Public Service Commission Ms. 8. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Balch BIngham

U.S. Nuclear Regulatory Commission ND-19-0525 Enclosure Page 1 of 6 Southern Nuclear Operating Company ND-19-0525 Enclosure Vogtle Electric Generating Plant(VEGP)Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 2.7.05.02.1 [Index Number 719]

U.S. Nuclear Regulatory Commission ND-19-0525 Enclosure Page 2 of 6 ITAAC Statement Desion Commitment

2. The VAS maintains each building area at a slightly negative pressure relative to the atmosphere or adjacent clean plant areas.
3. Displays of the parameters identified in Table 2.7.5-1 can be retrieved in the MCR.

Inspections/Tests/Analvses i) Testing will be performed to confirm that the VAS maintains each building at a slightly negative pressure when operating all VAS supply AHUs and all VAS exhaust fans.

ii) Testing will be performed to confirm the ventilation flow rate through the auxiliary building fuel handling and rail car bay/solid radwaste system areas when operating all VAS supply AHUs and all VAS exhaust fans.

iii) Testing will be performed to confirm the auxiliary building radiologically controlled area ventilation flow rate when operating all VAS supply AHUs and all VAS exhaust fans.

Inspection will be performed for retrievability of the parameters in the MCR.

Acceptance Criteria i) The time average pressure differential in the served areas of the annex,fuel handling and radiologically controlled auxiliary buildings as measured by each of the instruments identified in Table 2.7.5-1 is negative.

ii) A report exists and concludes that the calculated exhaust flow rate based on the measured flow rates is greater than or equal to 10,710 cfm.

iii) A report exists and concludes that the calculated exhaust flow rate based on the measured flow rates is greater than or equal to 22,500 cfm.

The displays identified in Table 2.7.5-1 can be retrieved in the MCR.

ITAAC Completion Description The subject ITAAC verifies that the time average pressure differential in the served areas of the annex, fuel handling and radiologically controlled auxiliary buildings as measured by each of the instruments identified in VEGP Combined License(COL)Appendix C Table 2.7.5-1 (Attachment A) is negative and that displays of the parameters identified in Attachment A can be retrieved in the Main Control Room (MCR). Testing is performed to verify that a report exists and concludes that the calculated exhaust flow rate based on the measured flow rates is greater than or equal to 10,710 cfm through the auxiliary building fuel handling and rail car bay/solid radwaste system areas when operating all Radiologically Controlled Area Ventilation System (VAS)supply Air Handling Units(AHUs) and all VAS exhaust fans, and that a report exists and concludes that the calculated exhaust flow rate based on the measured flow rates is greater than or equal to

U.S. Nuclear Regulatory Commission ND-19-0525 Enclosure Page 3 of 6 22,500 cfm through the auxiliary building radiologically controlled area when operating all VAS supply AHUs and all VAS exhaust fans.

i) The time average pressure differential in the served areas of the annex,fuel handlino and radiologically controlled auxiliary buildinos as measured bv each of the instruments identified in Table 2.7.5-1 is neoatiye.

Testing is performed in accordance with preoperational test procedures 3-VAS-ITPP-501 and 4-VAS-ITPP-501 (References 1 and 2)to confirm the time ayerage pressure differential in the seryed areas of the annex,fuel handling and radiologically controlled auxiliary buildings as measured by each of the instruments identified in Attachment A is negatiye.

Testing begins by yerifying the Annex/Auxiliary Building Ventilation System, the Fuel Handling Area(FHA) Ventilation System, unit heaters, unit coolers, duct heaters and humidifiers are all in seryice. An Oyation trend is established using the instruments in Attachment A and the test is run for a minimum of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. The calculated ayerage yalue for each instrument is recorded in Reference 1 and 2, and yerified to meet the acceptance criteria.

The results of the testing confirm that the time ayerage pressure differential in the seryed areas of the annex,fuel handling and radiologically controlled auxiliary buildings as measured by each of the instruments identified in Table 2.7.5-1 is negatiye for Unit 3 and Unit 4.

ii) A report exists and concludes that the calculated exhaust flow rate based on the measured flow rates is greater than or eoual to 10.710 cfm.

Testing is performed in accordance with preoperational test procedures 3-VAS-ITPP-501 and 4-VAS-ITPP-501 (References 1 and 2)to confirm that the calculated exhaust flow rate based on the measured flow rates through the auxiliary building fuel handling and rail car bay/solid radwaste system areas when operating all VAS supply AHUs and all VAS exhaust fans is greater than or equal to 10,710 cfm.

Testing begins by yerifying the Annex/Auxiliary Building Ventilation System, the FHA Ventilation System, unit heaters, unit coolers, duct heaters and humidifiers are all in seryice. The total exhaust flow yalues are determined during the system flow balance testing and documented in the flow balance test report of Reference 1 and 2.

The exhaust flow rate for Unit 3 is XX,XXX cfm and the exhaust flow rate for Unit 4 is YY,YYY cfm which confirms that a report exists and concludes that the calculated exhaust flow rate based on the measured flow rates is greater than or equal to 10,710 cfm.

lib A reoort exists and concludes that the calculated exhaust flow rate based on the measured flow rates is greater than or eoual to 22.500 cfm.

Testing is performed in accordance with preoperational test procedures 3-VAS-ITPP-501 and 4-VAS-ITPP-501 (References 1 and 2)to confirm that the calculated exhaust flow rate based on the measured flow rates through the auxiliary building radiologically controlled area when operating all VAS supply AHUs and all VAS exhaust fans is greater than or equal to 22,500 cfm.

U.S. Nuclear Regulatory Commission ND-19-0525 Enclosure Page 4 of 6 Testing begins by verifying the Annex/Auxiliary Building Ventilation System, the FHA Ventilation System, unit heaters, unit coolers, duct heaters and humidifiers are all in service. The total exhaust flow values are determined during the system flow balance testing and documented in the flow balance test report of Reference 1 and 2.

The exhaust flow rate for Unit 3 is XX,XXX cfm and the exhaust flow rate for Unit 4 is YY,YYY cfm which confirms that a report exists and concludes that the calculated exhaust flow rate based on the measured flow rates is greater than or equal to 22,500 cfm.

The disDiavs identified in Table 2.7.5-1 can be retrieved in the MGR.

An inspection is performed to verify the retrievability of the Vogtie Electric Generating Plant (VEGP) Unit 3 and Unit 4 plant parameters in the Main Control Room (MCR). The inspection for retrievability confirms that the displays of the parameters identified in Combined License(COL)

Appendix C Table 2.7.5-1 (Attachment A)can be retrieved in the MCR.

The inspection is performed in accordance with the Unit 3 and Unit 4 component test package work orders(References 3 and 4)and visually confirms that when each of the displays of parameters identified in Attachment A is summoned at an MCR workstation, the summoned plant parameter appears on a display monitor at that MCR workstation.

The results from References 3 and 4 confirm that the Unit 3 and Unit 4 plant parameter displays identified in Table 2.7.5-1 can be retrieved in the MCR.

The results of the testing and inspections confirm that for Unit 3 and Unit 4, the time average pressure differential in the served areas of the annex,fuel handling and radiologically controlled auxiliary buildings as measured by each of the instruments identified in Table 2.7.5-1 is negative, that a report exists and concludes that the calculated exhaust flow rate based on the measured flow rates is greater than or equal to 10,710 cfm, that a report exists and concludes that the calculated exhaust flow rate based on the measured flow rates is greater than or equal to 22,500 cfm, and that the displays identified in Table 2.7.5-1 can be retrieved in the MCR.

References 1 thru 4 are availabie for NRC inspection as part of Unit 3 and Unit 4 ITAAC 2.7.05.02.i Completion Packages(Reference 5 and 6).

List of ITAAC Findings In accordance with plant procedures for ITAAC completion. Southern Nuclear Operating Company(SNC) performed a review of all findings pertaining to the subject ITAAC and associated corrective actions. This review found there are no relevant ITAAC findings associated with this ITAAC.

U.S. Nuclear Regulatory Commission ND-19-0525 Enclosure Page 5 of 6 References(available for NRG inspection)

1. 3-VAS-ITPP-501,"Radiologlcally Controlled Area Ventilation System Preoperational tesf
2. 4-VAS-ITPP-501,"Radiologically Controlled Area Ventilation System Preoperational tesf
3. SNC922113,"Radiologically Controlled Area Ventilation System Display Verifications-ITAAC: SV3-2.7.05.02.i Item 3"
4. SNCYYYYYY,"Radiologically Controlled Area Ventilation System Display Verifications -

ITAAC: SV4-2.7.05.02.i Item 3"

5. 2.7.05.02.i-U3-CP-Rev0, ITAAC Completion Package
6. 2.7.05.02.i-U4-CP-Rev0, ITAAC Completion Package
7. NEI 08-01,"Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52"

U.S. Nuclear Regulatory Commission ND-19-0525 Enclosure Page6 of 6 Attachment A Excerpt from Unit 3COL Appendix C Table 2.7.5-1*

UNIT Equipment* Tag No

  • Display* Average Pressure 3 *Fuel Handling Area Pressure Differential *VAS-030 *Yes -O.XX in wg Indicator 3 *Annex Building Pressure Differential *VAS-032 *Yes -O.XX in wg Indicator 3 *Auxiliary Building Pressure Differential *VAS-033 *Yes -O.XX in wg Indicator 3 *Auxiliary Building Pressure Differential *VAS-034 *Yes -O.XX in wg Indicator 4 *Fuel Handling Area Pressure Differential *VAS-030 *Yes -O.XX in wg Indicator 4 *Annex Building Pressure Differential *VAS-032 *Yes -O.XX in wg Indicator 4 *Auxiliary Building Pressure Differential *VAS-033 *Yes -O.XX in wg Indicator 4 *Auxiliary Building Pressure Differential *VAS-034 *Yes -O.XX in wg Indicator