ND-19-0120, Unit 4 - Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.3.00.05b (Index Number 785)

From kanterella
(Redirected from ND-19-0120)
Jump to navigation Jump to search
Unit 4 - Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.3.00.05b (Index Number 785)
ML19056A447
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 02/25/2019
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of New Reactors
References
ND-19-0120
Download: ML19056A447 (7)


Text

Southern Nuclear FEB 2 5 2019 Michael J. Yox Regulatory Affairs Director Vogtle 3 & 4 7825 River Road Waynesboro, GA 30830 706-848-6459 tel Docket Nos.: 52-025 52-026 U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 ND-19-0120 10CFR 52.99(c)(3)

Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 and Unit 4 Notice of Uncompleted ITAAC 225-davs Prior to Initial Fuel Load Item 3.3.00.05b [Index Number 7851 Ladies and Gentlemen:

Pursuant to 10 CFR 52.99(c)(3), Southern Nuclear Operating Company hereby notifies the NRC that as of February 18, 2019, Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Uncompleted Inspection, Test, Analysis, and Acceptance Criteria (ITAAC) Item 3.3.00.05b

[Index Number 785] has not been completed greater than 225-days prior to initial fuel load. The Enclosure describes the plan for completing ITAAC 3.3.00.05b [Index Number 785]. Southern Nuclear Operating Company will at a later date provide additional notifications for ITAAC that have not been completed 225-days prior to initial fuel load.

This notification is informed by the guidance described in NEI-08-01, Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52, which was endorsed by the NRC in Regulatory Guide 1.215. In accordance with NEI 08-01, this notification includes ITAAC for which required inspections, tests, or analyses have not been performed or have been only partially completed.

All ITAAC will be fully completed and all Section 52.99(c)(1) ITAAC Closure Notifications will be submitted to NRC to support the Commission finding that all acceptance criteria are met prior to plant operation, as required by 10 CFR 52.103(g).

This letter contains no new NRC regulatory commitments.

If there are any questions, please contact Tom Petrak at 706-848-1575.

Respectfully submitted.

Michael J. Yox Regulatory Affairs Director Vogtle 3&4 Enclosure; MJY/GJUsfr Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 3.3.00.05b [Index Number 785]

U.S. Nuclear Regulatory Commission ND-19-0120 Page 2 of 3 To:

Southern Nuclear Operating ComDanv/ Georgia Power Company Mr. D. A. Bost (w/o enclosures)

Mr. D. L. McKinney (w/o enclosures)

Mr. M. D. Meier (w/o enclosures)

Mr. D. H. Jones (w/o enclosures)

Mr. J. B. Klecha Mr. G. Chick Mr. M. J. Yox Mr. A. 8. Parton Ms. K. A. Roberts Mr. T. G. Petrak Mr. W. A. Sparkman Mr. C. T. Defnall Mr. C. E. Morrow Mr. J. L. Hughes Ms. K. M. Stacy Ms. A. C. Chamberlain Mr. J. C. Haswell Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc:

Nuclear Reoulatorv Commission Mr. W. Jones (w/o enclosures)

Mr. F. D. Brown Ms. J. M. Heisserer Mr. C. P. Patel Mr. G. J. Khouri Ms. S. E. Temple Mr. N. D. Karlovich Mr. A. Lerch Mr. C. J. Even Mr. B. J. Kemker Ms. N. C. Coovert Mr. C. Welch Mr. I. Cozens Mr. J. Gaslevic Mr. V. Hall Qqiethoroe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen Municipai Eiectric Authoritv of Georgia Mr. J. E. Fuller Mr. S. M. Jackson

U.S. Nuclear Regulatory Commission ND-19-0120 Page 3 of 3 Dalton Utilities Mr. T. Bundros Westinahouse Electric Company. LLC Dr. L. Orlani (w/o enclosures)

Mr. D. 0. Durham (w/o enclosures)

Mr. M. M. Corletti Ms. L. G.

Iller Ms. J. Monahan Mr. J. L. Coward Other Mr. J. E. Hosier, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, Inc.

Mr. 8. Roetger, Georgia Public Service Commission Ms. 8. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Balch BIngham

U.S. Nuclear Regulatory Commission ND-19-0120 Enclosure Page 1 of 4 Southern Nuclear Operating Company ND-19-0120 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC Item 3.3.00.05b [Index No. 785]

U.S. Nuclear Regulatory Commission ND-19-0120 Enclosure Page 2 of 4 ITAAC Statement Desion Commitment 5.b) The boundaries between rooms identified in Table 3.3-2 of the auxiliary building are designed to prevent flooding of rooms that contain safety-related equipment.

I nspections/T ests/Analvses An inspection of the auxiliary building rooms will be performed.

Acceptance Criteria A report exists that confirms floors and walls as identified in Table 3.3-2 have provisions to prevent flooding between rooms up to the maximum flood levels for each room defined in Table 3.3-2.

ITAAC Compietion Description An inspection of the boundaries between the rooms identified in Vogtle Electric Generating Plant (VEGP) Unit 3 & Unit 4 Combined License (COL) Appendix C Table 3.3-2 (Attachment A),

is performed to demonstrate that the boundaries between these rooms are designed to prevent flooding of rooms that contain safety-related equipment.

Inspections are performed of auxiliary building rooms to demonstrate that floors and walls as identified in Table 3.3-2 have provisions to prevent flooding between rooms up to the maximum flood levels for each room defined in COL Appendix C Table 3.3-2. An inspection plan is prepared to identify all openings and penetrations on the floors and walls up to the maximum flood levels of the rooms. Each as-built opening or penetration observed and measured to be below the corresponding maximum flood level is inspected to ensure that the openings and penetrations are sealed as specified in the design documents. A final walkdown of the floors and walls is performed to ensure that all openings and penetrations have been identified and inspected.

The inspection plan and results of the visual inspection of the floors and walls are documented in Unit 3 and Unit 4 inspection reports (References 1 and 2, respectively), and confirms floors and walls as identified on COL Appendix C Table 3.3-2 have provisions to prevent flooding between rooms up to the maximum flood levels for each room defined in COL Appendix C Table 3.3-2.

References 1 and 2 are available for NRC inspection as part of Unit 3 and Unit 4 ITAAC 3.3.00.05b Completion Packages (References 3 and 4, respectively).

List of ITAAC Findings In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company (SNC) performed a review of all ITAAC findings pertaining to the subject ITAAC and associated corrective actions. This review found that there are no relevant ITAAC findings associated with these ITAAC. The ITAAC completion review is documented in the ITAAC

U.S. Nuclear Regulatory Commission ND-19-0120 Enclosure Page 3 of 4 Completion Packages for ITAAC 3.3.00.05b for Unit 3 and Unit 4 (References 3 and 4 respectively) and are available for NRC review.

References (available for NRG inspection)

1.

Unit 3 Inspection Report ITAAC 3.3.00.05b [Index No. 785] (SV3-AA-BBB-###)

2.

Unit 4 Inspection Report ITAAC 3.3.00.05b [Index No. 785] (SV4-CC-DDD-###)

3.

3.3 00.05b-U3-CP-Rev 0, ITAAC Completion Package

4.

3.3 00.05b-U4-CP-Rev 0, ITAAC Completion Package

5.

NEI 08-01, "Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52"

U.S. Nuclear Regulatory Commission ND-19-0120 Enclosure Page 4 of 4 Attachment A COL Appendix C Table 3.3-2 Table 3.3-2 Nuclear Island Building Room Boundaries Required to Have Flood Barrier Floors and Walls Boundary/

Maximum Flood Level (Inches)

Between Room Number to Room Number Room with Postulated Flooding Source Adjacent Room Floor/36 12306 12211 Floor/3 12303 12203/12207 Floor/3 12313 12203/12207 Floor/1 12300 12201/12202/12207 12203/12204/12205 Floor/3 12312 12212 Wall/36 12306 12305 Floor/1 12401 12301/12302/12303 12312/12313 Wall/1 12401 12411/12412 Floor/36 12404 12304 Floor/4 12405 12305 Floor/36 12406 12306 Wall/36 12404 12401 Wall/30 12452 12421 Floor/3 12501 12401/12411/12412 Floor/3 12555 12421/12423/12422 Wall/168 12156 12111/12112 Wall/76.5 12158 12111 Wall/132 12258 12211/12212